Title: IDEI, The economics of electricity markets
1IDEI, The economics of electricity markets
- Investment in transmission
- Issues for discussion
- Ignacio J. Pérez-Arriaga
- Comillas University (Madrid)
Toulouse, June 3, 2005
2Investment in transmissionWhich is the objective?
- Regulatory framework should be such that all
transmission facilities that meet a prescribed
social welfare efficiency criterion (which must
include economic implications of quality of
supply) are - built at optimal times
- properly operated maintained
- at minimum cost for its users
3Investment in transmissionIssues for discussion
- How can justified transmission investment needs
be identified? What is justified? Who
identifies? - How to achieve consistency between operation
investment criteria? Same decision maker? - How to incentivise building needed transmission
investment? Agents depend on regulatory framework - How to determine the beneficiaries of an
investment to make them pay for it? Pricing may
affect investment decisions
4The regulatory testWhat is a justified
investment?
- Investment optimality according to traditional
regulation - Invest in network assets only while the the
additional network investment cost is still
smaller than the additional saving in system
operation costs (generation costs, loss of
supply) - This definition is consistent with the one
adequate for a context of competition - Invest so that the net aggregated benefits (once
network charges are included) of all network
users (i.e. generators consumers) are
maximized - Technical reliability rules have to be met in any
case
5A useful property
- An economically justified network investment
under traditional network expansion rules - network investment cost lt savings in operation
costs - will increase the net benefit of
- Generators income from nodal prices operation
costs network charges - Consumers utility of electricity use cost of
purchasing electricity at nodal prices network
charges - if the residual network cost is allocated pro
rata of the economic benefits of each network user
6Investment in new facilitiesApproaches (the
regulatory context)
- System Operator proposes reinforcement plan, to
be authorized by regulator construction may be
assigned by a competitive auction - A private company is awarded the transmission
license and is regulated as a monopoly subject
to grid code remuneration based on some price
control scheme (e.g. RPI-X) - Coalitions of network users proposes
reinforcements, to be authorized by regulator
regulated remuneration of total costs
construction is assigned by competitive bidding - Risk investments same as above, but coalition
bears total costs regulated remuneration covers
partial costs - Merchant lines (remuneration based on market
value of their transmission services)
7Investment in new facilitiesApproaches (comments)
- SO Regulator May result in overinvestment if
regulator fails to set limits in the
authorization process - Private licensed company May result in
underinvestment unless very careful incentive
schemes are implemented - Coalitions of network users Only lines with
clear beneficiaries will be built. May be a
complement to 1 - Risk investments Same as 3, but more acute. Good
to promote investment in underdeveloped networks - Merchant lines Cannot be trusted to develop a
sound network, since transmission revenues from
nodal prices in a well developed network will
grossly under recover transmission costs. May be
a complement to 1 or 2
8Option 1System Operator Regulator
- Regularly, the System Operator must propose a
plan for reinforcements of the transmission
network - after taking into consideration (justified) any
proposals made by the network users - Regulatory authorities approve the plan
authorize construction of individual new
facilities - Construction, operation maintenance of each
facility are allocated in a competitive auction - pay as bid to winner
- limited duration of contract auction for the
next period? - set availability targets for each facility
penalties (credits) according to the actual
performance - May be complemented by options 3, 4 5
9Option 2 Private firm global regulated
remuneration
- A private company is awarded the transmission
license and regulated as a monopoly - Must follow prescribed design requirements (grid
code) - Incentives to meet performance targets (warning
separate clearly from incentives to System
Operator) - Global remuneration (RPI-X) for the complete
network, while taking into account - actual new investments
- economic lives depreciation of existing
investments - economic health of transmission company
- expected efficiency improvements
- Concern optimality of investments in general
will not be attained determining remuneration
becomes an art
10Option 3Users have the initiative (A B)
- Initiative of proposal of network reinforcements
corresponds to coalitions of network users - OPTION A coalition builds pays the
reinforcement, which needs authorization from
regulator - OPTION B after a quasi-judiciary process
(coalitions pro against, evaluation by system
operator) regulator decides whether reinforcement
is justified or not. - If justified, it is built under competitive
bidding - pay as bid to winner
- limited duration of license auction for the next
period - set availability targets penalties (credits)
according to performance - charge cost to all users with general allocation
method
11Option 4Users have the initiative (C)
- OPTION C risk investments
- Quasi-judicial process as in option B
- If the reinforcement is found justified
- the proprietary coalition is selected (a specific
auction procedure is followed) - assign construction by competitive bidding
- apply regulated tariffs (attenuated, according to
the line utilization) to all network users - financial rights on the congestion rents of the
reinforcement (firm transmission rights) are
given to its owners
12Option 5Merchant lines
- Basic idea Regulate the transmission activity as
any other competitive business ? merchant lines - Remuneration comes from congestion rents
- Network capacity may even be bid in a short-term
market (possible with DC lines) - Firm Transmission Rights (FTRs), may be seen not
only as a risk hedging mechanism, but also as an
incentive for investment - Difficulties
- insufficiency (in general) of market driven
revenues - High exposure to risk
- reliability lines
- potential for market power abuse
13Investment in transmissionIssues for discussion
- How can justified transmission investment needs
be identified? - How to achieve consistency between operation
investment criteria? - How to incentivise building needed transmission
investment? - How to determine the beneficiaries of an
investment to make them pay for it?
14How to achieve consistency between operation
investment criteria?
- SO Regulator No problem, use operation
criteria when simulating the system to decide on
investment - Private licensed company No problem, if there is
a suitable grid code to comply with - Coalitions of network users No guarantee
- Risk investments No guarantee
- Merchant lines No guarantee
15Investment in transmissionIssues for discussion
- How can justified transmission investment needs
be identified? - How to achieve consistency between operation
investment criteria? - How to incentivise building needed transmission
investment? - How to determine the beneficiaries of an
investment to make them pay for it?
16Objectives in transmission pricing
- To ensure that the transmission network charges
that are levied to the network users - recover the complete regulated costs of the
transmission network of each country/TSO or that
merchant lines (if any) are attractive
economically - send efficient economic signals
- in the short-term (for operation decisions)
- in the long-term (for investment location
decisions) - are non discriminatory
- are easy to understand implement, perceived
as fair
17Can pricing / remuneration provide right
incentives for network investment?
- Network users may receive signals that make them
to act so that the operation of the system is
efficient - losses
- congestions
- Network users may receive siting signals
commensurate with the incurred transmission costs - for siting new generators loads / retiring
existing ones - to promote new investments, in some regulatory
schemes - System Operators, transmission network planners
potential network investors may receive
adequate signals so that optimal network
investment happens or appropriate regulation
makes it happen
18Can pricing / remuneration provide right
incentives for network investment?
- Who are the network investors / planners? It
depends on the specific regulation, at national
or regional (multinational) levels - System Operators, with some degree of regulatory
supervision, either national or EU - Coalitions of network users, subject to
regulatory approval - Merchant investors, subject to regulatory
authorization - The regulatory treatment of the remuneration of a
new line the pricing access schemes depend on
the adopted approach
19Can pricing / remuneration provide right
incentives for network investment?
- Adequate remuneration of transmission depends on
who is really responsible for the development of
the network - If the transmission firm is active, (i.e takes
responsibility for network development) then the
remuneration must refer to an efficient well
adapted network performance-based economic
incentives to invest make sense - If the transmission firm is passive, (i.e does
not take responsibility for network development)
then the remuneration must refer to the actual
network incentives must basically depend on the
availability of the network equipment, although
mild incentives to improve operation can also
make sense
20Can pricing / remuneration provide right
incentives for network investment?
- Merchant investors will collect just congestion
rents (or their expected values, via capacity
contracts or firm transmission rights of some
kind) - then they cannot be trusted to build all the
required transmission infrastructure (maybe some,
if subject to the appropriate access pricing
conditions) - Coalitions of network users may promote, even
invest at some risk, in specific infrastructures,
but not in those whose benefit is widely
dispersed (probably the majority in well
developed networks)
21(continuation)
- ?There is a major role for regulated / planned
investment (use the EU market as an example) - presented by TSOs (individually or jointly)
belonging to a systematic plan - authorized by the involved regulators TSOs that
examine implications at EU level of the
reinforcements - included in the inter-TSO payment scheme, so the
costs are rightly shared among the users - ?Doors could be open for investment at risk
- who can exploit the existing incentives in
transmission pricing be subject to some
regulatory oversight, such as priority rules and
open access conditions
22Investment in transmissionIssues for discussion
- How can justified transmission investment needs
be identified? - How to achieve consistency between operation
investment criteria? - How to incentivise building needed transmission
investment? - How to determine the beneficiaries of an
investment to make them pay for it?
23A useful property (regarding beneficiaries)
- An economically justified network investment (for
instance, under traditional network expansion
rules - network investment cost lt savings in operation
costs) - will increase the net benefit of
- Generators income from nodal prices operation
costs network charges - Consumers utility of electricity use cost of
purchasing electricity network charges - if the residual network cost (trasnmission
cost minus any revenues from nodal prices) is
allocated pro rata of the economic benefits of
each network user
24The need to identify beneficiaries
- Basically no need for existing lines existing
network users - although adequate network charges may be relevant
for plants that are close to retirement - But sound economic signals are convenient /
necessary when the investment decision on new
generation projects may depend on transmission
charges / signals - Example 1 60.000 MW of proposed connection of
wind generators plus 50.000 of CCGT in Spain,
some requiring transmission expansion - Example 2 Decisions about investment-at-risk
versus planned investment in new lines for
distant generation projects in Peru
25END OF PRESENTATION
26The underlying theory
27The underlying theoryShort-term signals
- Nodal prices
- are energy prices that internalize the network
effects losses congestions - provide correct economic signals for system
operation - result in a net surplus, which in practice
happens to be insufficient to recover total
network costs - Frequently a uniform energy price is adopted
then the signals of losses congestions must be
separately sent - Note that persistent short-term signals
constitute valid signals for long-term decisions,
such as siting
28Theoretical results on cost recovery of
transmission networks
TOTAL COST OF NETWORK INFRASTRUCTURE
100
SHORT-TERM MARGINAL COSTS (NODAL PRICES)
LONG-TERM MARGINAL COSTS
ANY OTHER DIRECT CONSTRAINT
INCREASING RETURNS TO SCALE
DISCRETE NATURE OF NETWORK INVESTMENTS
NETWORK PLANNING ERRORS
RELIABILITY CONSTRAINTS
29InvestmentNature of transmission costs
- Actual transmission network costs
- Infrastructure costs
- investment capital costs
- operation maintenance costs
- Costs incurred because of the existence of the
network - Ohmic losses (generation costs)
- Costs of redispatch that are incurred to
eliminate violations of transmission constraints
(generation costs) - Some of the costs of ancillary services
- reactive power / operating reserves / black start
capability
30The underlying theoryLong-term signals (1)
- First priority is to charge network users so that
regulated transmission costs are fully recovered - Special treatment for risk investments (e.g.
merchant lines) - How to assign the residual network cost (or
complementary charge) to network users? - Long-term network charges should not be
transaction-based - On the basis of cost-causality (responsibility in
network costs) - Try to minimize economic distortion
- of short-term signals (e.g. avoid /kWh charges)
- use Ramsey-pricing principles, if needed
31The underlying theoryLong-term signals (2)
- Cost causality in transmission can be identified
(conceptually) - ? relate to the criteria for expansion of the
transmission network - traditional setting cost minimization
- liberalized setting maximization of aggregated
benefit of consumers and producers - ? assign cost responsibility to the beneficiaries
of each network asset, i.e. those for whom the
investment is made - long-term investment decisions are not distorted
32The underlying theoryLong-term signals (3)
- Time differentiation is needed in the structure
of network charges - since they should reflect the diversity in
economic impact of network use at different times - Geographical differentiation is needed in the
structure of network charges - since they should (in general) contain location
signals - note that geographical must be understood from
an electrical viewpoint
33The underlying theoryLong-term signals (4)
- Determination of responsibility in investment
and/or benefits is difficult ? Use only in
practice as a reference for a simpler proxy - use electric usage as a proxy
- but keep in mind that this is again an ambiguous
concept - when allocation to investment responsibility /
beneficiaries does not make sense at all or just
for a fraction of the network ? recur to
Ramsey-like ideas (second best) to minimize
distortion - in the split of charges to generation / consumers
- among generators / consumers
34The underlying theoryLong-term signals (5)
- Do nodal prices plus adequate complementary
charges provide sufficient investment signals for
transmission? - An economically justified network investment
under traditional network expansion rules - network investment cost lt savings in operation
costs - will increase the net benefit of
- Generators income from nodal prices operation
costs network charges - Consumers utility cost of purchasing
electricity network charges - if the residual network cost is allocated pro
rata of the economic benefits
35Which are the incentives from locational signals
for the different parties in the current design
of the EU Internal Electricity Market?
36Short-term incentive-based pricingIncentives for
generators
- Unless signals internalizing losses congestions
are received, the dispatch of generation will be
inefficient - EU-wide loss signals are missing in the current
design - A few countries / TSOs apply domestic loss
signals - An EU-wide coordinated congestion management
scheme is the only way to guarantee system
security to avoid inefficiency opportunistic
behavior
37Short-term incentive-based pricingIncentives for
consumers
- Same considerations apply to consumers
- But, in most countries, the mandatory uniform
tariff limits the application of any locational
economic signals
38Short-term incentive-based pricingIncentives for
System Operators
- Transmission System Operators are responsible for
network maintenance, provision of operation
reserves of different types, reactive power
support, black start capability they manage
network constraints and may influence network
losses - System security efficiency would greatly
benefit from a good performance of TSOs - Is it possible to find the right equilibrium
between efficiency security when designing
performance-based incentives for TSOs?
39(continuation)
- Several regulatory approaches are possible
- Avoid economic incentives that could turn out to
be perverse - Consider TSOs as neutral professional firms,
regulated as monopolies to perform its assigned
tasks, under strict cost-of-service regulation
transparency ? trust on their professionalism
respect for public opinion regulatory peer
supervision - Introduce some reduced economics incentives so
that efficiency gains are shared with consumers - set annual cost targets for each service that can
be controlled by TSOs let them share some of
the gains / losses - Apply a merchant philosophy of provision of these
services - This is considered to be unreasonable most of
these costs are beyond the control of the TSOs
they are volatile most important, there is often
a conflict between cost reduction security
40Long-term incentive-based pricingIncentives for
generators
- Generators might be subject to local G tariffs,
which - will have to comply with some EU-wide
harmonization conditions (level structure) ,
eventually, may even become a fully harmonized
pan EU G tariff - at least will internalize the effect of the
inter-TSO payment scheme - besides, generators will experience the long-term
effect of any persistent short-term signal of
losses or congestion - The relevance of these locational signals, when
compared to other considerations that influence
long-term decisions such as siting or active
promotion of network investments, will depend
much on the specific cases
41Long-term incentive-based pricingIncentives for
consumers
- L tariffs (which will internalize the effect of
the inter-TSO payment scheme) would have to
absorb the differences between the harmonized G
tariffs the regulated national transmission
costs - However, in most countries, mandatory uniform
tariffs for consumers prevent the application of
locational signals - Consumers will also experience the long-term
effect of any persistent short-term signal of
losses or congestion, if they are applied to them - It is doubtful the relevance of these locational
signals (if any) when compared to other
considerations that influence long-term decisions
of consumers, such as siting or active promotion
of network investments
42Incentive-based pricingIncentives for network
investors
- Who are the network investors / planners? It
depends on the specific regulation, at national
EU levels - System Operators, with some degree of regulatory
supervision, either national or EU - Coalitions of network users, subject to
regulatory approval - Merchant investors, subject to regulatory
authorization - The regulatory treatment of the remuneration of a
new line the pricing access schemes depend on
the adopted approach
43Investment in transmission facilitiesApproaches
- System Operator proposes reinforcement plan, to
be authorized by regulator construction may be
assigned by competitive bidding - A private company is awarded the transmission
license and is regulated as a monopoly subject
to grid code remuneration based on some price
control scheme (e.g. RPI-X) - Coalitions of network users proposes
reinforcements, to be authorized by regulator
regulated remuneration of total costs
construction is assigned by competitive bidding - Risk investments same as above, but coalition
bears total costs regulated remuneration covers
partial costs - Merchant lines (remuneration based on market
value of their transmission services)
44Incentive-based pricingIncentives for network
investors
- Merchant investors will collect just congestion
rents (or their expected values, via capacity
contracts or firm transmission rights of some
kind) - then they cannot be trusted to build all the
required transmission infrastructure (maybe some,
if subject to the appropriate access pricing
conditions) - Coalitions of network users may promote, even
invest at some risk, in specific infrastructures,
but not in those whose benefit is widely
dispersed (the majority in the EU)
45(continuation)
- ?There is a major role for regulated / planned
investment - presented by TSOs (individually or jointly)
belonging to a systematic plan ltsee previous
comments on incentives for TSOsgt - authorized by the involved regulators some
supra-national experts group that examines
implications at EU level of the reinforcements - included in the inter-TSO payment scheme, so the
costs are rightly shared among the users - ?Doors could be open for investment at risk
- who can exploit the existing incentives in
transmission pricing be subject to some
regulatory oversight, such as priority rules and
open access conditions
46Other issues concerns
- Locational signals generation investment
- More of an access than a pricing issue
- In non-well-meshed systems new generators want to
be protected from potential future congestions ?
obtain FTRs to hedge - How good is the proxy network use to cost
causality? Is there a metric of network usage
with sound economic properties? - Should any previous conclusions be changed
because of market power considerations? - Changing sound rules does not seem to be the
right approach to address market power