Diamond Project Status V'C'Kempson for the Diamond project team PowerPoint PPT Presentation

presentation player overlay
1 / 33
About This Presentation
Transcript and Presenter's Notes

Title: Diamond Project Status V'C'Kempson for the Diamond project team


1
Diamond Project StatusV.C.Kempson for the
Diamond project team
1. Project manpower 2. Building Status 3.
Accelerator Status
2
Diamond Light source
  • 3 GeV 3rd generation light source
  • 561.6 m Circumference, 3GeV booster, 100MeV linac
  • 22 Straight sections
  • Initial complement phase 1, of 71 beamlines
    under simultaneous construction with the machine
  • Phase 2 beamlines now fully funded bringing
    beamline total up to 20

3
Technical Division Staff
Beamlines
Total no. of Tech. Div. staff at month end
Machine (inc div office)
Currently 101 staff in total, including -
beamline support (16) - division office (4) -
fixed term contracts (3)
4
2 Buildings Status
Photo by Angelos Gonias, DLS
5
All concrete works complete Access route to inner
part of building closed on Sep. 20th
3 x 20Tonne cranes operational
6
DLS Building access for Machine Installation
Linac and Booster Sep. 10th 04 Storage Ring
Area 1 Oct. 11th 04 Storage Ring Area 2
(making 50) Nov. 29th 04
7
Oct. 8th official opening of the first
section(1/4) of the Diamond tunnel ( and
announcement of 120m for Phase II Beamlines)
8
Linac tunnel
Fitting of electrical trunking commenced Start
of linac installation by Accel in Nov.
9
Booster tunnel
34 out of 36 pairs of pedestals for the long
booster girders have been installed and aligned
by DLS. Fitting of electrical trunking commenced
10
Diamond House(Office block)
The Bridge
Proceeding well towards the contractual
completion date of Dec. 12th DLS staff will move
in Jan. '05
Atrium
Office space (part)
11
3 Accelerator Procurement Status
Currently committed 47.2m of 67.9m capital
budget (including installation contracts) i.e. 70
Only a few outstanding major orders to be
placed Tenders received - storage ring low-level
RF system - mechanical services installation Not
yet tendered - primary BPM support stands -
ex-vacuum ID vacuum vessels (U33, HU64) -
production undulator components - wiggler
front-end - fast corrector magnets
12
Machine Installation
  • Contracts placed for
  • - Safety Coordination Management
  • - Installation Manpower
  • - Electrical services installation
  • - Mechanical services installation
    (imminent)
  • DLS staff have received site induction training
    and (where appropriate) construction trade safety
    training.
  • Preparing for first machine contractors to arrive
    in Nov. (Linac).

13
Diamond Master schedule
  • Appoint Main Building Contractor Jan. '03 ?
  • Start enabling works Mar. '03 ?
  • Start main building works Oct. '03 ?
  • Start machine installation Sep '04 ?
  • Start beamlines installation Jan. '05
  • Linac (beam) commissioning May Jul. '05
  • Booster (beam) commissioning Sep. Nov. '05
  • Storage ring (beam) commissioning Jan. Dec. '06
  • Beamlines commissioning May Dec. '06
  • Start of User Operations Jan. '07

14
Machine construction details
  • Injection
  • Vacuum
  • IDs
  • Magnets for the Storage ring
  • Storage ring RF system
  • This talk necessarily missing some areas like
    controls, diagnostics, power supplies, etc
    because of lack of time!

15
Linac assembled section
5 m section Fully brazed Input window this
end Support structure close to final
arrangement Being prepared for cooling channel
attachment (glued) At Accel
16
Linac Gun tests at Delta Dortmund
Gun on test stand _at_ Delta Tested into DLS faraday
cup
Short pulse mode 1.2 nS pulse At spec gt1 A
17
Booster girder assembly components
Sext ptype
Girder assy rear
Booster girder assy ptype at Danfysik
Quad ptype
18
Booster pulsed magnets Injection and extraction
details
19
Booster Rf overall layout
Booster RF area
Labyrinth
Cavity
Load
HV psu
Circulator
Booster ring
Booster Shield wall
RF Amp
20
Booster RF cavity
Body components awaiting machining for cooling
ducts - ACCEL
21
Booster Tunnel Survey
D.W. Wilson
25 survey monuments on outer wall
44 target nests on inner wall
result 0.19 mm survey accuracy (95)
 
22
SR Vacuum system assembly and bakeout procedures
tested. First production girders ready for
assembly.
In the Diamond Test facilty (R79).
23
Insertion Devices
J.A. Clarke
  • Two support structures delivered (HU64 and U23 In
    Vac) accepted
  • Two control systems delivered commissioning
    underway
  • Assembly of HU64 blocks onto structure commenced
  • U23 in-vacuum magnet block assemblies delivered
  • ID measuring bench delivered commissioned
  • In-vacuum undulator vacuum vessel, taper sections
    and other vac components very close to delivery
  • SCW order placed

24
J.A. Clarke
6m field measuring bench
Pre-production ID support structure and control
system
First measurements of a test array
25
Storage Ring Tunnel Survey
D.W. Wilson
  • 48 survey monuments on inner wall
  • 96 wall nests on outer wall
  • A total of 384 observation for complete survey
  • First complete survey done using survey monuments
    and floor pins (sufficient accuracy to lay out
    the base plate positions)

26
Storage Ring Dipoles
Production Magnets awaiting testing and others
nearing completion.
27
Storage Ring Quadrupoles
28
Storage ring Sextupoles
Pole location ring
Prototype SX Magnet
Prototype LV Magnet on rotating coil bench
29
SR RF 3 SC Cavities
Cryogenics
Waveguide
RF amplifiers
Cavity location
Rack mounted equipment
Platform
Air Ventilation Units
LLRF
30
SR HPA on test at Thales
Switch less combiner
Reject load
Hybrid combiners
IOTs
31
Cavity straight based on Cornell type cavities
32
Storage ring cavities
DLS Cavity components - ACCEL
Vertical Test Scheduled for November 2004
33
In conclusion a summary
  • Building infrastructure making solid progress to
    schedule
  • Building services lagging behind (M and E)
  • Machine Installation about to commence
  • Linac Nov-Feb 05
  • Booster Jan-May 05
  • Beamline hutches Jan 05
  • Storage Ring HPA Jan Mar 05
  • Cryogenics Apr 05
  • Booster beam commissioning Sept-Nov 05
  • Storage Ring beam Commissioning Dec 05 Dec 06
    (including fitting of first IDs)