Title: Joint Modular Lighter System Program Status


1
Joint Modular Lighter SystemProgram Status
  • JLOTS RD SYMPOSIUM V
  • 2 February 2000
  • Cliff Lederer
  • Naval Facilities Engineering Service Center
  • JMLS Deputy Technical Manager

2
JMLS Definition
  • A ship-to-shore, sea state 3, in-stream offload
    capability for Army Transportation Group and
    Naval Beach Group

3
Modular
  • Flat End Module (clockwise) female end, male end,
    and UHMW non-skid deck

4
Modular
5
JMLS Navy Deployment
  • Maritime Pre-positioning Force
  • Navy deploys JMLS on deck
  • Use JMLS primarily for
  • LO/LO of MPF

6
JMLS Army Deployment
  • Afloat
  • Pre-positioning
  • Stocks
  • Army deploys JMLS in container cells of T-ACS
  • Use JMLS primarily for RO/RO of LMSR

7
JMLS Subsystems
  • Warping Tug (WT)
  • Causeway Ferry (CF)
  • Roll-On/Roll-Off Discharge Facility (RRDF)
  • Air Cushion Vehicle Landing Platform (ACVLAP)
  • Floating Causeway (FC)

8
Warping Tug
9
Causeway Ferry
10
Roll-On/Roll-Off Discharge Facility
11
Air Cushion Vehicle Landing Platform
12
Floating Causeway
13
Status
  • Design and Phase II manufacturing complete
  • Test and Evaluation
  • Acquisition
  • ORD staffing complete final approval imminent
  • Acquisition Planning underway

14
Design
  • Significant User input via Integrated Product
    Teams
  • Different causeway ferry for MPF required
  • JMLS is larger and heavier than NL (i.e., carry
    less)
  • Contract baseline CF is 48- by 155-ft ? 2 CF per
    ship lt required
  • 32-ft wide by 117- or 155-ft long ? 4 CFs per
    ship required
  • disregard this slide - not shown

15
Test and Evaluation
  • Calm Water Connections at BMI
  • July/Aug 99
  • First Open Water Connection Tests at Little Creek
  • Sept/Oct 99
  • Contractor Demonstration
  • Jan - Feb 00
  • Military Utility Assessment
  • Mar - May 00
  • End of ACTD
  • OPEVAL
  • FY 01

16
Calm Water Connection Tests
17
Calm Water Connection Tests
  • Successfully connected flat end modules
    end-to-end and side-to-side
  • Conducted User Familiarization at end of test
    period

18
First Open Water Test
  • Connection tests of flat end modules
  • Gain experience
  • Maximum encountered was high SS2 (3.2 ft)
  • Results were encouraging

19
First Open Water Tests
20
Contractor Demonstration
  • Arrival of RRDF at NAB Little Creek on 8 January
    2000

21
Contractor Demonstration
  • Arrival of Warping Tug and Causeway Ferry on 12
    January

22
Contractor Demonstration
  • Causeway Ferry Beach Operations

23
Current JMLS Acquisition Strategy
FY02
FY00
FY 01
2Q/FY00 3Q/FY00 4Q/FY00
1Q/FY01
2Q/FY01 3Q/FY01 4Q/FY01
1Q/FY02
ACTD
Military Utility Assessment
Contractor Demos
Milestones
Approval for Full Production (AFP)
Approval for Limited Production
Contract Awards
LRIP Hardware
Full Production Options
LRIP Hardware Design/Manufacturing Maturation
Operational Evaluations
FC
WT/CF RRDF ACVLAP PIER

24
Challenges
  • Schedule
  • Design Issues
  • Ship space
  • Power module mechanical systems
  • In terms of military utility, the design looks
    promising

25
Summary
  • CINCs require a SS3 JLOTS capability
  • JMLS program challenges (technical, schedule,
    funding, etc.) exist but are being managed
  • Initial TE success with calm water and near SS3
    connections
  • Contractor Demonstration in progress
  • JMLS is
  • SS3 capable
  • Service interoperable
  • Intermodally transportable