Title: Bond Construction Update Board of Trustees


1
Bond Construction Update Board of Trustees
  • Long Beach Community College District
  • June 23, 2009

EDUCATE ? ENGAGE ? EMPOWER
2
Agenda
  • Completed Construction Projects
  • LAC Central Plant
  • LAC Learning Resource Center
  • LAC Q R Roof Replacement
  • LAC P Faculty Restroom Upgrades
  • PCC Central Plant
  • PCC Learning Resource Center
  • District Wide - Master Landscape Plan
  • District Wide - Energy Efficiency Project Phase
    2A
  • Current Upcoming Construction Projects
  • LAC South Quad Complex
  • LAC Building A, Student Services Retrofit
  • LAC Math Technology Building
  • LAC Parking Structure
  • LAC Building O Complex
  • LAC Infrastructure Improvements
  • LAC Q R ADA/HVAC Upgrades
  • PCC Industrial Tech Phase 1
  • PCC MDAB (Multi-Disciplinary Academic Building)

3
Current and UpcomingConstruction Projects
South Quad Complex Measure E 2002
  • Construction approx. 99 Complete
  • Space includes
  • Approx. 68,000 ASF
  • 32 modern classrooms and labs
  • 38 faculty offices
  • Executive offices
  • Multipurpose room
  • State of the art Board Room
  • Substantial completion anticipated Fall 2009

4
Current and UpcomingConstruction Projects
LAC Building A Student Services
Retrofit Measure E 2008
  • Construction Document phase in progress
  • Adds 6,018 ASF to existing building
  • Will house AR, Counseling, Health Services,
    Cashier, Transfer Ctr., etc.
  • Estimated start of construction Fall 2010

5
Current and UpcomingConstruction Projects
LAC Math Technology Building Measure E 2008
  • Completed Schematic Design
  • Will house Math and Culinary Arts instructional
    program as well as Reprographics
  • Estimated start of construction Winter 2013

6
Current and UpcomingConstruction Projects
LAC Parking Structure Measure E 2008
  • Spaces for 900 Vehicles
  • To be procured under Design Build method
  • Photovoltaic Electrical Generation Array on top
    level
  • To be located Southeast corner of Lot J adjacent
    to the Verizon building
  • Outfitted with single-axis tracking system
  • Minimum 450 KW output
  • Curriculum building opportunity
  • Exhibit classroom
  • Anticipated start of construction Spring 2010

7
Current and UpcomingConstruction Projects
LAC Building O Complex Measure E 2008
  • Property acquired December 2008
  • Two structures totaling 87,000 square feet
  • Occupants shall be IITS, BMT, Warehouse Facility
    (operational), ERD, and Foundation Office
    (Relocating July 6th)
  • Tenant improvements underway on ERD offices,
    elevator installation for bldg. 1
  • Potential rental spaces being assessed

8
Current and UpcomingConstruction Projects
  • LAC Infrastructure Improvement Projects
  • Measure E 2008
  • Completes 3.5 mile long chilled water line loop
  • Total annual estimated savings of 1.5 million Kwh
  • Provides system redundancy and mitigates
    operational impacts
  • Upgrades include Reclaimed Water, Domestic
    Water, Data, etc.
  • Majority of existing building HVAC systems to be
    connected to new infrastructure
  • Landscaping upgrades to be implemented in
    conjunction with infrastructure project phasing

9
Current and UpcomingConstruction Projects
LAC Q R ADA/HVAC - Measure E 2008
  • Complete building ADA upgrade includes
    restrooms, stair lift, etc. (Bldg. R)
  • All new infrastructure new piping, fixtures,
    etc. (Bldg. R)
  • Minor renovations to offices (Bldg. R)
  • Total renovation of locker/training rooms (Bldg.
    R)
  • HVAC upgrade includes new air handlers,
    ductwork, etc. (Bldg. Q R)
  • Update fire alarm system (Bldg. Q R)
  • Construction will be done in phases so as to
    minimize disruption of classes
  • Final construction documents to be submitted to
    DSA Fall 2009
  • Estimated start of construction Summer 2010

10
Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1 Measure
E 2002
  • Modern facility houses Welding Department and
    other trade programs
  • Construction is 78 complete
  • Replaces existing antiquated structures
  • New Northern face of the campus
  • Completion anticipated late Fall 2009

11
Current and UpcomingConstruction Projects
PCC MDAB (Multi-Disciplinary Academic Building)
- Measure E 2002
  • 90 construction documents submitted for review
  • Install portables for swing space at PCC Fall
    2009
  • Anticipated start of MDAB construction December
    2009
  • Project to be completed in two phases

12
Current and UpcomingConstruction Projects
PCC Building CC Retrofit - Measure E 2008
  • To be designed by Hill Partnership Architects
  • Houses the Fitness Center, Gymnasium, Weight
    Room, and Faculty and Staff Offices
  • Swing space to be located on PCC Campus (Bldg.
    GG)
  • To be completed concurrently with MDAB project
    phase 2
  • Anticipated start of construction Summer 2011

13
Current and UpcomingConstruction Projects
District Wide Electronic Signage Plan Measure
E 2008
  • District Wide Signage Plan complete
  • Currently in City Permitting phase
  • Final site locations determined
  • Construction completion of Marquee Signs Spring
    2010

14
Current and UpcomingConstruction Projects
District Wide Energy Retrofits - Measure E 2008
  • Phase 1 Construction of Central Plants
  • The chillers at the Central Plants were selected
    to achieve maximum efficiencies both at part load
    and full load conditions. The plant not only
    reduces the peak electrical demand at the campus
    but also offers lower emissions thus reducing the
    impact on the environment. Received rebates from
    Southern California Edison
  • LAC Central Plant
  • Designed to have (2) 600 ton centrifugal chillers
    and (1) 300 ton chiller with space for a future
    600 ton chiller. The Central Plant is designed to
    serve most of the existing buildings and all the
    new buildings at the campus.  
  • PCC Central Plant
  • Designed to have (2) 300 ton centrifugal chillers
    and (1) 300 ton multi-stack chiller. The Central
    Plant is designed to serve most of the existing
    buildings and approximately three new buildings
    at the campus.

15
Current and UpcomingConstruction Projects
District Wide Energy Retrofits - Measure E 2008
  • Phase 2A (Complete)
  • Lighting upgrades
  • HVAC upgrades
  • Controls upgrades
  • Pool upgrades
  • Water systems upgrades
  • Hot water system upgrades
  • Re-roofing
  • Phase 2B (Design Phase)
  • HVAC upgrades (Air Handlers, Zone upgrades, tie
    to Central plant, etc.)
  • Controls upgrades (FAC Approved temp. range
    70-75)
  • Lighting upgrades (Interior/Exterior/Lighting
    controls)
  • Hot water system upgrades
  • Irrigation controls
  • Window film addition

16
Current and UpcomingConstruction Projects
Financial Benefit of Energy Retrofit Program
17
Current and UpcomingConstruction Projects
Los Coyotes Property - Measure E 2008
  • Re-design current dirt lot to have 80 parking
    stalls with new lighting and drainage.
  • (Awaiting City feedback)
  • Re-slurry and re-stripe existing asphalt parking
    lot. (Done)
  • Replace elevator controls to bring them up to new
    current standards. (In process)
  • Installation of new automated front door.
  • (In process)
  • Building perimeter landscape upgrade.
  • (In process)

18
Current and UpcomingConstruction Projects
Upcoming Projects
  • LAC
  • Carson Street Median Fence Replacement
    (Construction completion July 2009)
  • Pool boiler upgrade (In process)
  • Replace current antiquated heating system with
    energy efficient boilers.
  • Bldg. F - Conversions of rooms F104 and F106 to
    new classroom space. (Awaiting structural
    calculations)
  • Expansion of Building I (In Design Phase)
  • Bookstore to be relocated here
  • Bldg. E Interior painting, carpet/tile
    replacement, and restroom upgrades
  • Bldg. K Roof extension over kiln area
  • CDC - Roof, carpet, and playground equipment
    replacement
  • PCC
  • Bldg. MM (FPP)
  • Exterior renovation (In Process utilizing
    scheduled maintenance funds)
  • Paint, windows, replacement of all exterior doors
  • Restroom ADA upgrade (In Process)
  • Bldg. JJ Add new landscaping around perimeter
  • Add additional parking at corner of PCH and
    Walnut

19
Planned Phasing of Future Projects
  • 2009-10
  • Parking Structure groundbreaking Spring 2010
  • South Quad Complex complete - Fall 2009
  • Tech 1 at PCC complete Fall 2009
  • Building O occupancy scheduled
  • Foundation July 2009
  • ERD, Warehouse, BMT and IITS January 2010
  • Begin infrastructure construction Fall 2009
  • Master landscaping implementation will follow
    this project
  • Submit FPP for M/N Project at LAC and MM Project
    at PCC and submit IPP for P Building at LAC and
    MM Project at PCC July 1, 2009
  • Install portables for swing space at PCC Fall
    2009

20
Planned Phasing of Future Projects
  • 2009-10 (continued)
  • Submit plans to DSA for Building A renovation
    August 2009
  • Submit plans to DSA for Building I (Bookstore)
    renovation September 2009
  • Submit plans to DSA for Building R (Gym)
    renovations Fall 2009
  • Begin retrofit of Z Building Fall 2009
  • Begin construction of Buildings DD and EE at PCC
  • Anticipating December 2009 start
  • Schematic design begins for Outdoor PE Labs at
    LAC Spring 2010
  • Anticipating swing space move for Building A at
    LAC June 2010
  • Marquees complete Spring 2010

21
Planned Phasing of Future Projects
  • 2010-11
  • Begin Building R (Gym) HVAC and ADA upgrades
    Summer 2010
  • Anticipating Spring 2011 completion
  • Begin construction of Building I (Bookstore) and
    move to portable swing space Summer 2010
  • Retrofit completion of Building Z Summer 2010
  • Submit plans to DSA for Outdoor PE Labs Fall
    2010
  • Begin construction of Building A at LAC Fall
    2010
  • Begin Schematic Design for Buildings C and F at
    LAC
  • Submit plans to DSA no later than Summer 2011

22
Planned Phasing of Future Projects
  • 2011-12
  • Infrastructure project complete at LAC Summer
    2011
  • Submit plans to DSA for Math/Technology Building
    at LAC Summer 2011
  • Begin construction of Buildings AA, BB and CC at
    PCC Summer 2011
  • Construction completion of Buildings DD and EE at
    PCC Summer 2011
  • Begin construction of Outdoor PE Labs at LAC
    Summer 2011
  • Anticipating Spring 2012 completion
  • Anticipated construction completion of Building I
    (Bookstore) at LAC Fall 2011
  • Anticipated construction completion of Parking
    Structure at LAC Fall 2011

23
Planned Phasing of Future Projects
  • 2012-13
  • Move Buildings C and F programs into Swing Space
    (M/N Building) and begin construction Summer
    2012
  • Anticipated Construction completion of Building A
    at LAC Summer 2012
  • Submit plans to DSA for M/N Building at LAC and
    Building MM (Phase 1) at PCC Summer 2012
  • Begin Schematic Design for Building P at LAC and
    Building MM (Phase 2) at PCC Summer 2012
  • Submit to DSA Spring 2013
  • Begin construction of Math/Technology Building at
    LAC Winter 2013

24
Planned Phasing of Future Projects
  • 2012-13 (continued)
  • Begin Schematic Design for Building D and E
    renovations Fall 2013
  • Anticipated Construction completion of Buildings
    AA, BB and CC at PCC Spring 2013
  • Submit plans to DSA for Building GG at PCC
    Summer 2012

25
Planned Phasing of Future Projects
  • 2013-14
  • Begin construction on Building GG at PCC Summer
    2013
  • Anticipated Construction completion of Buildings
    C and F at LAC Fall 2013
  • Begin construction of Buildings M/N at LAC and MM
    (Phase 1) at PCC Fall 2013
  • Submit plans to DSA for Buildings D and E
    renovations at LAC Fall 2013
  • Schematic design for Performing Arts Building
    (GH) and Building R at LAC Spring 2014

26
Planned Phasing of Future Projects
  • 2014-15
  • Anticipated Construction completion of
    Math/Technology Building at LAC Summer 2014
  • Begin construction on Buildings D and E at LAC
    Fall 2014
  • Submit plans to DSA for Performing Arts Building
    and Building R (Gym) at LAC Spring 2015
  • Anticipate construction start Spring 2016
  • Anticipated construction completion of Buildings
    M/N at LAC and MM at PCC late Spring 2015
  • Begin construction on Buildings P at LAC and MM
    (Phase 2) at PCC Spring 2015

27