Title: CMM Assessment Grant
1CMM Assessment Grant IIAC Meeting - May 22 2003
Funded by Innovation and Technology Fund of HKSAR
Government Managed by Hong Kong Productivity
Council
2Objectives
- To speed up adoption rate of CMM in HK and have
early successful cases. - To encourage local Independent Software Vendors
(ISVs) to improve software development process
and increase competitiveness. - To provide assistance and advice to local ISVs in
CMM assessment. - To share experiences with local ISVs about CMM
deployment.
3Who are eligible to apply?
- It is incorporated in Hong Kong under Companies
Ordinance (Cap. 32). - It has substantial connection with Hong Kong.
(A significant proportion of its research,
design, development, production, management
or general business activities located in Hong
Kong). - It is a company with primary business focus on
software development. - (In-house MIS unit serving internal user
divisions will not be considered.) - It has not achieved any CMM Level before.
4Vetting criteria
- Have a need and plan for achieving better
software product and process quality. - Have a clear idea on the perceived benefits of
achieving CMM Level 2 or above. - Demonstrate a strong commitment towards quality
objectives and project plan. - Demonstrate a financial need for this Grant.
Preference will be given to SMEs. - The 7-member CMM Assessment Grant Vetting
Committee comprise IT professionals, IT
industrialists, academics and Government
officials.
5Funding support
- External costs for hiring external consultants
and CMM Lead Assessor is in the range of
HK500,000 to HK800,000. - Funding support to each applicant company will
be 50 of these external costs but capped at
a maximum of HK300,000. - The applicant company can choose its own choice
of scheme (SW-CMM or CMMI) and level (2 to
5).
6Reimbursement schedule
- To ensure proper use of the Grant and encourage
active participation of the applicant, the Grant
will reimburse in 3 phases - Upon the satisfactory progress, reimbursement
will be made - Phase 1 20 upon finalizing Project Plan
- Phase 2 40 upon finalizing Process Manual
- Phase 3 40 upon Endorsement Letter from Lead
Assessor
7What we have done
Mar 4, 2003
Announcement Press Conf
Apr 4, 2003 (26 applications received)
Application Deadline
First Vetting Meeting
Apr 25, 2003
Second Vetting Meeting
May 3 2003
(Plus Applicants Presentations)
May 12 2003 (15 applications selected)
Notification
First Applicants Briefing
May 20, 2003
8List of 15 successful applicants
- Arcotect Ltd.
- Automated Systems (HK) Ltd (Software Division)
- COL Ltd.
- Eastpro Ltd
- EPRO Systems (HK) Ltd
- ET Net Solutions Integrator Ltd
- Excel Technology International (HK) Ltd
- Future Solutions (Holgings) Ltd
- ICO Ltd
- Int'l Transport Information Systems Ltd
- KanHan Technologies Ltd
- Kinetix Systems Ltd
- MillionTECH Development Ltd
- We Software Ltd.
- YA Professional Services Ltd
9Coming Milestones
now Jul 15 2003
Applicant to Source Consultant
before Jul 31 2003
Submit Quotation for Processing
Signing formal Agreement
before Aug 15 2003
Fast track (12 months)
Aug-Sep 2003
Phase 1 (Project Plan)
Oct 2003 Jun 2004
Phase 2 (Process Manual)
Phase 3 (Assessment)
Jul 2004 (Early Success Cases)
Normal track (18 months)
Aug-Nov 2003
Phase 1 (Project Plan)
Dec 2003 Dec 2004
Phase 2 (Process Manual)
Jan 2005
Phase 3 (Assessment)
Jul 2005
Project completion