IDEI, The economics of electricity markets - PowerPoint PPT Presentation

About This Presentation
Title:

IDEI, The economics of electricity markets

Description:

System Operator proposes reinforcement plan, to be authorized by ... Initiative of proposal of network reinforcements corresponds to coalitions of network users ... – PowerPoint PPT presentation

Number of Views:18
Avg rating:3.0/5.0
Slides: 47
Provided by: idei
Category:

less

Transcript and Presenter's Notes

Title: IDEI, The economics of electricity markets


1
IDEI, The economics of electricity markets
  • Investment in transmission
  • Issues for discussion
  • Ignacio J. Pérez-Arriaga
  • Comillas University (Madrid)

Toulouse, June 3, 2005
2
Investment in transmissionWhich is the objective?
  • Regulatory framework should be such that all
    transmission facilities that meet a prescribed
    social welfare efficiency criterion (which must
    include economic implications of quality of
    supply) are
  • built at optimal times
  • properly operated maintained
  • at minimum cost for its users

3
Investment in transmissionIssues for discussion
  • How can justified transmission investment needs
    be identified? What is justified? Who
    identifies?
  • How to achieve consistency between operation
    investment criteria? Same decision maker?
  • How to incentivise building needed transmission
    investment? Agents depend on regulatory framework
  • How to determine the beneficiaries of an
    investment to make them pay for it? Pricing may
    affect investment decisions

4
The regulatory testWhat is a justified
investment?
  • Investment optimality according to traditional
    regulation
  • Invest in network assets only while the the
    additional network investment cost is still
    smaller than the additional saving in system
    operation costs (generation costs, loss of
    supply)
  • This definition is consistent with the one
    adequate for a context of competition
  • Invest so that the net aggregated benefits (once
    network charges are included) of all network
    users (i.e. generators consumers) are
    maximized
  • Technical reliability rules have to be met in any
    case

5
A useful property
  • An economically justified network investment
    under traditional network expansion rules
  • network investment cost lt savings in operation
    costs
  • will increase the net benefit of
  • Generators income from nodal prices operation
    costs network charges
  • Consumers utility of electricity use cost of
    purchasing electricity at nodal prices network
    charges
  • if the residual network cost is allocated pro
    rata of the economic benefits of each network user

6
Investment in new facilitiesApproaches (the
regulatory context)
  • System Operator proposes reinforcement plan, to
    be authorized by regulator construction may be
    assigned by a competitive auction
  • A private company is awarded the transmission
    license and is regulated as a monopoly subject
    to grid code remuneration based on some price
    control scheme (e.g. RPI-X)
  • Coalitions of network users proposes
    reinforcements, to be authorized by regulator
    regulated remuneration of total costs
    construction is assigned by competitive bidding
  • Risk investments same as above, but coalition
    bears total costs regulated remuneration covers
    partial costs
  • Merchant lines (remuneration based on market
    value of their transmission services)

7
Investment in new facilitiesApproaches (comments)
  • SO Regulator May result in overinvestment if
    regulator fails to set limits in the
    authorization process
  • Private licensed company May result in
    underinvestment unless very careful incentive
    schemes are implemented
  • Coalitions of network users Only lines with
    clear beneficiaries will be built. May be a
    complement to 1
  • Risk investments Same as 3, but more acute. Good
    to promote investment in underdeveloped networks
  • Merchant lines Cannot be trusted to develop a
    sound network, since transmission revenues from
    nodal prices in a well developed network will
    grossly under recover transmission costs. May be
    a complement to 1 or 2

8
Option 1System Operator Regulator
  • Regularly, the System Operator must propose a
    plan for reinforcements of the transmission
    network
  • after taking into consideration (justified) any
    proposals made by the network users
  • Regulatory authorities approve the plan
    authorize construction of individual new
    facilities
  • Construction, operation maintenance of each
    facility are allocated in a competitive auction
  • pay as bid to winner
  • limited duration of contract auction for the
    next period?
  • set availability targets for each facility
    penalties (credits) according to the actual
    performance
  • May be complemented by options 3, 4 5

9
Option 2 Private firm global regulated
remuneration
  • A private company is awarded the transmission
    license and regulated as a monopoly
  • Must follow prescribed design requirements (grid
    code)
  • Incentives to meet performance targets (warning
    separate clearly from incentives to System
    Operator)
  • Global remuneration (RPI-X) for the complete
    network, while taking into account
  • actual new investments
  • economic lives depreciation of existing
    investments
  • economic health of transmission company
  • expected efficiency improvements
  • Concern optimality of investments in general
    will not be attained determining remuneration
    becomes an art

10
Option 3Users have the initiative (A B)
  • Initiative of proposal of network reinforcements
    corresponds to coalitions of network users
  • OPTION A coalition builds pays the
    reinforcement, which needs authorization from
    regulator
  • OPTION B after a quasi-judiciary process
    (coalitions pro against, evaluation by system
    operator) regulator decides whether reinforcement
    is justified or not.
  • If justified, it is built under competitive
    bidding
  • pay as bid to winner
  • limited duration of license auction for the next
    period
  • set availability targets penalties (credits)
    according to performance
  • charge cost to all users with general allocation
    method

11
Option 4Users have the initiative (C)
  • OPTION C risk investments
  • Quasi-judicial process as in option B
  • If the reinforcement is found justified
  • the proprietary coalition is selected (a specific
    auction procedure is followed)
  • assign construction by competitive bidding
  • apply regulated tariffs (attenuated, according to
    the line utilization) to all network users
  • financial rights on the congestion rents of the
    reinforcement (firm transmission rights) are
    given to its owners

12
Option 5Merchant lines
  • Basic idea Regulate the transmission activity as
    any other competitive business ? merchant lines
  • Remuneration comes from congestion rents
  • Network capacity may even be bid in a short-term
    market (possible with DC lines)
  • Firm Transmission Rights (FTRs), may be seen not
    only as a risk hedging mechanism, but also as an
    incentive for investment
  • Difficulties
  • insufficiency (in general) of market driven
    revenues
  • High exposure to risk
  • reliability lines
  • potential for market power abuse

13
Investment in transmissionIssues for discussion
  • How can justified transmission investment needs
    be identified?
  • How to achieve consistency between operation
    investment criteria?
  • How to incentivise building needed transmission
    investment?
  • How to determine the beneficiaries of an
    investment to make them pay for it?

14
How to achieve consistency between operation
investment criteria?
  • SO Regulator No problem, use operation
    criteria when simulating the system to decide on
    investment
  • Private licensed company No problem, if there is
    a suitable grid code to comply with
  • Coalitions of network users No guarantee
  • Risk investments No guarantee
  • Merchant lines No guarantee

15
Investment in transmissionIssues for discussion
  • How can justified transmission investment needs
    be identified?
  • How to achieve consistency between operation
    investment criteria?
  • How to incentivise building needed transmission
    investment?
  • How to determine the beneficiaries of an
    investment to make them pay for it?

16
Objectives in transmission pricing
  • To ensure that the transmission network charges
    that are levied to the network users
  • recover the complete regulated costs of the
    transmission network of each country/TSO or that
    merchant lines (if any) are attractive
    economically
  • send efficient economic signals
  • in the short-term (for operation decisions)
  • in the long-term (for investment location
    decisions)
  • are non discriminatory
  • are easy to understand implement, perceived
    as fair

17
Can pricing / remuneration provide right
incentives for network investment?
  • Network users may receive signals that make them
    to act so that the operation of the system is
    efficient
  • losses
  • congestions
  • Network users may receive siting signals
    commensurate with the incurred transmission costs
  • for siting new generators loads / retiring
    existing ones
  • to promote new investments, in some regulatory
    schemes
  • System Operators, transmission network planners
    potential network investors may receive
    adequate signals so that optimal network
    investment happens or appropriate regulation
    makes it happen

18
Can pricing / remuneration provide right
incentives for network investment?
  • Who are the network investors / planners? It
    depends on the specific regulation, at national
    or regional (multinational) levels
  • System Operators, with some degree of regulatory
    supervision, either national or EU
  • Coalitions of network users, subject to
    regulatory approval
  • Merchant investors, subject to regulatory
    authorization
  • The regulatory treatment of the remuneration of a
    new line the pricing access schemes depend on
    the adopted approach

19
Can pricing / remuneration provide right
incentives for network investment?
  • Adequate remuneration of transmission depends on
    who is really responsible for the development of
    the network
  • If the transmission firm is active, (i.e takes
    responsibility for network development) then the
    remuneration must refer to an efficient well
    adapted network performance-based economic
    incentives to invest make sense
  • If the transmission firm is passive, (i.e does
    not take responsibility for network development)
    then the remuneration must refer to the actual
    network incentives must basically depend on the
    availability of the network equipment, although
    mild incentives to improve operation can also
    make sense

20
Can pricing / remuneration provide right
incentives for network investment?
  • Merchant investors will collect just congestion
    rents (or their expected values, via capacity
    contracts or firm transmission rights of some
    kind)
  • then they cannot be trusted to build all the
    required transmission infrastructure (maybe some,
    if subject to the appropriate access pricing
    conditions)
  • Coalitions of network users may promote, even
    invest at some risk, in specific infrastructures,
    but not in those whose benefit is widely
    dispersed (probably the majority in well
    developed networks)

21
(continuation)
  • ?There is a major role for regulated / planned
    investment (use the EU market as an example)
  • presented by TSOs (individually or jointly)
    belonging to a systematic plan
  • authorized by the involved regulators TSOs that
    examine implications at EU level of the
    reinforcements
  • included in the inter-TSO payment scheme, so the
    costs are rightly shared among the users
  • ?Doors could be open for investment at risk
  • who can exploit the existing incentives in
    transmission pricing be subject to some
    regulatory oversight, such as priority rules and
    open access conditions

22
Investment in transmissionIssues for discussion
  • How can justified transmission investment needs
    be identified?
  • How to achieve consistency between operation
    investment criteria?
  • How to incentivise building needed transmission
    investment?
  • How to determine the beneficiaries of an
    investment to make them pay for it?

23
A useful property (regarding beneficiaries)
  • An economically justified network investment (for
    instance, under traditional network expansion
    rules
  • network investment cost lt savings in operation
    costs)
  • will increase the net benefit of
  • Generators income from nodal prices operation
    costs network charges
  • Consumers utility of electricity use cost of
    purchasing electricity network charges
  • if the residual network cost (trasnmission
    cost minus any revenues from nodal prices) is
    allocated pro rata of the economic benefits of
    each network user

24
The need to identify beneficiaries
  • Basically no need for existing lines existing
    network users
  • although adequate network charges may be relevant
    for plants that are close to retirement
  • But sound economic signals are convenient /
    necessary when the investment decision on new
    generation projects may depend on transmission
    charges / signals
  • Example 1 60.000 MW of proposed connection of
    wind generators plus 50.000 of CCGT in Spain,
    some requiring transmission expansion
  • Example 2 Decisions about investment-at-risk
    versus planned investment in new lines for
    distant generation projects in Peru

25
END OF PRESENTATION
26
The underlying theory
27
The underlying theoryShort-term signals
  • Nodal prices
  • are energy prices that internalize the network
    effects losses congestions
  • provide correct economic signals for system
    operation
  • result in a net surplus, which in practice
    happens to be insufficient to recover total
    network costs
  • Frequently a uniform energy price is adopted
    then the signals of losses congestions must be
    separately sent
  • Note that persistent short-term signals
    constitute valid signals for long-term decisions,
    such as siting

28
Theoretical results on cost recovery of
transmission networks
TOTAL COST OF NETWORK INFRASTRUCTURE
100
SHORT-TERM MARGINAL COSTS (NODAL PRICES)
LONG-TERM MARGINAL COSTS
ANY OTHER DIRECT CONSTRAINT
INCREASING RETURNS TO SCALE
DISCRETE NATURE OF NETWORK INVESTMENTS
NETWORK PLANNING ERRORS
RELIABILITY CONSTRAINTS
29
InvestmentNature of transmission costs
  • Actual transmission network costs
  • Infrastructure costs
  • investment capital costs
  • operation maintenance costs
  • Costs incurred because of the existence of the
    network
  • Ohmic losses (generation costs)
  • Costs of redispatch that are incurred to
    eliminate violations of transmission constraints
    (generation costs)
  • Some of the costs of ancillary services
  • reactive power / operating reserves / black start
    capability

30
The underlying theoryLong-term signals (1)
  • First priority is to charge network users so that
    regulated transmission costs are fully recovered
  • Special treatment for risk investments (e.g.
    merchant lines)
  • How to assign the residual network cost (or
    complementary charge) to network users?
  • Long-term network charges should not be
    transaction-based
  • On the basis of cost-causality (responsibility in
    network costs)
  • Try to minimize economic distortion
  • of short-term signals (e.g. avoid /kWh charges)
  • use Ramsey-pricing principles, if needed

31
The underlying theoryLong-term signals (2)
  • Cost causality in transmission can be identified
    (conceptually)
  • ? relate to the criteria for expansion of the
    transmission network
  • traditional setting cost minimization
  • liberalized setting maximization of aggregated
    benefit of consumers and producers
  • ? assign cost responsibility to the beneficiaries
    of each network asset, i.e. those for whom the
    investment is made
  • long-term investment decisions are not distorted

32
The underlying theoryLong-term signals (3)
  • Time differentiation is needed in the structure
    of network charges
  • since they should reflect the diversity in
    economic impact of network use at different times
  • Geographical differentiation is needed in the
    structure of network charges
  • since they should (in general) contain location
    signals
  • note that geographical must be understood from
    an electrical viewpoint

33
The underlying theoryLong-term signals (4)
  • Determination of responsibility in investment
    and/or benefits is difficult ? Use only in
    practice as a reference for a simpler proxy
  • use electric usage as a proxy
  • but keep in mind that this is again an ambiguous
    concept
  • when allocation to investment responsibility /
    beneficiaries does not make sense at all or just
    for a fraction of the network ? recur to
    Ramsey-like ideas (second best) to minimize
    distortion
  • in the split of charges to generation / consumers
  • among generators / consumers

34
The underlying theoryLong-term signals (5)
  • Do nodal prices plus adequate complementary
    charges provide sufficient investment signals for
    transmission?
  • An economically justified network investment
    under traditional network expansion rules
  • network investment cost lt savings in operation
    costs
  • will increase the net benefit of
  • Generators income from nodal prices operation
    costs network charges
  • Consumers utility cost of purchasing
    electricity network charges
  • if the residual network cost is allocated pro
    rata of the economic benefits

35
Which are the incentives from locational signals
for the different parties in the current design
of the EU Internal Electricity Market?
36
Short-term incentive-based pricingIncentives for
generators
  • Unless signals internalizing losses congestions
    are received, the dispatch of generation will be
    inefficient
  • EU-wide loss signals are missing in the current
    design
  • A few countries / TSOs apply domestic loss
    signals
  • An EU-wide coordinated congestion management
    scheme is the only way to guarantee system
    security to avoid inefficiency opportunistic
    behavior

37
Short-term incentive-based pricingIncentives for
consumers
  • Same considerations apply to consumers
  • But, in most countries, the mandatory uniform
    tariff limits the application of any locational
    economic signals

38
Short-term incentive-based pricingIncentives for
System Operators
  • Transmission System Operators are responsible for
    network maintenance, provision of operation
    reserves of different types, reactive power
    support, black start capability they manage
    network constraints and may influence network
    losses
  • System security efficiency would greatly
    benefit from a good performance of TSOs
  • Is it possible to find the right equilibrium
    between efficiency security when designing
    performance-based incentives for TSOs?

39
(continuation)
  • Several regulatory approaches are possible
  • Avoid economic incentives that could turn out to
    be perverse
  • Consider TSOs as neutral professional firms,
    regulated as monopolies to perform its assigned
    tasks, under strict cost-of-service regulation
    transparency ? trust on their professionalism
    respect for public opinion regulatory peer
    supervision
  • Introduce some reduced economics incentives so
    that efficiency gains are shared with consumers
  • set annual cost targets for each service that can
    be controlled by TSOs let them share some of
    the gains / losses
  • Apply a merchant philosophy of provision of these
    services
  • This is considered to be unreasonable most of
    these costs are beyond the control of the TSOs
    they are volatile most important, there is often
    a conflict between cost reduction security

40
Long-term incentive-based pricingIncentives for
generators
  • Generators might be subject to local G tariffs,
    which
  • will have to comply with some EU-wide
    harmonization conditions (level structure) ,
    eventually, may even become a fully harmonized
    pan EU G tariff
  • at least will internalize the effect of the
    inter-TSO payment scheme
  • besides, generators will experience the long-term
    effect of any persistent short-term signal of
    losses or congestion
  • The relevance of these locational signals, when
    compared to other considerations that influence
    long-term decisions such as siting or active
    promotion of network investments, will depend
    much on the specific cases

41
Long-term incentive-based pricingIncentives for
consumers
  • L tariffs (which will internalize the effect of
    the inter-TSO payment scheme) would have to
    absorb the differences between the harmonized G
    tariffs the regulated national transmission
    costs
  • However, in most countries, mandatory uniform
    tariffs for consumers prevent the application of
    locational signals
  • Consumers will also experience the long-term
    effect of any persistent short-term signal of
    losses or congestion, if they are applied to them
  • It is doubtful the relevance of these locational
    signals (if any) when compared to other
    considerations that influence long-term decisions
    of consumers, such as siting or active promotion
    of network investments

42
Incentive-based pricingIncentives for network
investors
  • Who are the network investors / planners? It
    depends on the specific regulation, at national
    EU levels
  • System Operators, with some degree of regulatory
    supervision, either national or EU
  • Coalitions of network users, subject to
    regulatory approval
  • Merchant investors, subject to regulatory
    authorization
  • The regulatory treatment of the remuneration of a
    new line the pricing access schemes depend on
    the adopted approach

43
Investment in transmission facilitiesApproaches
  • System Operator proposes reinforcement plan, to
    be authorized by regulator construction may be
    assigned by competitive bidding
  • A private company is awarded the transmission
    license and is regulated as a monopoly subject
    to grid code remuneration based on some price
    control scheme (e.g. RPI-X)
  • Coalitions of network users proposes
    reinforcements, to be authorized by regulator
    regulated remuneration of total costs
    construction is assigned by competitive bidding
  • Risk investments same as above, but coalition
    bears total costs regulated remuneration covers
    partial costs
  • Merchant lines (remuneration based on market
    value of their transmission services)

44
Incentive-based pricingIncentives for network
investors
  • Merchant investors will collect just congestion
    rents (or their expected values, via capacity
    contracts or firm transmission rights of some
    kind)
  • then they cannot be trusted to build all the
    required transmission infrastructure (maybe some,
    if subject to the appropriate access pricing
    conditions)
  • Coalitions of network users may promote, even
    invest at some risk, in specific infrastructures,
    but not in those whose benefit is widely
    dispersed (the majority in the EU)

45
(continuation)
  • ?There is a major role for regulated / planned
    investment
  • presented by TSOs (individually or jointly)
    belonging to a systematic plan ltsee previous
    comments on incentives for TSOsgt
  • authorized by the involved regulators some
    supra-national experts group that examines
    implications at EU level of the reinforcements
  • included in the inter-TSO payment scheme, so the
    costs are rightly shared among the users
  • ?Doors could be open for investment at risk
  • who can exploit the existing incentives in
    transmission pricing be subject to some
    regulatory oversight, such as priority rules and
    open access conditions

46
Other issues concerns
  • Locational signals generation investment
  • More of an access than a pricing issue
  • In non-well-meshed systems new generators want to
    be protected from potential future congestions ?
    obtain FTRs to hedge
  • How good is the proxy network use to cost
    causality? Is there a metric of network usage
    with sound economic properties?
  • Should any previous conclusions be changed
    because of market power considerations?
  • Changing sound rules does not seem to be the
    right approach to address market power
Write a Comment
User Comments (0)
About PowerShow.com