PRMRWSA Source Water Feasibility Study - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

PRMRWSA Source Water Feasibility Study

Description:

PRMRWSA Source Water Feasibility Study – PowerPoint PPT presentation

Number of Views:120
Avg rating:3.0/5.0
Slides: 15
Provided by: pbs79
Category:

less

Transcript and Presenter's Notes

Title: PRMRWSA Source Water Feasibility Study


1
PRMRWSA Source Water Feasibility Study
  • October 15, 2008

2
History
  • 2005 Water Planning Alliance PRMRWSA
    identified future supply opportunities
  • 2006 Authority Regional Water Supply Master
    Plan evaluates 6 high potential supply
    opportunities
  • 2007 Authority Board approves feasibility
    study on 3 source areas
  • 2008 Completion of Source Water Feasibility
    Study

3
(No Transcript)
4
Feasibility Study
  • Major Opportunities
  • Surface Water
  • Groundwater
  • Resource Evaluation
  • Flow / Quality / Timing
  • Existing Users
  • Land Use
  • Project Development
  • Reservoirs Intakes
  • Treatment Requirements
  • Connections
  • Cost Screening
  • Environmental Benefits
  • Program Development
  • Meet Future Needs
  • Project Combinations Comparisons

5
Reservoir Site Selection
  • Multi-Step Reservoir Site Process
  • Considered
  • Environmental Criteria
  • Flood Maps
  • Number of Property Owners and Land Use
  • Geo-Hazards, etc.
  • ID Potential Sites
  • 11 Sites in Shell/Prairie
  • 8 Sites in Upper Myakka
  • Site Evaluations
  • 3 Sites Shell / Prairie
  • 3 Sites Upper Myakka
  • 2 Sites Dona Bay

6
Upper Myakka / Flatford
  • 3 Reservoir Sites
  • 1000 acre sites
  • 6 Billion Gallons
  • 2 Intake Sites
  • Yield 10 20 mgd
  • Environmental benefit by reducing water in swamp

7
Groundwater Permits
  • Mostly Agricultural Use
  • 120 MGD Permitted Groundwater Use
  • Brackish GW Resource
  • Regulatory Considerations
  • Concentrate disposal issues

8
Shell/Prairie Creek
  • 3 Reservoir Sites
  • 1000 acre sites
  • 6 billion gallons
  • 2 Intake Sites
  • Yield 12 20 mgd
  • Environmental benefit reduce low-flow
    withdrawals

9
Groundwater Permits
  • Mostly Agricultural Use
  • 100 MGD Permitted Groundwater Use
  • Significant Brackish GW Resource
  • Concentrate disposal issues

10
Dona Bay / Cow Pen Slough
  • 2 Reservoir Sites
  • 550 acres
  • 1000 acres
  • 4-10 bg
  • 1 Intake Sites
  • Yield 7 20 mgd
  • Environmental benefit reduce fresh water to
    Dona Bay

11
Groundwater Permits
  • Mostly Public Supply Use
  • Brackish Groundwater
  • No Permit Inventory Conducted
  • Expansion of Existing GW Facilities

12
Study-Wide Findings
  • Large Surface Water Resource Available
  • Storage Required
  • Environmental Benefits
  • Conjunctive groundwater development improves
    reliability and reduces reservoir size
  • Groundwater sources can be almost anywhere in the
    regional system
  • Membrane treatment required for all sources

13
Next Steps
  • Complete Technical Analysis
  • Develop Projects
  • Board Workshop on November 5
  • Board Meeting December 3
  • Preliminary Design
  • Final Design
  • Construction

14
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com