Smart House Project - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Smart House Project

Description:

Smart House Project. Group - Mission Impossible III. Team - Casey Madsen. Yuning Shi ... Fabricate and erect wood frame $37,000. Construct phase I building $70,000 ... – PowerPoint PPT presentation

Number of Views:130
Avg rating:3.0/5.0
Slides: 18
Provided by: Yun81
Category:
Tags: house | madsen | project | smart

less

Transcript and Presenter's Notes

Title: Smart House Project


1
Smart House Project
  • Group - Mission Impossible III
  • Team - Casey Madsen
  • Yuning Shi
  • Jim Stahlman
  • Weiqing Tu

2
Project Description
  • - Smart House, residential
  • - Two-Story Dwelling
  • - Computer Controlled
  • Electrical System

3
Project Implementation
  • - Budgeting Cost Estimation
  • - Scheduling
  • - Resource Allocation

4
Budgeting
  • - Information Gathering Strategy
  • - Risk Analysis
  • - Project Costs

5
Information Gathering Strategy
  • - Top-Down Budgeting
  • vs.
  • Bottom-Up Budgeting
  • - Category/Activity
  • vs.
  • Program Budgeting

6
Risk Analysis
  • Risk of Smart House Project
  • - Poorly defined requirements
  • - Lack of qualified resources
  • - Poor estimating
  • - Environmental risks
  • - Social risks

7
Project Costs
  • Activity Estimated Cost
  • Design wood frame 7,000
  • Design Building 70,000
  • Design mechanical equipment 20,000
  • Fabricate and erect wood frame 37,000
  • Construct phase I building 70,000
  • Design electrical equipment 13,000
  • Construct phase II building 77,000
  • Procure interior items
  • Install interior items 40,000
  • Total 400,000

8
Scheduling
  • - Scheduling Techniques
  • - Scheduling Procedures
  • - Project Schedule

9
Scheduling Techniques
  • - Gantt Chart
  • Used to represent the timing of tasks required
    to complete a project.
  • - PERT / CPM Network
  • A directed graph that shows tasks, duration and
    precedence relationships.

10
Schedule Procedure
  • - Determine the required time to complete each
    project item.
  • - Calculate the available time to complete each
    project item.
  • - Compare the required time with the available
    time of each project item for its float.
  • - Identify the critical project items
  • - Determine the float times of the non-critical
    items.
  • - Calculate the duration of the project.
  • - Validate the time schedule.

11
Project Schedule
1,4
Design wood frame
Fabricate and erect wood frame
2
8,10
Construct phase II building
Construct phase I building
14,14
Design building
0,0
1
3
7
11
18,18
Fabricate mechanical equipment
4,4
10,10
Install mechanical and electrical equipment
Design mechanical equipment
4
6
6,6
5
Procure electrical equipment
Design interior items
8,12
8
9
10
14,18
Procure interior items
Install interior items
5,9
12
Resource Allocation
  • - Process of distributing an organizations
    tangible assets to effectively achieve company
    goals.
  • - Heart of management decision-making

13
Labor Distribution
14
Labor Distribution
15
Resource Leveling
  • - Shifting tasks within slack periods to create
    smoother resource requirement schedule
  • - Advantage

16
Resource Leveling Practice
Before Leveling
After Leveling
17
Questions?