Title: ST THOMAS MORE PARISH CHURCH BUILDING PLAN
1ST THOMAS MORE PARISH CHURCH BUILDING PLAN
2Program Outline
- St. Thomas More Building Plan
- Recent History/Work Efforts To Date
- Building Layouts Original vs. Phased Approach
- Draft Financial Plan
- Current Activities
- Communication Committee
- Finance Committee
- Next Steps
- Timeline(s)
- Now to December 2008
- Beyond
3Recent History
- The Committee
- (Fr Bob, Randy Dyer, Jeff Elekes, John Alexy,
Paul Prozinski, Joseph Kunthara, Terry Fewel,
Fred, Liebhaber, Cathy Williams (liaison for
Spiritual Life) - Meetings
- Findings
- Gym/Social Hall vs Remodel of Existing Church
- vs New Church
- New Church in Phases..
- New Finance Plan
4Proposed Building Site
5Original Church Design
Build within Nave
6New Church Phase Approach
750 Seats Same as Current Church
7Proposed Phase l and Future Phase ll
8Draft Financial Plan Summary 10-22-08
Lower End Upper End ANTICIPATED PROJECT
EXPENSES New Building Structure, Basement,
Taxes 3,487,000 3,487,000 Other Campus
Improvements Utilities Adj., Storm
Treatment, Electrical 431,000 717,000
Seismic Retrofit, Gym Floor, Furnishing
Deferred Necessary Project Soft Costs
Permits, Design, Engineering, Inflation 1,547,00
0 1,940,000 5,465,000 6,144,000
9Building Finance Committee, 10-20-08
10Draft Financial Plan Summary,10-22-08
Lower End Upper End ANTICIPATED PROJECT
REVENUES Previous Capital Campaign
850,000 850,000 5 year Planned
Set-a-Side/Savings 757,339 757,339 New
Capital Campaign Campaign/Pledges to Start
Sometime 2009 2,800,000 3,500,000 Mortgage to
Start in Year 6 1,057,661 1,036,661
5,465,000 6,144,000 FUTURE
MORTGAGE Principal Amount 1,057,661 1,036,66
1 Interest Rate 6.75
6.75 Number of Years 15
15 Monthly Mortgage Amount 9,400
9,200 Annual Mortgage Amount 112,800
110,400
11Short Term Building Timeline
10/15/08
12/15/08
9/15/08
10/1/08
11/1/08
12/31/08
11/15/08
12/1/08
9/1/08
1ST Letter Sent Out
Multicultural meeting. Complete Finance Plan.
Pastoral Council
12/5 3rd Letter Sent Out
Report Vote Results
STMP re-registration mailer
VOTE
2nd Letter Sent Out
Meetings After Masses
Meet With Parish Groups
12Long Term Building Timeline
Aug-Dec 2008
Oct 2010-Apr 2011
6 mos. Oct 2011
6 mos. Apr 2012
Dec 2008
Apr 2011
Feb-Mar 2009
Apr 2009
Oct 2012 Ground Breaking
Archdiocesan Approval
50 of projected cash Has been raised
Design Developed
Present Concept Drawings Estimates to Community
Permits/Construction Documents/Bidding
Schematic Design Completed
Parishioners Vote
Initiate Capital Campaign Fundraising Begins