Title: Demand Response Market Barriers: Canada
1Demand ResponseMarket BarriersCanada
- Ian H. Rowlands
- presentation to IEA DSM Task XIII
- 5th Experts Workshop
- 9-10 November 2005, Melbourne, Australia
2Purposes
- to offer an overview of the electricity systems
in Canada - to provide a more detailed summary of recent and
current developments in the province of Ontario - to highlight some key market barriers to
increased demand response in Ontario
3Electricity systems in Canada
Canada total 528 TWhr
North 1 TWhr
B.C. 60 TWhr
Sask./Man. 36 TWhr
Quebec 194 TWhr
Alberta 54 TWhr
Atlantic 38 TWhr
Ontario 145 TWhr
Electricity demand, 2003 source National Energy
Board, 2005
4Electricity systems in Canada
Canada total (generation by energy source),
2003 hydro 58.9 coal 18.5 nuclear
12.4 natural gas 5.9
North 57 oil
B.C. 84 hydro
Sask. 47 coal
Quebec 93 hydro
Man. 93 hydro
Alberta 54 coal
Atlantic 56 hydro
Ontario 32 nuclear
Electricity generating capacity, 2003 source
National Energy Board, 2005
5Electricity systems in Canada
Canadian Electricity Demand by Sector,
2001 source Canadian Electricity Association
6Electricity systems in Canada
- governance of the electricity systems
- under the terms of the Canadian constitution,
primarily a provincial responsibility - ownership structures
- some private (e.g,, Alberta, Nova Scotia)
- presence of markets
- some open (Alberta, Ontario, in particular)
7A focus on Ontario
- largest province in Canada
- 39 per cent of countrys population
- 40 per cent of economic activity
- second largest electricity system in Canada
- 2003 generating capacity of 30,457 MW
- 2003 electricity demand of 144,967 GWhr
- involvement in Task XIII
- representatives of the Ontario Power Authority
and the Ontario Energy Board as Task XIII
experts.
8Ontarios electricity system
Electricity demand, 2003 commercial
36.8 residential 34.4 industrial 28.8
Key statistics
Electricity generation, 2003 nuclear 41.3 hydro
24.0 coal 23.9 natural gas 9.0
source Natural Resources Canada
photo credit OPG
9Ontarios electricity system
- remained relatively unchanged for almost a
century - monopoly, somewhat vertically-integrated
- pace of change accelerated during mid-1990s
- after some delays, market opening in May 2002
- partial closing of the market in December 2002
- new government elected in October 2003
10Ontarios electricity system
- driving forces for change
- aging physical plant
- C4 billion, for example, needed in upgrades and
reinforcements for the provinces transmission
system over the next ten years (source ECSTF,
2004) - relatively little investment during recent period
of uncertainty - increasing demand, particularly summer peaks
- 1996-2004 average annual growth in total energy
consumption of 1.4 - 1996-2005 average annual growth in summer peak
demand of 2.2 (source IESO) - environmental concerns
- commitment to close coal-fired power stations by
2009
11Ontarios electricity system
- Power use sets record Blackout hits downtown
(28 June 2005) - Shortages aren't over, Energy Minister Duncan
says (22 July 2005) - Power dims in Ontario brownout (4
August 2005)
12Ontarios electricity system
9 of 10 peak demand periods recorded in Ontario
occurred during summer 2005
source Independent Electricity System Operator
(Ontario)
13Ontarios electricity system
source Independent Electricity System Operator
(Ontario)
14Ontarios electricity system
- current activities
- development of a conservation culture
- target for 5 reduction in peak load (1,350 MW)
by 2007 - renewable energy target 5 of electricity supply
by 2007, and 10 by 2010 - pilot programs of the Independent Electricity
System Operator
15Ontarios electricity system
- activities of the Ontario Power Authority
- is responsible for ensuring an adequate,
long-term supply of electricity in Ontario
(www.powerauthority.on.ca) - deliberations currently proceeding regarding
supply mix advice - requested by the Minister of Energy in May 2005
- report due back to the Minister by 1 December
16Ontarios electricity system
- some indication as to what lies ahead
- Energy Conservation Responsibility Act, 2005
- introduced on 3 November 2005
- provides the framework for the commitment to
install 800,000 smart meters in Ontario homes and
businesses by 2007, and to have them installed in
all homes and businesses by 2010 - capital cost for all consumers estimated at C1
billion (to be recovered through the rate base)
17Ontarios electricity system
Red Peak pricing 9.3 Blue Mid-peak pricing
6.4 White Off-peak pricing 2.9 All
weekends Off peak pricing
18Market barriers
- Low electricity prices, generally
source Natural Resources Canada
19Market barriers
- Low electricity prices, generally
Residential (retail) price of electricity, 2005,
US cents per kWhr
Wisconsin 9.96 /kWh
Minnesota 8.96 /kWh
Ontario 8.12 /kWh
Michigan 9.11 /kWh
New York 15.59 /kWh
Ohio 8.99 /kWh
Pennsylvania 10.51 /kWh
source Energy Information Administration
20Market barriers
- presently little incentive to act
- like a Tragedy of the Commons, the savings are
spread across all users - within communities
- within buildings (e.g., multi-unit complexes)
21Market barriers
- low understanding of electricity issues among
consumers - ignorance regarding resources used to generate
electricity
in the first place
What is the largest contributor to Ontarios
electricity supply at present? (n1,056)
22Market barriers
- low understanding of electricity issues among
consumers - bewilderment regarding electricity bills
- business owners, for example, do not understand
the difference between commodity (electricity)
charges and demand (delivery) charges
23Market barriers
- low understanding of how consumers will react to
different incentives - what are their decision-making processes all
about? - businesses focus only on bottom line?
- what is valued?
- citizens also interested in social good?
- what is valued?
24Market barriers
- potential market participants on the supply-side
are not given sufficient financial incentive - not all benefits are explicitly valued
- tangible, financial benefits that are created are
not passed on to the project proponent
25Market barriers
- significant transaction costs on the supply-side
- RFP process can be expensive in terms of time and
money - different layers of administrative demands
- dealing with more than 90 local distribution
companies across the province - discussions now underway on the development of
standard contracts
26Market barriers
- confidence in the future of the rules
- previous delays in market opening
- changes to the coal phase-out date
photo credits www.arisetech.com
27Summary and conclusions
- speakers contact details
- Ian Rowlands
- University of Waterloo
- irowland_at_fes.uwaterloo.ca
- 1-519-888-4567, ext. 2574