1
LUSI WBS 1.4
X-Ray Correlation Spectroscopy Final Instrument
Design Review Engineering Status Eric Bong April
21, 2009
2
Outline
  • WBS 1.4 Scope
  • Early Science/CD-4 Deliverables
  • Progress since PIDR
  • Status
  • Engineering/Design Status
  • Cost Schedule Performance
  • Critical Path
  • Risk Identification Mitigation
  • Safety
  • Summary

3
WBS 1.3 Early Science/CD-4 Deliverables
Early Finish January 2012 (B/L Early Finish
November 2012)
Early Finish August 2011
4
Progress Since PIDR
  • BCR - Reconfiguration of XCS Instrument
  • Moved Large Offset Monochromator
  • Addition of Post Monochromator to project scope
  • Moved Split Delay into alcove upstream of Hutch
    4
  • Relocated diagnostics to characterize beam before
    and after the monochromators
  • Eliminated long beam-line transport in XRT
  • XRT Beam-Line Design
  • Extensive modification of LLNL design required
  • Negotiated redesign of XRT to minimize re-work
  • Split redesign cost with LCLS
  • Now far less rework required to install XCS
    components

5
Progress Since CD-2
  • Translation of XCS onto CXI Line
  • Supports Early Science
  • Documentation for Long Lead Procurement
  • PRDs, ESDs, SOWs,
  • Diffractometer
  • Large Angle Detector Mover
  • Large Offset Monochromator
  • Held Long Lead Procurement Review, April 23, 2009
  • Commercial alternative for diagnostic stopper
  • Vendor indicates modification of existing stopper
    design to add B4C wafer on face is possible
  • Savings of design and fabrication time
  • Updates P3 to indicate change in acquisition
    strategy

6
Progress Since CD-2
  • XCS Engineering/Design staff
  • Added 1 Mech Engineer / Designer February 2009
  • Added 2 Mech Engineer / Designers May 2009
  • Preliminary Design Reviews (PDRs)
  • Vacuum XRT Hutch4
  • Supports XRT Hutch 4
  • Granite Tables
  • Large Angle Mover Vacuum Assembly
  • PDRs complete
  • Baseline vibration data obtained in the LCLS Far
    Experimental Hall

Vertical/Horizontal PSD, 1-100Hz (Compliments P.
Montanez, J. Turner)
7
Engineering Design Status
  • Engineering Design Staff
  • Ted Osier, Michael Kosovsky, Henry Alvarez,
    Navtej Hundal, Eric Bong

Hutch 4 Optics, Diffractometer Large Angle
detector Mover
X-Ray Transport Hall (XRT)
Split and Delay Area
XCS Instrument Scientist Aymeric Robert
Post-Monochromator
XCS Visiting Scientist Soo-Heyong Lee
Large Offset Monochromator
8
Engineering/Design Status 1.4.1
  • Documentation
  • CAD system model documentation hierarchy (CAD
    Drawing Tree/File Structure) released
  • XRT FEH H4 beamline layouts complete with all
    available models implemented updated
  • PRDs/ESDs/ICDs/Purchasing Specs complete.
  • Hutch Design
  • Reviewed 30, 60, 90 100 AE drawings
  • FEH Hutch construction June thru December 2009
    (LCLS)
  • APP and Risk Identification/Registry complete and
    up to date

9
Engineering/Design Status 1.4.2
  • XCS Optic Support Tables (WBS 1.4.2)
  • Hutch 4 Granite Support Tables (WBS 1.4.2.2)
  • Modification of XPP support table design
  • Granite base with movable strong-back
  • PDR 29 May 2009
  • Leveraging existing designs (when applicable)
    reduces overall engineering design effort. Use
    of common parts reduces maintenance costs.
  • Safety Earthquake restraint of granite base,
    covered pinch points.
  • Budget at Completion (BAC) 200k
  • Stoppers (WBS 1.4.2.3)
  • Diagnostic stoppers not PPS.
  • Changed plan from modification to PPS stopper
    design to Commercial Item.
  • Worked with vendor on modification of an off-the
    shelf product to incorporate 10mm on face of
    stopper. Commercial stopper uses same controls as
    vacuum valves.
  • Issued BCR to change P3.
  • Budget at Completion (BAC) 187k

10
Engineering/Design Status 1.4.4
  • XCS Large Angle Detector Mover (WBS 1.4.4.3)
  • Processed BCR to split effort between carriage
    motion and upper assemblies.
  • Carriage motion build to spec.
  • Vacuum, detector positioner and beam stop SLAC
    design.
  • PRD, ESD Purchase Spec complete.
  • Procurement Review Held.
  • Requisition in purchasing.
  • Safety Earthquake restraint pinch points,
    interlock of automatic motion.
  • Design reviews required at vendor for carriage.
  • LUSI controls interface required.
  • Budget at Completion (BAC) 856k
  • XCS Diffractometer (WBS 1.4.4.1)
  • Planed as SLAC assemble. Changed to build to
    spec, same as XPP. Processed BCR.
  • PRD, ESD Purchase Spec complete
  • Procurement Review Held.
  • Ready to release RFQ
  • Safety Earthquake restraint pinch points,
    interlock of automatic motion.
  • Design reviews required at vendor.
  • LUSI controls interface required.
  • Budget at Completion (BAC) 685k

11
Engineering/Design Status 1.4.5
  • XCS Hutch Utilities (WBS 1.4.5)
  • Hutch layout design complete.
  • LCLS responsible for hutch construction.
  • Crane installation moved from LUSI to LCLS
  • XCS responsible scientist and engineer involved
    hutch 4 specification and design reviews.
  • Tasks to be completed by XCS
  • Raised flooring
  • Storage cabinets, work benches and tool chests
  • Utilities distribution
  • Budget at Completion (BAC) 369k

12
Engineering/Design Status 1.4.6
  • XCS Hutch 4 Vacuum (WBS 1.4.6.2)
  • Designed to shift to CXI line.
  • Vacuum component selection complete.
  • Uses many XRT support designs.
  • Completed preliminary design report.
  • Ready to purchase all vacuum equipment.
  • Safety Pressure vessel code requirement
    mitigated using burst disks.
  • Budget at Completion (BAC) 400k
  • XCS XRT Vacuum (WBS 1.4.6.1)
  • Quantity of drift tubes finalized.
  • Vacuum component selection complete.
  • Vacuum support design well advanced.
  • Completed preliminary design report.
  • Ready to purchase all vacuum equipment.
  • Safety Pressure vessel code requirements
    mitigated using burst disks.
  • Budget at Completion (BAC) 363k

13
Engineering/Design Status 1.4.7
  • XCS Installation (WBS 1.4.7)
  • LUSI Installation Coordinator
  • Obtain required installation permits.
  • Conduct daily tailgate meeting w/ UTR (University
    Technical Representative).
  • Conduit to engineering for field installation
    issues.
  • Provide installation status for incorporation
    into LUSI schedule.
  • XCS XRT Installation
  • Phased with LCLS and CXI installations.
  • Advanced schedule could combine all XCS XRT
    installation with CXI except monochromators.
  • Budget at Completion (BAC) 351k
  • XCS Hutch 4 Installation
  • Early Science
  • All components except XCS detector
  • Install duplicate XPP detector to commission and
    early science
  • Early Finish June 2011
  • CD-4
  • XCS Detector
  • Early Finish January 2012
  • Budget at Completion (BAC) 613k

14
Engineering/Design Status 1.4.6
  • Large Offset Mono (WBS 1.5.3.1 )
  • Planed as build to specification.
  • Vendor build complete
  • Option for SLAC to build crystal holder
  • PRD, ESD Purchase Spec complete.
  • Procurement Review Held.
  • Review requires revisions to PRD, ESD Purchase
    Spec
  • Safety Earthquake restraint.
  • Design reviews required at vendor for carriage.
  • LUSI controls interface required.
  • Budget at Completion (BAC) 1,778k
  • 1.5.3.7 Post Mono (WBS 1.4.6.2)
  • Fabrication of existing ANL design.
  • ANL drawings have been requested.
  • SLAC will review drawings prior to purchasing
    components.
  • Safety Earthquake restraint.
  • LUSI controls interface required.
  • Budget at Completion (BAC) 455k

15
XCS Instrument Design Status Summary
System/Component Review Baseline Advanced
1.4.1 Integration FIDR 8/5/09 6/30/09
1.4.2.2 Hutch Granite Table PDR 6/29/09 5/29/09
1.4.2.3 Diagnostic Stopper COTS 6/9/09 5/15/09
1.4.4.1 Diffractometer LLPR 4/21/09 4/23/09
1.4.4.3 Large Angle Mover Carriage LLPR 12/14/09 4/23/09
1.4.4.3 Large Angle Mover Vacuum PDR 5/29/09
1.4.5.1 Hutch Specification FDR 2/28/09 2/28/09
1.4.5.2 Hutch Utilities Equipment PDR 10/2/09 10/2/09
1.4.6.1 XCS XRT Vacuum Design PDR 3/4/09 5/19/09
1.4.6.2 XCS H4 Vacuum Design PDR 3/2/09 5/19/09
1.5.3.1 Large Offset Monochromator LLPR 6/5/09 4/23/09
1.5.3.7 Chanel Cut Monochromator PR 8/31/09 8/31/09
16
Cost and Schedule Performance (2)
17
Cost Performance Report
March Data
April Data
18
XCS Critical Path
DCO X-ray Focusing Lens and Harmonic Rejection
Mirror Awards
DCO Harmonic Rejection Mirror Preliminary Design
Review
XCS Diagnostics Stopper Design Effort
  • Removing budgetary constraints will move critical
    path to XCS long lead items
  • Re-plan of stopper acquisition will move stopper
    off critical path

19
XCS Look Ahead
  • Six month look-ahead of XCS Instrument
    milestones
  • ARRA advanced schedule
  • Purchasing started on Diffractometer and Detector
    Mover Carriage.
  • Large Offset Monochromator purchasing start
    requires revision of specifications dictated by
    procurement review.
  • Non LLP item purchasing must wait for CD3
    approval.

20
Risk Identification Mitigation
  • Risk Identification/Registry complete and up to
    date as per LCLS Risk Management Plan PMD
    1.1-002-r4
  • 15 risks identified at CD-2 for XCS WBS 1.4
  • 5 Risks for BNL Detector
  • Schedule - late MOU
  • Schedule - late design
  • Schedule - late fabrication
  • Schedule - late testing
  • Technical does not meet requirements
  • 5 Risks each for for Large Angle Detector Mover
    Diffractometer
  • Schedule Procurement Placement
  • Schedule - late design
  • Schedule - late fabrication
  • Schedule - late testing
  • Technical does not meet requirements
  • 2 risks identified at CD-2 for DCO Monochromator
    WBS 1.5.3.1
  • 2 Risks for Monochromator
  • Schedule Manufacturing
  • Technical Optical Stability

21
Safety
  • LUSI Hazard Analysis Report (PM-391-001-34)
    complete
  • Safety issues are considered at every stage of
    the design, fabrication and installation process
  • Safety considerations (some examples)
  • Ionizing Radiation
  • Hutch walls will comply with SLAC Radiation
    Safety memo RP-RPG-080606-MEM-01
  • Hutch PPS
  • Pressure/Vacuum Vessel Safety
  • Compliant with 10CFR851
  • Seismic Safety
  • Designs compliant with Seismic Design
    Specification for Buildings, Structures,
    Equipment, and Systems, SLAC-I-720-0A24E-002-R002
  • Mechanical
  • Interlocks for equipment protection
  • Engineered solutions that prevent potential
    pinch-points with moving machinery
  • Hoisting and Rigging
  • Positioning of devices that require the use of
    the FEH H4 overhead crane shall be performed by
    only by qualified personnel with an approved lift
    plan.

22
Summary
  • XCS instrument configuration design is complete.
  • All preliminary design reviews complete.
  • XCS scope is stable following BCR to move
    monochromators.
  • Acquisition strategy for stoppers and large angle
    detector has been integrated into the schedule.
  • Long Lead Procurement Review for diffractometer,
    large angle detector mover and large offset
    monochromator has been completed.
  • Purchasing of LLP items has begun.
  • Releasing budgetary constraints moved critical
    path to long lead procurement items.
  • Scheduled early CD3 spending authority advances
    schedule.
  • ARRA funding re-baseline advances XCS schedule
    providing early science in August 2011.

23
Supporting Slides
24
Expanded CSSR by CAM
25
Control Accounts Work Packages by WBS L2
26
Control Accounts Work Packages by CAM
27
P3 Files Total Activities by CAM
28
P3 Files Milestones by WBS L2
29
Procurements and Dollars WBS
30
Labor/Non-labor Split WBS 1.4