Mills Peninsula Health Services Hospital Replacement Project - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Mills Peninsula Health Services Hospital Replacement Project

Description:

Demolish existing hospital after new construction is complete. 20 acre site. Hospital 450,000 SF base isolated foundation and steel structure ( 1 mile east ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 12
Provided by: tur763
Category:

less

Transcript and Presenter's Notes

Title: Mills Peninsula Health Services Hospital Replacement Project


1
Mills Peninsula Health Services Hospital
Replacement Project
Speakers notes Burlingame, CA ( 5 miles south
of SFO airport ) Full campus replacement New
parking structure 830 stalls New Hospital and
New Professional Office Building (POB) Demolish
existing hospital after new construction is
complete 20 acre site Hospital 450,000 SF base
isolated foundation and steel structure ( 1 mile
east of San Andreas Fault Line ) POB 150,000
SF un-bonded braced frame 241 patient rooms 70
shelled rooms 10 Operating Rooms
2
Selected Pics from Mills
3
Look familiar??
4
Last Planner System
  • This is the second step in Last Planner System -
    a reverse phase schedule meeting
    collaboration with foreman andother stakeholders
    using pull scheduling not push
  • Look at one foreman even reading drawings to make
    their plan realistic and reading them before
    showing up on job site..novel idea

5
Team after a Rev. phase schedule meeting
smiling!
6
Michael N. KennedyProduct development for the
lean enterprise author. Dallas.
Knowledge management and design of systems with
tradeoff curves Book NBBJ and HGA and others
are reading together as a firm Or on integrated
project teams in a study action team.
7
Job site status reporting
People do what you measure.. In this case, it is
percent plan complete PPC Reliable every
day!
8
Planning ensures smooth flow
Schedules at Turner when Using Last Planner
System
Proposal Schedule
1
Developed collaboratively with all stakeholders
in room at once. Covers a 3 to 4 month duration /
group of activities. This is to plan work with
more accuracy and detail than the Updated
Baseline Schedule may show.
Baseline Schedule
2
Updated Baseline
3
In contract w/ Owner
Revised Baseline
4
Use at weekly meetings
Actual starts / finishes, complete added to
Baseline Updated Baseline
Reverse Phase Schedule
4a
Review daily, score, learn
Added activities, changed durations, logic,
sequence of work Revised Baseline
Six Week Look- Ahead Schedule
4b
Weekly Work Plan
5
Check it w/ 4b,etc
9
Productivity using Last Planner
Measure productivity Percent Plan Complete (PPC)
PPC
PPC
PPC 50
10
George Zettel Will Lichtig
11
First Turner job using Last Planner system
Sutter Davis MOB II.