GCT Q-M EDR, CERN, 2/10/07 C. Foudas - Imperial 1 - PowerPoint PPT Presentation

1 / 4
About This Presentation
Title:

GCT Q-M EDR, CERN, 2/10/07 C. Foudas - Imperial 1

Description:

Each of the 18 RCT crate transmits 28 Q M bits (18x28=504) ... also by November 07. Several Months of data validation will follow (A. Taper, G. ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 5
Provided by: Robert1128
Category:
Tags: cern | edr | gct | foudas | imperial | taper

less

Transcript and Presenter's Notes

Title: GCT Q-M EDR, CERN, 2/10/07 C. Foudas - Imperial 1


1
Q/M-Bit GCT Task
  • The tasks of the muon system
  • - Receive from RCT 252252 QM 504 Bits.
  • - Each of the 18 RCT crate transmits 28
    QM bits (18x28504).
  • - Hence, the Q/M bits are ?-segmented as
    the come to GCT.
  • - The Q/M bits need to be transmitted to
    GMT ?-segmented.
  • - All 504 bits are transmitted to GMT ? No
    data reduction
  • - The data are transmitted to GMT via 12
    cables.
  • - All other physics triggers require 61
    cables.
  • - The cable specification was inherited by
    the new GCT along
  • with the task requirement.

2
The Muon System
  • The Muon system
  • 3 Processing Cards (3 SNAP12, V5, Cross-Point
    Switch, MicroController.
  • Custom uTCA backplane (2 more Cross-Point
    Switches) and uTCA crate.
  • 3 More Cards which convert to the Infiniband
    protocols (now under further review)
  • 12 Infiniband cables connect with GMT

Optical Input from the Source Cards
12 Infiniband Cables to GT
3 Processing Cards
Link Converters (Infiniband)
This Subject of todays review
uTCA Backplane
3
GCT Current State of Affaires
  • The Electron Trigger has been commissioned and M.
    Hansen and A. Tapper are in the process of
    removing the last differences between firmware
    and emulator.
  • The Jet trigger is proceeding in a satisfactory
    way. The new Wheel Card seems to work and
    communications and data transfers have been
    established from a Jet Leaf via the Wheel and all
    the way to the Concentrator Card (G.
    Sidiropoulos). It seems at the moment realistic
    to install the Jets Trigger also by November 07.
    Several Months of data validation will follow (A.
    Taper, G. Iles, G. Sidiropoulos, M. Hansen) but
    it should go faser then the electrons since the
    Jets are moving into a system that debugged and
    working.
  • Source Card Links In the process of changing to
    100 Mhz oscillators (M Stettler).
  • GCT to GT Links Studies continue (G. Iles)
  • It appears that M. Stettler, who is back at CERN
    in Feb. 08, be free to concentrate his efforts
    to the Muon System

4
Preliminary Plan
  • Processor Card should go out at the end of 07
    and be back sometime in March 08.
  • The Backplane should be out to the manufacturer
    sometime in late Spring 08
  • We should have Backplane and Processor Cards in
    Summer 08.
  • The Links to GMT remain an unknown but that
    should be rectified in a few months.
  • Need to produce a resource loaded plan by the end
    of the year