Title: DO Timeline Split Silicon V2.0
1DO TimelineSplit Silicon V2.0
Fiber TrackerSiliconForward MuonCalorimeterOve
rall Installation double shift assumed
2000
2001
M A M J J A
S O N D J F M
Roll detector into Collision Hall
Remove shield wall
Platform moves, returns east
North
South
CFT install align
CFT hookup
Install/align/survey north south trusses in
Collision Hall
Install VLPC cassettes
Move/hookup ECS on platform
Ready for beam Feb 16, 2001
1st CFT crate operational
Install/commission silicon front-end
Install/hookup/checkout SMT
1st CAL quadrant available
Clear waveguide production
Run II begins Mar 1, 2001
Assemble north south trusses on sidewalk
Install/survey C- and B-layer MDTs and pixels
Install/survey A-layer pixels
Install A-layer MDTs
Detector Hookup/Commissioning
Phase II
Tracker Hookup (CFT, SMT, PS), VLPCs, Trigger,
Forward Muon
Phase III
Cosmic Ray Commissioning Tracker Muon
Systems, Cosmic Triggering
Phase I Central Muon, DAQ, RECO,
Trigger