FNAL Factories - MP9
Hand Soldering
Hand Soldering
Tension Testing
Cathode Storage
Anode Stoage
2
FNAL Factories - MP9
Ionized Air Cleaning
Chamber Assembly
Framed Chamber
Elect./Cables Inst.
not a FNAL operation
3
FNAL Factories - MP9 QA/QC
  • Proper Tension on 200 mm wires
  • Hand-installation

Problem
Discrepancy Report
RD
Tooling Development
Solution
4
Manpower Experience - FY00
  • Inspection
  • See MATERIALS discussion
  • Process Engineering
  • Responsibilities
  • Edit and finalize travelers/assembly
    procedures/operating procedures for all chambers
    and all critical toolings. Handle FNAL travelers
    in the production process.
  • Provide documentation for process control. Edit
    and handle Discrepancy Reports (DR).
  • Check incoming/outgoing kits from the various
    FNAL factories (Lab 8, MP9).

5
Manpower Experience - FY00
  • Engineering Drafting
  • Responsibilities
  • Chamber and Tooling Drawings Finalization/Release
  • Changes as approved by the L2-L3 Managers.
  • Technical Supervision of Production Aspects
  • Assembly Technicians
  • Responsibility
  • Chamber Assembly
  • Chamber Fixing
  • No pressing ned to increase Technical Manpower
    for Production purposes in the first 6 months of
    FY00

6
Production Readiness Review
  • Production Readiness Review - Dec 16 99
  • Assess the preparation of the MP9 factory to
    start chamber production based on the present
    design
  • Factory Organization
  • Design and Production Flow
  • Tooling Readiness
  • Safety
  • QA/QC Program, Procedures, Travelers and
    Training
  • Manpower Management/Estimates
  • Schedule
  • Approval for ME234/2 Pre-production and Prototype
    Production Schedule
  • 4 ME234/2 Chambers produced in Jan.-Jun. 00
  • 4 Prototypes produced in the same time period.

7
Production Readiness Review
  • Issues
  • Electronics/Alignment System Integration on
    Chamber frames
  • In progress, milestones in Place for Jun. 00
  • Train and Establish Technical Pool in MP9
  • In progress
  • CERN Approval for all Materials
  • In progress
  • Roles definition for FNAL - PNPI/IHEP and FNAL -
    Fast Sites relationships
  • FNAL-IHEP/PNPI in progress, starting from MOU
  • FNAL - Fast Sites to be defined by L2-L3 Managers
  • Test of first Chambers at FNAL
  • In progress
  • Configuration Control Sign-off will mark the
    beginning of ME234/2 Production at FNAL

8
Schedule
9
Summary and Conclusions
  • Panel Factory in full Production. Manpower
    requirement and production speed within
    estimates
  • Chamber Procurement under control and within
    cost.
  • Assembly Factory ready to start after formal
    sign-off at the conclusion of the integration
    effort.