Decommissioning and prospective new build organisational and planning issues, UKAEA achievements PowerPoint PPT Presentation

presentation player overlay
1 / 21
About This Presentation
Transcript and Presenter's Notes

Title: Decommissioning and prospective new build organisational and planning issues, UKAEA achievements


1
Decommissioning and prospective new
buildorganisational and planning issues, UKAEA
achievements

17th July 2008 Manchester
Presentation to KNOO
2
Contents
  • UK decommissioning NDA model, achievements
  • Energy gap?
  • New build reactor types and sites
  • New build security and timing issues
  • UKAEA recent decommissioning achievements

3
Decommissioning - Introduction
  • In 2002 the government published the Managing
    the nuclear legacy a strategy for action White
    Paper.
  • This led to the formation of the Nuclear
    Decommissioning Authority (NDA) under the 2004
    Energy Act.
  • The NDA are responsible for the decommissioning
    the legacy from existing civil nuclear plants.
  • Government White Paper (Cm 7386) published this
    month suggests for volunteer communities to come
    forward for geological waste disposal sites.

4
NDA decommissioning model
5
Clustering and Schedule
  • LLWR contract let
  • Sellafield contract due to be let this autumn
  • Magnox South (Bradwell, Berkley, Sizewell A,
    Hinkley A, Dungeness A) competition now on hold
    pending a review of competition strategy
  • Remaining clusters (Magnox North,
    Harwell/Winfrith, Dounreay)

6
NDA Achievements
  • Common UK-wide approach to decommissioning
    programme planning
  • Management contract for LLWR let in March.
  • Preferred bidder announced for Sellafield.
  • Formation of Site Licence Companies Sellafield
    Ltd, DSRL Ltd, Magnox Electric Ltd.
  • New entrants into supply-chain

7
NDA spends
  • NDA budget is 8.6bn for 2008-11 (3 years).
  • Funding priority based on hazard reduction.
  • Highest hazards are primarily at Sellafield.
  • Funds now diverted from low hazard sites (e.g.
    Harwell, Winfrith) to address the high hazards.
  • Estimated total cost increases as the NDA gets
    more of an understanding of the true tasks ahead.
    Current estimate is 73bn.

8
Reactor locations
Decommissioning in progress Magnox AGR PWR
Hunterston A
Dounreay
Chapelcross
Calder Hall
Sizewell A
Trawsfynydd
Harwell
Berkley
Bradwell
Hinkley Point A
Dungeness A
Winfrith
9
UK energy mix 2007
Source National Grid
10
Energy gap?
  • By 2020, 12GW of fossil fuel power stations, and
    2 (or 7.4GW) nuclear generation will have ceased
    generating electricity.
  • 14GW of fossil fuel power stations planned in the
    near term, and a further 2GW from wind farms and
    imports.
  • Security of gas supply is uncertain in the
    future, and energy usage is increasing.
  • Potential shortfall is small, but further nuclear
    closures from 2020 mean more capacity needs to be
    ready.

11
Potential new build to fill the energy gap
  • Government White Paper on Nuclear Power (Cm 7296)
    and more recently, Business Secretary John Hutton
    say that industry should look to go further than
    just replacing existing nuclear capacity.
  • Nuclear seen as clean alternative to fossil fuels
    to provide baseline generation, with a secure
    fuel supply.
  • New build reactors would produce far less waste
    than existing designs.

12
Types of new reactor
  • 4 Gen III reactor designs submitted to the HSE
    NII for the Generic Design Assessment process
  • Westinghouse Advanced Power Reactor (AP1000)
  • EDF/AREVA Evolutionary Power Reactor (EPR)
  • AECL Advanced Candu Reactor (ACR-1000)
  • GE Economic Simplified Boiling Water Reactor
    (ESBWR)
  • All 4 passed the first stage in March 2008, but
    AECL withdrew from the process in April.
  • 3 designs now into the detailed review stage.

13
New build designs
GE ESBWR
EDF/AREVA EPR
Westinghouse AP1000
14
New-build sites
  • The likely sites for new build are on sites of
    existing stations, with good connections to the
    grid.
  • Sites in Scotland are not likely.
  • The favoured sites are likely to be
  • Sizewell
  • Hinkley Point
  • Bradwell
  • Dungeness
  • New sites would now be considered too.

15
Reactor Comparison
Comparison of reactor types in terms of waste
production and efficiency.
Sources Magnox, AGR, PWR from the NDA, AP1000
from CoRWM
16
Impact on security
  • New-build designs use fuel more efficiently
    (greater burn-up). This leads to a lower
    volume, but more radioactive spent fuel.
  • High radioactivity makes it harder to handle.
    Two-edged sword.
  • A greater burn-up leads to less proliferation
    issues (less weapons-grade plutonium is
    generated).
  • New-build designs can all take MOX fuel, which
    can be fabricated using plutonium from military
    applications or spent fuel, again reducing
    proliferation risk.

17
Timing Implications
  • New build plants would need to come on stream
    before 2020 to avoid energy shortages.
  • Firm decisions with respect to planning and
    pre-permissioning Regulation needed soon.
  • If nuclear, then capacity to build key components
    (pressure vessels) is severely limited
    world-wide, and many other countries are going
    nuclear too.

18
UKAEA achievements
  • Dounreay Shaft isolation project ahead of
    schedule
  • Last of the radioactive isotopes removed from the
    Pile 2 reactor at Windscale
  • 2007 MAST campaign completed with records for
    heating power and plasma currents achieved
  • Last of the 1500 tonnes of liquid sodium removed
    from the Prototype Fast Reactor
  • Formation of the Harwell Science and Innovation
    Campus
  • Safety Dounreay has clocked up more than 3m man
    hours without a Lost Time Accident.

19
UKAEA achievements
20
Summary
  • Costs for the decommissioning of existing
    facilities can be reduced.
  • New-build seen as a key part of UK energy mix in
    the future.
  • Timescales are tight to avoid a potential energy
    gap.

21

Thank you
Write a Comment
User Comments (0)
About PowerShow.com