Title: Introduction to Construction
1Introduction to Construction
2Introduction to Construction
- The construction course is one of continuous
development throughout 2, 3 or 4 years through - formal teaching of technical knowledge
- self directed learning, including working
individually and in groups of increasing
complexity
3Introduction to Construction
- The construction units are very career
orientated, giving technical information and
developing the skills required by industry. - Due to the increasing complexity of site
management, good technical and communication
skills and the ability to work in groups of
specialists are vital requirements.
4Introduction to Construction
- Typical skills are
- Good communicator
- Technical understanding
- Use of IT
- Group Working
- Business understanding
Drawing IT
Technical
Year 1
Skills
Reports
Managerial
Year 4
5Construction Practice
- Aims
- To introduce RISK MANAGEMENT, including Health
Safety and Environmental issues relevant to the
construction site. - To introduce the various parties involved in a
construction project. - To introduce the methods of working and
construction techniques.
6Construction Practice
- Methods
- Formal lectures
- Continuous project based learning
- Construction site visits
- Assessment
- 100 by project coursework plus site test
7Construction Practice
- Staff Lion Gate Room 1.33
- J Reynolds Careers advice, CEM Tutor
- A Petersen CEM Course Leader
- A Tutesigensi MSc Course Leader,Research
- Staff are only available during lecture and
tutorial times all questions outside of these
times should be sent via PROJECT TALK
8THE PROJECT LIFE CYCLE
9Hazard Risk Management
- Identification of hazards
- Elimination and control of risks
- Avoiding accidents and injuries
- Avoiding occupational ill health
- It is also about
- Avoiding abortive work
- Avoiding financial loss
- Professional responsibilities
- Complying with statutory obligations
- Avoiding fines and prison sentences
10Manage Human Resource
11Manage Construction Plant
12Manage Materials
13Hazard Risk Management
- Designers create many of the risks,
- Contractors can mostly only manage the risks,
- while the workers have to endure them.
- Clients must learn more about their
responsibilities and think about the risks. - Construction professionals are involved at all
stages. We need to work together to ensure
consistently high standards. - John Barber MA LLB CEng FICE MHKIE FCIArb
- Barrister to ICE
14Characteristics of the Construction Industry
- National Importance
- Difficult to define (DIY etc)
- Annual turnover varies widely
- About 80,000m to 100,000m per year
- Employs about 6 to 8 of national workforce
- Major Health Safety and Environment issues
15- PROJECTS
- Mostly unique
- Long duration
- Outside
- Price often fixed by competitive tender
- COMPANIES
- Client /Promoter - provides finance
- Designer
- Contractor
16- COMPANIES
- Clients - Government, Industrial, Commercial
- Designers - Consultant Engineers Architects
- Contractors - Civil Engineering, Building,
General - Specialists - Earthworks, Demolition, Steelwork
etc. - Size - 90 employ less than 20 people Small
firms carry out approx. 30 work Large firms
usually multi-disciplinary - Materials - Manufacture, Supplier
- Project Management - Quantity surveying etc.
17- The UK Construction Industry is rapidly
- moving towards -
- Design Build ( Operate ) Contracts
- Use of specialist sub-contractors
- Main Contractor acting in a management role
- Fast Track construction
- Construction courses have to reflect this
- changing model.
18History of a ProjectConstruction is the last
phase of a series of interrelated activities
- 1 Idea - the establishment of a need
- 2 Feasibility study
- Market forecast
- Investigations of various possibilities
- Planning
- 3 Comparison of alternatives economic appraisal
194 Recommendation of specific project 5 Site
Investigation 6 Detailed Design 7 Contract
preparation - Conditions - Roles
Responsibilities - Risk Allocation 8
Invitations to Tender 9 Approval of Tender 10
Construction
20Alternative Contract Methods
- 4 Recommendation of specific project
- 5 Site Investigation
- 6 Detailed Design
- 7 Contract preparation - Conditions - Roles
Responsibilities - - Risk Allocation
- 8 Invitations to Tender
- 9 Approval of Tender
- 10 Construction
Design Construct
Alternative Design
21Pre Construction Phase
- 1 Contractor receives invitation to tender
- 2 Preparation of tender - Site location, access
etc - - Ground Conditions
- - Method of working - plant, labour
materials - - RISK ASSESSMENT
- 3 Obtain costs from suppliers
- 4 Additional costs - Overheads, supervision and
financing - 5 Submit tender to Client or Engineer
22Construction Phase
- 6 Detailed programme of work
- 7 Health Safety and Environment plan
- 8 Construction
- - site accommodation, services, hoardings etc
- - site clearance, bulk excavation
- - excavate and construct foundations
- - construct frame / walls
- - cladding, roof, weatherproof
- - internal finishes, external services
23Design Build Management
24Examples of construction work
25Hendon Sewage Treatment Works - Environmental
26M8 Motorway Bridge Strengthening - Structural
27Jubilee Line Underground London - Transport
Tunnelling
28Chek Lap Yok Airport, Hong Kong Transport,
Environmental
29Rail Maintenance Renewal - Transport
30www.civil.port.ac.uk
31www.civil.port.ac.uk/pumice/cemg.htm
32www.civl.port.ac.uk/pumice/timetables/cctime.htm
33www.civl.port.ac.uk/pumice/timetables/cctime.htm
34- Tutorial for week 1
- access web page
- construction practice
- week 1 lecture notes
- project button under schematic to access map
- Incinerator project