Rebranding NHS Connecting for Health - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Rebranding NHS Connecting for Health

Description:

Porter Novelli campaign - Patient and Public awareness and rights ... Worcs/Coventry Community probably live with Damadian release. Coventry Admin pilot July ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 15
Provided by: colinb8
Category:

less

Transcript and Presenter's Notes

Title: Rebranding NHS Connecting for Health


1
National News
  • Rebranding NHS Connecting for Health
  • John Bacon SRO role mainstream performance
    management ?
  • Some admission of delays
  • Spine decoupling project
  • Porter Novelli campaign - Patient and Public
    awareness and rights
  • Integrating NPfIT / 10 HIC / workforce, combined
    benefits plans
  • Do Once and Share

2
Agenda
  • Early PASs
  • P1R2
  • PACS
  • Choose and Book
  • SUS
  • Infrastructure
  • Communications
  • Programme Management

3
DIP and Contractual Update
  • Still a funding gap
  • Current WMS risk is c3m over contract life
  • Contractual only for early projects (inc. Worcs
    CMH)
  • Other 2005 projects indicative final dates to
    be agreed by end of May
  • Planning for 2006 (P1R2) in October/November
  • CSCA achieved Bundle Key Milestone (BKM) with
    caveats
  • CCN signed around CSC delays, Authority delays
    and extra functionality

4
WMSHA Early PASs
  • Wave 1 timetable reviewed post BKM in light of
    numbers of bugs found in late CfH testing
    /deployment testing
  • Worcs/Coventry Community probably live with
    Damadian release
  • Coventry Admin pilot July
  • Worcs Pilot August Full September
  • UHCW under review
  • Common issues
  • EUT environment stability much improved, but
    further testing to be completed
  • lack of process around fixing bugs discovered in
    testing and live running
  • WMS escalation to Cluster
  • Technical environments
  • Quality of software and level of bugs
  • Bug-fixing (process timliness)
  • Compensation
  • Incremental delay and inability to plan properly
  • Strategic Instances and Legitimate Relationship
    Service (LRS)

5
Release Scoping
6
WMSHA Early PAS risks
  • Availability of tactical and strategic instances,
    migration approach SHA IT Programme Board
    approved employing a project manager
  • Uncertainty around LRS availability leads to
    issues around sequence/priority/timescales of
    wave 2 projects
  • End User Training environments
  • Cluster have purchased 150 available by mid
    June
  • allocation method (capitation to SHA) means we
    will need to purchase more
  • Will review level of need in light of replanned
    wave 1 projects
  • Possibly 12 extra, possibly costing 600k (over 5
    years)

7
P1R2 and Clinical Systems
  • P1R2 delayed to December 05
  • Northern Clusters working group to look at NPfIT
    plan to de-risk clinicals by loosening coupling
    of spine and local NCRS
  • GP systems
  • CSC/Cluster working through practicalities of how
    to implement recent announcements
  • Hosted EMIS PCS (Alternative GP system) possibly
    from end of year
  • GP Lorenzo still the strategic solution

8
PACS
  • Business cases should be complete by now
  • Capital requirements to be notified to SHA by
    16/5 for case to go to capital group on 19/5
  • UHCW situation is a significant caveat

9
Choose and Book
  • LHCs have submitted revised rollout plans
  • SHA ABC taskforce visiting all PCTs
  • Directory of Service should be complete by end
    June
  • 30 GPs should be registered by end June
  • PCTs to have commissioning rules in place by end
    June
  • ATOS Project manager allocated as an SHA resource
    need to agree how to best use this resource,
    and the rest of the CB resource

10
Secondary Uses Service
  • Rollout delayed, and timescale unclear now
    expect phased rollout from June
  • Training plan being developed nationally
  • Outstanding issues re effective information
    support for Payment by Results
  • Next User group meeting 6/5 (April cancelled)

11
Infrastructure
  • Registration Authorities progressing
  • Most WMS organisations now have registered RA
    Managers
  • SHA team registering remaining staff now, and
    providing support
  • HR not universally keen
  • But this will be pursued
  • Role based access control (RBAC) proving complex
    and time-consuming
  • workshop held
  • more NHS input sought
  • will improve (but not necessarily quickly)
  • Some problems with RA equipment supply
  • Need to manage to ensure PAS projects GPs both
    done

12
Infrastructure
  • N3
  • Timely delivery of connections still unacceptable
  • However, BT nominally achieved target of 6000
    connections, but not all signed off by NHS.
  • Still significant outstanding issues re
  • Group connections (incorporating COINs and VPNs)
  • Support for PACS
  • Keith Boardman leading for SHA and escalating
    issues with NPfIT/Cluster
  • Service Desks
  • Processes for interaction between Local/NPfIT/CSC
    service desks are being clarified
  • Some training (ITIL) available
  • Service Desk Managers forum set up to work
    through issues and share good practice

13
Communications
  • National work Porter Novelli
  • Information/campaign for NHS staff from June/July
  • Public campaign from Autumn linking to
    deployment projects

14
Programme Management Governance and Programme
Management Review
  • Reviews at Cluster, WMSHA all issued in draft,
    discussed at Boards
  • WMS workshop on implementation of recommendations
  • Will lead to increased standardisation and rigour
    in
  • Risk and issue management, escalation
  • Change Management
  • Planning
  • Monitoring and Reporting
  • Decision making clarity of authority at each
    level
  • Detailed, resourced action plans to be debated at
    April SHA IT Programme Board

15
Longer Term Priorities
  • Interim solutions, business systems etc
  • Change Management / Strategic alignment/ HICs etc
  • NHS resources and capacity
  • Shared services / effective support
  • SHA Business Plan
  • SHA Information Strategy (Audit requirement)
Write a Comment
User Comments (0)
About PowerShow.com