Title: Diapositive 1
1Marie-Claire AOUN CRE marie-claire.aoun_at_cre.fr
2Agenda
- Overview of the project
- Guidelines for Good Practice on Open Season
Procedures (GGPOS) - Aims of the project
- Experiences on coordinated open seasons
- Need to improve the coordination of the open
seasons - Questions
3Guidelines for Good Practice on Open Seasons
(GGPOS)
- Role of the Open seasons procedures
- Assess the market demand for capacity
- Allow a project sponsor to efficiently consult
the market about how much infrastructure it needs
and under what terms - Allocate resulting capacity in a transparent and
non-discriminatory way - Structure of an Open Season in 2 phases
- Assessment of the markets needs on the basis of
an open season notice and through non binding
capacity requests from interested parties - Capacity allocation and capacity contracts
- Need for long term as well as short term
contracts
4GGPOS what they provide for coordination
- Need for coordination with adjacent SOs
- Participants should be able to assess service on
adjacent systems - Products offered by the adjacent TSOs have to be
compatible - Products have to be offered in a coordinated way,
using compatible and/or coordinated timetables
and processes. - Coordination between NRAs
- Clarity of the regulatory frameworks and
sufficient degree of similarity (in order to
design compatible products) - Ensure that differences between regulatory
frameworks are not a barrier to investment - NRAs have to jointly monitor the open season
- NRAs provide timely and coordinated input on
allocation of costs and tariffs for the use of
the infrastructure
5Aims of the project
- The main principles of the GGPOS provide floor
requirements in order to ensure transparent and
non-discriminatory open seasons - There is a need to provide more concrete guidance
on the coordination of open seasons. - The project focuses on coordinated open seasons,
but also addresses other difficulties encountered
by past and present open seasons - The aim is also to define a rule to determine how
much additional capacity should be developed for
short term needs, on top of the long term
capacity requested through the open seasons
- Complete GGPOS on the basis of the experience
gained through the ongoing coordinated open
seasons - Define effective and operational coordinated open
seasons mechanisms
6Growing number of ongoing open seasons need for
coordination
Energinet.dk
GTS 2012
EGT/Gasunie/DONG
GTS - Gasunie De
EGT
GRTgaz - Fluxys
GRTgaz
7Open season GRTgaz/Fluxys ( GTS 2012)
- Ongoing process launched in April 2007
- Binding phase Nov. Dec. 2008
- First experience for cooperation and sharing of
information between TSOs and NRAs - Difficult to draw a final conclusion before the
end of the process Positive points and critical
issues
GTS 2012 Open Season
GRTgaz
8Open season GRTgaz/Fluxys ( GTS 2012)
- Positive points
- Definition of consistent timeframes and some
coordination on contractual aspects - Coordinated capacity allocation shippers are not
exposed to the risk of capacity mismatch - Memorandum of Understanding between GRTgaz and
Fluxys - Open season 2012 of GTS Possibility for shippers
to adjust their bids by GTS thanks to the update
of the timing of phase 2 of the open season - Critical issues
- Delay of more than one year due to discussions
regarding transit tariffs in Belgium - Capacity requests in the 1st phase are free
lack of incentives for shippers to reveal their
real needs (? E.ON GT open season) - Short term capacity on top of the requested
capacity only provided on the French side
9Growing number of ongoing open seasons need for
coordination
- E.ON Gastransport (EGT)
- End of binding phase in June 2008
- Little coordination with adjacent TSOs, partly
due to the large network area and to the
important number of IPs covered by the OS - Need for coordination with GRTgaz
- Integrated network development GTS/Gasunie
- Cross-border network development approach
- Initial phase of market screening (Nov. - Dec.
2008) - Non-Binding (Phase 1) and binding agreements
(Phase 2) in 2009
10Growing number of ongoing open seasons need for
coordination
- Energinet.dk Open season 2009
- Model paper Dialogue on Open season design
(Nov. 2008) - 1st phase (Feb. 2009) 2nd phase
(Aug. 2009) - Capacity bids for each point can vary by /- 15
from the 1st phase to the 2nd phase - Need for coordination with adjacent SOs (Gassco,
Gas System, Swedegas , E.ON Gastransport, DONG
Energy Pipelines, Gasunie Deutschland)
11National specificities impact coordination
- Different stakes in adjacent MS ? divergent
priorities - Belgium transit service
- France develop Hub to Hub capacity
(Zeebrudge/TTF/PEG North) - Germany gas network expansion need to
coordinate with several adjacent SOs
(Energinet.dk, GTS, Fluxys and GRTgaz) - Different allocation of risks between the market
players in MS - Investment planning varies from one country to
another
12Need to improve the coordination of the O.S
Main difficulties encountered related to
coordination
- Between regulators rules on each side of the
border - Share of the capacity dedicated to short term
bookings - Between TSOs
- Contractual aspects In case of delay in the
realisation of the project on one side of the
border - Information exchange between the adjacent TSOs
Confidentiality claimed by certain TSOs hindering
the information exchange with adjacent SO No
legal barriers for sharing data Contractual
provisions of confidentiality.
13Conclusion
- Growing number of OS ? increasingly becoming the
standard procedure for major investment projects
in many MS - Coordination between TSOs and NRAs is possible as
proved by the ongoing coordinated open seasons - Coordination can be hindered by several
obstacles - External element that slows down the ongoing
process - Divergences between regulatory rules of adjacent
MS - Lack of information sharing between adjacent TSOs
- The coordination of open seasons requires
- Compatibility of the different systems
- A certain degree of similarities in regulatory
frameworks - Complete cooperation between adjacent TSOs
14Question 1 Coordination issues
- What are the concrete difficulties you have
encountered during open seasons processes related
to coordination with an adjacent TSO - Coordination of regulatory rules?
- Coordination between TSOs on contractual aspects,
timing, technical issues? - Other?
15Question 2 Information exchange
- Do you agree with the fact that adjacent TSOs
should share with each other all the information
related to the open season procedure for a
successful coordination?
16Question 3 Additional short term capacity
- Do you think that additional capacity should
systematically be developed for short term needs
or security of supply reasons, on top of the long
term capacity requested through the open seasons?
If yes, how much (10, 20)?
17- Thank you for your attention!
-