Title: Slide 1
1Determination of OGIP for Wells in
Pseudosteady-State-Old Techniques, New Approaches
By Mazher Ibrahim and R.A. Wattenbarger Texas
AM University M. Wael Helmy, El Paso Production
2Problem Statement
3Problem Statement
Real gas pseudo-pressure
4Problem Statement
Non- Linearity
5Problem Statement
6Objectives
- Present the shortcoming in using initial
properties - Present new Pseudotime
- Present new Pseudotime and superposition
- Calculate accurate OGIP with
- Properties change with pressure
- Rate variations
7Simulation Case 1 Constant Rate
8Simulation Case 1, Constant Rate
Simulation Data
9Production History for Simulation Case 1
10m(pi) - m(pwf )/qg vs. t Plot
Non-Linearity
11OGIP from Tangent Slope
12New Method Normalized Pseudotime
13New Normalized Pseudotime
Normalized Pseudotime take into account the
effect of properties change with pressure
1. Porosity
2. Update initial water saturation
3. Update total compressibility
14Dm(p)/qg vs. t and tn
15Simulation Case 2 Variable Rate
16Production History for Simulation Case 2
17Superposition Time (Super-t)
Superposition take into account the effect of
rate and pwf change
PSS Superposition Equation
18m(pi) - m(pwf )/qg vs. Super-t Plot
Non-Linearity Problem (No unique straight line)
19New Method Normalized Pseudotime and
Superposition
20New Method (Super-tn)
Normalized Pseudotime and Superposition take into
account the effect of- 1. Rate and pwf
change 2. Properties change with pressure
Normalized Pseudotime and Superposition
21m(pi) - m(pwf )/qg vs. Super-t and Super-tn
22m(pi) - m(pwf )/qg vs. Super-tn
23VBA Program
Output of Program
Data Required
Stop
24Field Case 1 Well H-58
25Reservoir Data for Well H-58
26Production Data for Well H-58
Gp 6.29 BscfProduction time 532 day
27m(pi) - m(pwf )/qg vs. Super-t Super-tn
28OGIP from Iteration Procedures
29Reservoir Data for Well H-60
30Production Plot for Well H-60
Gp 5.003 BscfProduction time 659 day
31m(pi) - m(pwf )/qg vs. Super-t Super-tn
32OGIP from Iteration Procedures
33 Conclusions
A new normalized pseudotime is proposed in order
to improve the accuracy of calculating the OGIP.
34 Conclusions
Superposition with the new normalized pseudotime
gives the accurate OGIP at any change in rate and
properties.
35 Conclusions
We should take into account the change in
porosity and initial water saturation with
average pressure in calculating the OGIP
36Thanks