Source Control Surface Waste Pile Demonstration Project - PowerPoint PPT Presentation

1 / 86
About This Presentation
Title:

Source Control Surface Waste Pile Demonstration Project

Description:

Source Control Surface Waste Pile Demonstration Project – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 87
Provided by: amylynnm
Category:

less

Transcript and Presenter's Notes

Title: Source Control Surface Waste Pile Demonstration Project


1
Source Control - Surface Waste Pile Demonstration
Project
  • Activity III, Project 10

2
Problem
  • Acid Mine Drainage can be formed when surface and
    groundwater infiltrate surface waste piles that
    are placed in drainages.
  • The result is increased metals loading and
    suspended solids in surface waters, erosion, and
    reduced pH.

3
Project Objective
  • In situ stabilization and/or encapsulation of a
    surface waste pile

4
Peerless Mine Located in Montana
5
Peerless Mine Surface Waste Pile
6
Materials Testing
  • 50 source control materials were tested to ASTM
    standards when applicable. Material Testing
    Included
  • 1. Permeability
  • 2. Acid Resistance
  • 3. Applicability
  • 4. Compatibility
  • 5. Freeze-Thaw and Wet-Dry Cycling
  • 6. Elasticity and strength

7
Materials Testing of Source Control Materials
8
Field Emplacement
  • Two Problem Areas - Surface Water and Groundwater
  • Groundwater Technology - Hydraulic Barrier
    (Surface Water Collection Trench and French Drain
    System)
  • Surface Technology - Spray Applied Cover

9
Construction of Water Collection Trench and
French Drain
10
Water Collection Trench and French Drain
Construction
11
Spray-Applied Capping Material
  • Easy to spray-apply at site
  • Reduces water and wind erosion
  • Can be applied on webbed jute fabric or on the
    surface of the pile

12
(No Transcript)
13
Primary Spray Coating
14
Spray-Applied Urethane Material
15
Final Spray-Application for the Surface Waste Pile
16
Peerless Surface Waste Pile Ready for Top Soil
and Vegetation Application
17
Application Problems and Causes
  • Pinholes in wet areas
  • Low temperatures caused curdling effect and
    increased viscosity
  • Sagging on slopes
  • Application without jute fabric
  • Difficult to spray disturbed soil and around
    large rock

18
Conclusion and Recommendations
  • The application of the French drain and the
    Spray-applied urethane cover did improve the
    water quality at the Peerless Mine.
  • The French drain intercepted much of the
    groundwater.
  • The Spray-applied cap decreased infiltration and
    increased erosion control.

19
Activity III Project 12SULFATE-REDUCING
BACTERIAREACTOR DEMONSTRATION
20
Introduction
  • Thousands of abandoned mines in the Western U.S.
    discharge water, commonly called acid mine
    drainage (AMD), that is usually formed in the
    mine where sulfide bearing minerals, particularly
    pyrite, are exposed to oxygen and water as
    described by the following chemical reaction
  • FeS2 15/4 O2 7/2 H2O ---gt Fe(OH)3
    2SO42- 4H

21
(No Transcript)
22
Project Scope
  • Conventional treatment strategies for AMD are not
    feasible.
  • However, sulfate reducing bacteria (SRB) are
    capable of increasing the pH and reducing the
    load of dissolved metals in the effluent
  • Three bioreactors were built at the Calliope
    site.

23
Construction Overview
  • Three reactors were constructed in the Fall of
    1998.
  • Two bioreactors contain a passive pretreatment
    section to increase pH of water before the AMD
    enters the bioreactor chamber. Such a setting
    will enable evaluating the effect of inducing an
    optimal pH and EH into AMD on the efficiency of
    the SRB.

24
(No Transcript)
25
(No Transcript)
26
Bioreactors Components
  • Each bioreactor consists of discrete
    chambers each filled with either organic carbon,
    crushed limestone, or cobbles.
  • For the pretreatment section, a chamber with cow
    manure was included to lower the EH of AMD.
  • Crushed limestone provides buffering capacity to
    increase the pH of AMD in the pretreatment
    section.
  • Cobbles, placed in the primary treatment section
    of the bioreactor, constitute a stable substrate
    for bacterial growth.

27
.
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
Results
34
The pH of treated AMD has been in the range of
7 - 10
35
.Temperature of AMD changes seasonally with the
temperature of air.
36
Oxidation-reduction potential (Eh) of the
influent has always been above 50 mV.
37
(No Transcript)
38
(No Transcript)
39
(No Transcript)
40
(No Transcript)
41
(No Transcript)
42
.
43
.
44
Microbial Capping Barrier for the Control of
Acid Mine Drainage
Activity III Project 14
45
Microbial Capping Barriers
Surface application or subsurface injection of
bacteria and nutrient solutions.
46
Microbial Capping Barrier
47
Microbial Capping Barrier
O2
H20
C6H12O6
O2 C6H12O6
CO2 H2O
AEROBIC
C6H12O6 H2O
C2H3O2 H2 CO2
Fermentative
ANAEROBIC
C2H3O2 SO42-
H2S HCO3
M2 S2-
MS?
48
Microbial Capping Barrier Demonstration
  • Column Testing
  • Crescent Mine tailings, initiated January, 1999
  • Fox Lake tailings, initiated October, 1999
  • Mammoth tailings, initiated March, 2000
  • Field demonstration at Mammoth Site
  • Construction of test cells complete
  • Treatment to begin in Spring, 2000

49
Crescent Mine Site
50
Crescent Mine Site
  • Elevated elements
  • silver 32.6 mg/kg
  • lead 4,570 mg/kg
  • cadmium 3.67 mg/kg
  • zinc 618 mg/kg
  • copper 356 mg/kg

data from the Montana Department of State Lands
51
(No Transcript)
52
Crescent Tailings Sulfate-Reducing Bacteria vs
Time
53
Fox Lake Tailings
  • Elevated elements
  • Aluminum 50 ppm
  • Cobalt 0.3 ppm
  • Copper 2 ppm
  • Manganese 4 ppm
  • Sulfur 720 ppm
  • Zinc 20 ppm

54
Fox Lake Mine Site
55
(No Transcript)
56
Conclusions from Column Tests
  • Nutrient treatments were effective for decreasing
    oxidation-reduction potential.
  • Nutrient treatment of acid-producing tailings
    resulted in an effluent pH increase.
  • Nutrient treatments were effective for
    stimulating Sulfate-Reducing bacteria within the
    tailings.

57
Mammoth Tailings Site
  • Elevated elements
  • Aluminum 400-1400 mg/kg
  • Arsenic 167-572 mg/kg
  • Copper 70-2500 mg/kg
  • Lead 10-100 mg/kg
  • Manganese 10-1000 mg/kg
  • Zinc 20-222 mg/kg

data from the Montana Department of State Lands
58
Upper Mammoth Tailings Site
59
Upper Mammoth Tailings
60
Mammoth Tailings Field Test
  • Test cells
  • Lined to ensure accurate measurement of influent
    and effluent water volume and quality.
  • Treatment cell
  • Will receive biocapping treatment beginning in
    Spring, 2000.
  • Control cell
  • Will be treated with an equivalent amount of
    water to treatment cell.

61
Test Cell Schematic
Water supply line
Control valve
Totalizing Flowmeter
Distribution laterals
Effluent Holding Tank
Lined test cell
Totalizing Flowmeter
Buried process control boxes
System effluent line
Surface Drainage
Effluent Valve
62
Test Cell Excavation
63
Liner Drain Field Installation
64
Completed Test Cell
65
Mammoth Field Test Status
Test cells constructed Background data
collected Initial nutrient treatment
applied Additional monitoring treatments will
be applied after Spring thaw
66
Technology Benefits
  • Natural biological process
  • In-situ treatment
  • Low application costs
  • Complete treatment - acidity, metals
  • Stabilization of tailings for revegetation

67
Tailing Source Control Demonstration Project
  • Activity III, Project 15

68
Problem
  • Wind and water erosion are a major problem
    because of the fine particle size of the tailings
    material.

69
Mammoth Tailings Site
70
Mammoth Tailings Site
71
Project Objective
  • Demonstrate the applicability of source control
    technologies for in situ stabilization and/or
    encapsulation of a surface waste pile to prevent
    the influx of water, whether precipitation and/or
    groundwater, thus decreasing AMD formation and
    the erosion of the tailings material.

72
Project Phase Approach
  • Phase I - Mine Site Selection and Site
    Characterization
  • Phase II - Materials Testing and Selection
  • Phase III - Field Emplacement, Long-term
    Monitoring and Technology Evaluation

73
The Mammoth Tailings Site
74
Showing the Erosion Channels at the Mammoth
Tailings Site
75
Site Characterization
  • Monitor Weather Conditions
  • Monitor Soil Moisture
  • Perform Soil Analysis (Physical and chemical)
  • Perform Air Monitoring
  • Perform Erosion Testing

76
Materials Testing
  • Source control materials were tested to ASTM
    standards when applicable. Material Testing
    Included
  • 1. Permeability
  • 2. Acid Resistance
  • 3. Erosion Testing
  • 4. Compatibility
  • 5. Freeze-Thaw and Wet-Dry Cycling
  • 6. Elasticity and strength

77
Materials Testing of Source Control Materials
78
Field Emplacement
  • Field Emplacement be performed during the Summer
    2000
  • The demonstration will consist of placing a
    background and a test plot side-by-side.

79
Conclusion and Recommendations
  • The demonstration will be performed at the
    Mammoth Tailings Site
  • Field Emplacement will occur during the Summer
    2000
  • At least two test plots will be used, a
    background and a test plot
  • A decision on the materials tested will be made
    during April and May 2000

80
Support to SITE Mercury Project/In Situ Mercury
Stabilization Technologies Demonstration
Project Activity III, Project 19
81
Background
  • The In Situ Mercury Stabilization Technologies
    Demonstration Project will show the effectiveness
    of various technologies for in situ treatment and
    stabilization for mercury-contaminated mine waste
    material.

82
Objectives
  • The primary goal of the project is to conduct
    comparative mercury stabilization tests using
    mercury-contaminated material.

83
Status
  • The Sulphur Bank Mine has been identified.
  • Characterization is being conducted

84
(No Transcript)
85
Clear Lake / Hermon Pit
86
Hermon Pit (Lake)
Write a Comment
User Comments (0)
About PowerShow.com