AMS02 tracker mechanics status of construction, assembly, integration - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

AMS02 tracker mechanics status of construction, assembly, integration

Description:

Full test at each step with RA source and noise control ... (Kynar heat shrink tubing) to confine the threads of the copper braids. ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 37
Provided by: amsC3
Category:

less

Transcript and Presenter's Notes

Title: AMS02 tracker mechanics status of construction, assembly, integration


1
AMS-02 tracker mechanicsstatus ofconstruction,
assembly, integration
Divic RAPIN, UniGe
  • Production
  • - Ladder integration
  • - Installation on planes
  • Inner tracker integration
  • - Assembly
  • - Cabling
  • - Temperature sensors
  • Quality control
  • - Examples

2
General view of Silicon tracker
  • 5 planes, 8 layers
  • Plane 1, layer 1
  • Plane 2, layers 23
  • Plane 3, layers 45
  • Plane 4, layers 67
  • Plane 5, layer 8
  • 192 ladder modules

3
Ladder Assembly Status (Perugia-Geneva)
  • ASSEMBLY
  • 210 ladders build
  • PHASE 2 hybrid box legs gluing
  • completed
  • EMI SHIELDING
  • ( kapton foil wrapping)
  • 31 ready for process
  • Full test at each step with RA source and noise
    control

4
Installation of ladders on support planes (UniGe
clean room)
Plane 3 being stored (under Nitrogen)
Details of fixation on both sides
5
Status of installation of ladders on planes
  • Plane 1
  • - layer 1, 30 ladders to be
    done
  • Plane 2
  • - layer 2, 24 ladders completed
  • - layer 3, 22 ladders completed
  • Plane 3
  • - layer 4, 20 ladders completed
  • - layer 5, 20 ladders completed
  • Plane 4
  • - layer 6, 22 ladders completed
  • - layer 7, 24 ladders completed
  • Plane 5
  • - layer 8, 30 ladders 4/5 done

6
Preliminary tracker assembly at Uni-GE
Dry assembly of shells-planes was made before
installation of ladders on planes.
7
Assembly of the inner tracker at UniGe
  • Set-up for storage insertion into the magnet.
  • The various lengths of the cables were
    calculated. Cables tested in UniGe
  • Cables must be installed before the supporting
    shells.
  • Extra length must be attached to temporary
    supports.

8
Cables (2192 flat cables)
  • Cabling scheme, routing, topology and various
    lengths were studied and defined in July 2003
    using mock-up.
  • Manufactured by GA in Italy.

Before installation, on all cables
- Electrical tests were performed. - Cable
length checked (by weight). - Cables sorted
according to the integration sequence.
Filipe Da Silva
9
Vibration tests of the cables and connexions
Mechanical behaviour and fixation scheme were
studied thanks to the vibration table
of University of Bern. Mr Beat Zahnd
cable alone
cable bundle
connexions/cables for a 3-layer column
  • No problems found for cables, connectors and
    connexions
  • Distance between cable fixations were determined
    (for vacuum case)
  • Cable supporting scheme between vacuum case and
    crates still needs study

10
Inner tracker assy at Uni-GE A new clean room
(véranda) was installed to accomodate the Durga
assembly jig (formerly called ETHZ Frankenstein
machine), after modifications for AMS2 geometry.
11
Plane 2 in place, supported by its ring
Temporary cable support
Support ring
12
Insertion of plane 3
thermal connexions
13
Insertion and thermal connexion of plane 4
14
For a better support, vertical bars are added to
replace the shells during cabling activities
Last component
Lower conical flange
15
Cabling Preliminary work
Documentation
Definition of procedures
Tooling
V0.1
V3.5
16
Cabling procedure for half column (simplified)
For 3 ladders
  • Check cables allocation
  • Weight and clean the cables
  • Slide and plug the cables
  • Ladder connexion test (darkness)
  • - pedestals pattern read-out and check
  • - low voltage bias check
  • Pack and secure extra cable length
  • Documentation

17
Installation and test of the first column (M13)
18
Storage of the extra length of cables
Lower cable support
19
We are proceeding with cabling
Manfred Willenbrock Samuel Delaere
20
Temperature sensors for inner tracker
  • Facts and wishes
  • Plane 3 is the hottest place and cooling loop is
    at Tconst.
  • TTCS can accommodate read-out of additional
    Dallas sensors.
  • Any connexion topology is acceptable chain,
    star, mixed
  • Redundancy impose two identical chains.
  • Temperature measurements for each octant on each
    plane.
  • Read-out chains are prepared and tested before
    installation.
  • Constraints from mechanics
  • No possibility for sensor cables to cross the
    shells.
  • Apertures through the planes usually occupied by
    flat cables.
  • Only apertures on Y (7-wafer ladder columns) are
    available.
  • Even turning around a plane between thermal bars
    and shells is difficult.

21
Example of a double chain of Dallas sensors
Chains prepared by A. Koulemzine for TOF
Connector cannot be slided trough the planes
using free apertures
Sensors can
22
Free apertures
Difficult locations (2 mm clearance from
the edges of the bars to the shell)
23
Possible locations for sensors
cables
PL2
No cables through plane 3
PL3
PL4
Possible places where to glue sensors on thermal
bars
cables
24
Choice of the tracker collaboration for inner
tracker July 18
  • Sensors for outer planes and cooling loops will
    be decided and installed later
  • Use a double chain with 1 connector and 4 or 6
    pairs of sensors.
  • Fix the connector on an empty slot of top conical
    flange and slide the chain downward trough column
    1P or 1M.
  • Install (glue) the sensors on thermal bars on the
    bottom side of plane 3.
  • Build special pieces to hold the cables within
    the 2 mm clearance in the delicate locations and
    glue them to thermal bars.
  • Other topologies cannot be installed without
    cutting the chain

25
Quality control Summary
  • Ladders
  • data base with status, results of electric tests
    and comments
  • manual records of inspections and actions
  • Integration of thermal bars on planes
  • manual records
  • Integration of ladders on planes
  • manual records (graphics)
  • electronic tests on data base
  • Tracker integration
  • well defined procedures
  • trace is kept (operator, date, comments, etc...)
  • Cabling
  • idem
  • electric tests

26
Integration of thermal bars on planes
Quality control example
Control sheet for each bar pair
Control sheet for a plane
27
Part of control document used during integration
of ladders on a plane
Example
28
Control sheet and procedure for cabling
Example
29
ExampleProcedure and control for cable connexion
30
A new procedure was needed due to an unforeseen
problem ...
A non-conformity procedure was opened ... (report
is being written)
31
Some of the thermal connectors (copper braids)
suffered from the compression applied during
their connexion.
  • All damaged threads are broken on one side only
  • None found to be loose

Use of space qualified schrumpfschlauch (Kynar
heat shrink tubing) to confine the threads of the
copper braids.
Tests on prototypes
32
The procedure is applied to all connectors
- Preliminary cleaning with micro vacuum
cleaner - Nothing found in the filter
33
Near future integration operations at UniGe
  • Complete the cabling, tests and cable securing
  • Installation of thermal sensors
  • Mounting shells
  • Packing (in Nitrogen) the inner tracker in a box
    convenient for storage and transport to CERN.
  • Star tracker support bonding on plane 1
  • Completion of outer planes (storage in Nitrogen)
  • Evaporators pre-assembly

34
Preliminary precaution Make sure that the
heat load on the
detector electronics is acceptable
  • One side of the connectors is glued on the
    thermal bar
  • Installation and heating (175 deg) must be done
    in situ.
  • Possible heating of the hybrid circuit was
    tested.
  • No problems since heating time is always less
    than 30 seconds.

35
Procedure and controls for heat shrink tubing
installation
36
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com