RCUC - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

RCUC

Description:

The dispatch process: Adheres to Operational Priorities (safety, security, economy) ... Scheduling & Dispatch Workshop. Operating the System ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 23
Provided by: ncc72
Category:
Tags: rcuc | dispatch

less

Transcript and Presenter's Notes

Title: RCUC


1
RCUC The Dispatch Process
  • Donal Connolly (Eirgrid)
  • Michael Preston (SONI)

2
Introduction
  • Scheduling versus Dispatch
  • Immediate Priorities
  • Medium Term Priorities and Inputs into the
    decision to Reschedule or Redispatch
  • Why Dispatch and Schedule may differ
  • Load Rise and Night Valley

3
Scheduling and Dispatch
  • The output of the scheduling process is
  • A Unit Commitment schedule
  • A set of discrete MW set points for each unit at
    30 minute intervals
  • A reserve schedule for each jurisdiction
  • A tie-line flow schedule
  • The dispatch process
  • Adheres to Operational Priorities (safety,
    security, economy)
  • Aims to match demand with generation on a second
    by second basis
  • Maintains tie-line flow schedules
  • Maintains adequate levels of operating reserve at
    all times
  • Plans for credible generation and transmission
    contingencies
  • Manages real time system disturbances that cause
    frequency deviations, transmission overloads or
    voltage problems
  • The Control room operators use the output of the
    scheduling process to guide them in the dispatch
    process

4
Operating the System
  • When assessing whether the current schedule is
    adequate to feed into the dispatch process the
    Operator will give consideration to
  • Immediate Priorities
  • Frequency, Voltage and Flows on Line within
    limits
  • Reserve check
  • Tie Line Flow (actual to RCUC schedule)
  • Medium Term Priorities
  • Load comparison (actual to latest forecast to
    RCUC schedule)
  • Wind comparison (actual to latest forecast to
    RCUC schedule)
  • Generator Availability Changes
  • Tie Line Flow
  • Margin Check
  • If the schedule is not adequate the Operator will
    prepare a new schedule

5
Load Comparison
April
Summer
Winter
Summer B/H
6
Wind Comparison
7
Tie Line Schedule
8
Margin Check
  • MW
  • MWs Available 4673
  • Short Available 4464
  • To/From SONI 311
  • Wind 114
  • 4889
  • Est. Peak 4000
  • Margin 889
  • Reserve
  • POR 308 MW (75 of largest in feed, 5 15 sec)
  • SOR 308 MW (75 of largest in feed, 15 90 sec)
  • TOR1 410 MW (100 of largest in feed, 90 sec 5
    min)
  • TOR2 410 MW (100 of largest in feed, 5 min 20
    min)

9
Reschedule or Dispatch
10
RCUC to EDIL
11
Unit Trip
49.94 Hz
78 MW
TH4 Sync
-207 MW
49.29 Hz
12
Dispatch Instructions (Unit Trip)
13
Frequency Response
14
Load Comparison
Previous Day
Previous Week
Current Day
Cold Front
Match
15
Wind Forecast
  • Divergent Forecasts
  • Forecast Different from Wind
  • Forecast Timing

16
Met Information
17
Wind Rising
18
Contingency Analysis
19
Load Rise 07 Apr 08
  • RCUC looks at 30 minute intervals but demand is
    changing on a second by second basis and the
    dispatcher must consider how the demand changes
    when issuing instructions

0600 0900 1348 MW Wind Output and Loss of
largest in-feed
20
Dispatch Instructions 07 Apr 08
  • As can be seen here, to manage a typical morning
    load rise the operator had to issue 55 separate
    MW instructions over a 2 and ½ hour period.

21
Night Valley 06 May 07
  • This table shows the problems faced by the
    operator when all plant is dispatched to Minimum
    Load.
  • The operator may have to de-commit plant in an
    unscheduled way due to unexpected increases in
    wind output, decreases in system demand,
    generator limitations or a combination of all of
    these.

22
Summary
  • The Scheduling Process feeds into the Dispatch
    Process
  • Operators take a number of real-time factors into
    account when issuing dispatch instructions
  • Time permitting, Operators will re-schedule if
    the current schedule cannot be followed
  • Operators will face unplanned issues when
    dispatching
  • At all times operators give priority to safety
    and security
Write a Comment
User Comments (0)
About PowerShow.com