Title: Source Control Surface Waste Pile Demonstration Project
1Source Control - Surface Waste Pile Demonstration
Project
2Problem
- Acid Mine Drainage can be formed when surface and
groundwater infiltrate surface waste piles that
are placed in drainages. - The result is increased metals loading and
suspended solids in surface waters, erosion, and
reduced pH.
3Project Objective
- In situ stabilization and/or encapsulation of a
surface waste pile
4Peerless Mine Located in Montana
5Peerless Mine Surface Waste Pile
6Materials Testing
- 50 source control materials were tested to ASTM
standards when applicable. Material Testing
Included - 1. Permeability
- 2. Acid Resistance
- 3. Applicability
- 4. Compatibility
- 5. Freeze-Thaw and Wet-Dry Cycling
- 6. Elasticity and strength
7Materials Testing of Source Control Materials
8Field Emplacement
- Two Problem Areas - Surface Water and Groundwater
- Groundwater Technology - Hydraulic Barrier
(Surface Water Collection Trench and French Drain
System) - Surface Technology - Spray Applied Cover
9Construction of Water Collection Trench and
French Drain
10Water Collection Trench and French Drain
Construction
11Spray-Applied Capping Material
- Easy to spray-apply at site
- Reduces water and wind erosion
- Can be applied on webbed jute fabric or on the
surface of the pile
12(No Transcript)
13Primary Spray Coating
14Spray-Applied Urethane Material
15Final Spray-Application for the Surface Waste Pile
16Peerless Surface Waste Pile Ready for Top Soil
and Vegetation Application
17Application Problems and Causes
- Pinholes in wet areas
- Low temperatures caused curdling effect and
increased viscosity - Sagging on slopes
- Application without jute fabric
- Difficult to spray disturbed soil and around
large rock
18Conclusion and Recommendations
- The application of the French drain and the
Spray-applied urethane cover did improve the
water quality at the Peerless Mine. - The French drain intercepted much of the
groundwater. - The Spray-applied cap decreased infiltration and
increased erosion control.
19Activity III Project 12SULFATE-REDUCING
BACTERIAREACTOR DEMONSTRATION
20Introduction
- Thousands of abandoned mines in the Western U.S.
discharge water, commonly called acid mine
drainage (AMD), that is usually formed in the
mine where sulfide bearing minerals, particularly
pyrite, are exposed to oxygen and water as
described by the following chemical reaction - FeS2 15/4 O2 7/2 H2O ---gt Fe(OH)3
2SO42- 4H
21(No Transcript)
22Project Scope
- Conventional treatment strategies for AMD are not
feasible. - However, sulfate reducing bacteria (SRB) are
capable of increasing the pH and reducing the
load of dissolved metals in the effluent - Three bioreactors were built at the Calliope
site.
23Construction Overview
- Three reactors were constructed in the Fall of
1998. - Two bioreactors contain a passive pretreatment
section to increase pH of water before the AMD
enters the bioreactor chamber. Such a setting
will enable evaluating the effect of inducing an
optimal pH and EH into AMD on the efficiency of
the SRB.
24(No Transcript)
25(No Transcript)
26Bioreactors Components
- Each bioreactor consists of discrete
chambers each filled with either organic carbon,
crushed limestone, or cobbles. - For the pretreatment section, a chamber with cow
manure was included to lower the EH of AMD. - Crushed limestone provides buffering capacity to
increase the pH of AMD in the pretreatment
section. - Cobbles, placed in the primary treatment section
of the bioreactor, constitute a stable substrate
for bacterial growth.
27.
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32(No Transcript)
33Results
34The pH of treated AMD has been in the range of
7 - 10
35.Temperature of AMD changes seasonally with the
temperature of air.
36Oxidation-reduction potential (Eh) of the
influent has always been above 50 mV.
37(No Transcript)
38(No Transcript)
39(No Transcript)
40(No Transcript)
41(No Transcript)
42.
43.
44Microbial Capping Barrier for the Control of
Acid Mine Drainage
Activity III Project 14
45Microbial Capping Barriers
Surface application or subsurface injection of
bacteria and nutrient solutions.
46Microbial Capping Barrier
47Microbial Capping Barrier
O2
H20
C6H12O6
O2 C6H12O6
CO2 H2O
AEROBIC
C6H12O6 H2O
C2H3O2 H2 CO2
Fermentative
ANAEROBIC
C2H3O2 SO42-
H2S HCO3
M2 S2-
MS?
48Microbial Capping Barrier Demonstration
- Column Testing
- Crescent Mine tailings, initiated January, 1999
- Fox Lake tailings, initiated October, 1999
- Mammoth tailings, initiated March, 2000
- Field demonstration at Mammoth Site
- Construction of test cells complete
- Treatment to begin in Spring, 2000
49Crescent Mine Site
50Crescent Mine Site
- Elevated elements
- silver 32.6 mg/kg
- lead 4,570 mg/kg
- cadmium 3.67 mg/kg
- zinc 618 mg/kg
- copper 356 mg/kg
data from the Montana Department of State Lands
51(No Transcript)
52Crescent Tailings Sulfate-Reducing Bacteria vs
Time
53Fox Lake Tailings
- Elevated elements
- Aluminum 50 ppm
- Cobalt 0.3 ppm
- Copper 2 ppm
- Manganese 4 ppm
- Sulfur 720 ppm
- Zinc 20 ppm
54Fox Lake Mine Site
55(No Transcript)
56Conclusions from Column Tests
- Nutrient treatments were effective for decreasing
oxidation-reduction potential. - Nutrient treatment of acid-producing tailings
resulted in an effluent pH increase. - Nutrient treatments were effective for
stimulating Sulfate-Reducing bacteria within the
tailings.
57Mammoth Tailings Site
- Elevated elements
- Aluminum 400-1400 mg/kg
- Arsenic 167-572 mg/kg
- Copper 70-2500 mg/kg
- Lead 10-100 mg/kg
- Manganese 10-1000 mg/kg
- Zinc 20-222 mg/kg
data from the Montana Department of State Lands
58Upper Mammoth Tailings Site
59Upper Mammoth Tailings
60Mammoth Tailings Field Test
- Test cells
- Lined to ensure accurate measurement of influent
and effluent water volume and quality. - Treatment cell
- Will receive biocapping treatment beginning in
Spring, 2000. - Control cell
- Will be treated with an equivalent amount of
water to treatment cell.
61Test Cell Schematic
Water supply line
Control valve
Totalizing Flowmeter
Distribution laterals
Effluent Holding Tank
Lined test cell
Totalizing Flowmeter
Buried process control boxes
System effluent line
Surface Drainage
Effluent Valve
62Test Cell Excavation
63Liner Drain Field Installation
64Completed Test Cell
65Mammoth Field Test Status
Test cells constructed Background data
collected Initial nutrient treatment
applied Additional monitoring treatments will
be applied after Spring thaw
66Technology Benefits
- Natural biological process
- In-situ treatment
- Low application costs
- Complete treatment - acidity, metals
- Stabilization of tailings for revegetation
67Tailing Source Control Demonstration Project
68Problem
- Wind and water erosion are a major problem
because of the fine particle size of the tailings
material.
69 Mammoth Tailings Site
70Mammoth Tailings Site
71Project Objective
- Demonstrate the applicability of source control
technologies for in situ stabilization and/or
encapsulation of a surface waste pile to prevent
the influx of water, whether precipitation and/or
groundwater, thus decreasing AMD formation and
the erosion of the tailings material.
72Project Phase Approach
- Phase I - Mine Site Selection and Site
Characterization - Phase II - Materials Testing and Selection
- Phase III - Field Emplacement, Long-term
Monitoring and Technology Evaluation
73The Mammoth Tailings Site
74Showing the Erosion Channels at the Mammoth
Tailings Site
75Site Characterization
- Monitor Weather Conditions
- Monitor Soil Moisture
- Perform Soil Analysis (Physical and chemical)
- Perform Air Monitoring
- Perform Erosion Testing
76Materials Testing
- Source control materials were tested to ASTM
standards when applicable. Material Testing
Included - 1. Permeability
- 2. Acid Resistance
- 3. Erosion Testing
- 4. Compatibility
- 5. Freeze-Thaw and Wet-Dry Cycling
- 6. Elasticity and strength
77Materials Testing of Source Control Materials
78Field Emplacement
- Field Emplacement be performed during the Summer
2000 - The demonstration will consist of placing a
background and a test plot side-by-side.
79Conclusion and Recommendations
- The demonstration will be performed at the
Mammoth Tailings Site - Field Emplacement will occur during the Summer
2000 - At least two test plots will be used, a
background and a test plot - A decision on the materials tested will be made
during April and May 2000
80Support to SITE Mercury Project/In Situ Mercury
Stabilization Technologies Demonstration
Project Activity III, Project 19
81Background
- The In Situ Mercury Stabilization Technologies
Demonstration Project will show the effectiveness
of various technologies for in situ treatment and
stabilization for mercury-contaminated mine waste
material.
82Objectives
- The primary goal of the project is to conduct
comparative mercury stabilization tests using
mercury-contaminated material.
83Status
- The Sulphur Bank Mine has been identified.
- Characterization is being conducted
84(No Transcript)
85Clear Lake / Hermon Pit
86Hermon Pit (Lake)