Description:

Hosts cable trays (for overhead power/network drops) ... Lighting & cable tray (not yet started) Overhead Power drops installation. (not yet started) ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 15
Provided by: CALT5
Category:

less

Transcript and Presenter's Notes

Title: WANINLAB California Institute of Technology


1
WAN-IN-LABCalifornia Institute of Technology
  • Physical design, Power distribution
    Air-conditioning
  • Elvin Nixon, Nick Grewal, George Lee, Raj Jayaram

2
Heads-Up The Complete Network
3
Heads-Up Core Network
4
Heads-up 13 ONS15454 Optical Nodes
5
Physical lay-out Power distribution 386 SqFt
6
DC Power distribution
7
Lighting lay-out
8
Physical lay-out features
  • Located just opposite to Net-lab, easy/secured
    access.
  • 386 SqFt, entire space used as machine room
  • Hosts Liebert cooler air-condition calculation
    depicted in later slides
  • Hosts DC centralized power supply rack
  • AC circuit outlets breaker panels provided at
    required points
  • Hosts 12 telecom standard racks with cable
    manager.
  • Hosts cable trays (for overhead power/network
    drops)
  • Condensation/humidity factors taken into account
  • False ceiling provided along with air-vents at
    appropriate places
  • Raised floor not desired to conserve space/cost.
  • 1GE Out-of-band uplink connection provided by IST
    department via overhead network drop we plan to
    use an aggregation switch downstream.

9
Wattage Chart
  • ITEM WATTAGE QTY WATTage Comments
  • ONS15454 30A_at_1060W 13 14KW -48V DC
  • Cisco7613 30A_at_4000W 4 16KW 208240 AC
  • 1U Servers 10A_at_400W 30 12KW 110V AC
  • Misc 10A_at_8000W 1 08KW 110v AC
  • TOTAL 50KW connected load

10
Power distribution features
  • Capable of handling 50KW of connected load.
  • Centralized DC supply (-48v for ONS 13 units)
    being provided by contractor, with battery bank,
    in a single isolated rack.
  • DC cabling done by contractor upto the ONS units
    using overhead cable drops.
  • AC supply (208240V for Cisco7613 4 units) being
    provided by Caltech Electrical department.
  • AC supply (110V for 30 servers) being provided by
    Caltech Electrical department.
  • AC power drops provided direct from points at
    appropriate places using overhead drops.
  • AC circuit breakers provided at centralized
    location.
  • UPS systems (with built-in isolation
    transformers) provide a backup of 10minutes for
    all units shall be provided.

11
Cooling Requirements
  • Formula used
  • Watts x (0.860)Kcal/hour Watts x
    (3.414)Btu/hour Btu/hour divided by 12,000tons
    of refrigeration required
  • So, for the connected load of 50KW amount of
    cooling required is
  • 50000 x 3.414 170700 Btu/hour

    170700/12000 14.225 tons of cooling
    required.
  • The Liebert cooling system is capable of
    providing a lot more than the above requirement.

12
Rack Cable distribution
13
Rack Cable distribution features
  • Telecom standard racks are used Diemensions
    ??x??x??
  • ONS series (13 units) will go into racks 2 to 6.
    -48v power drops will be provided by the
    centralized DC supply.
  • 7613 series (4 units) will go into racks 1 7.
    240V AC power drops will be provided from points
    that are located at appropriate places.
  • 1U rack-mount servers will go into racks 8 9.
  • There is lot of room to add more racks in the
    future.
  • Each rack has a cable management panel.
  • Overhead cable trays are used to carry power
    drops and network/console cable drops seperately.
  • Console ports for all these units are connected
    using TIP/Terminal servers.
  • Management (OutOfBand) ports are connected to an
    aggregation switch and the uplink of 1GE is
    provided by IST department.
  • Fiber spool storage spaces are available in the
    racks itself.
  • Connection to external networks (fiber drops)
    like CACR/HEP is extended from the next building
    into this facility.

14
Schedule Current status
  • Action items
  • Order Liebert cooling system (done)
  • Clean-up the Jrg lab space (done)
  • Wall floor work. (in-progress)
  • AC Power supply installation. (not yet started)
  • Lighting cable tray (not yet started)
  • Overhead Power drops installation. (not yet
    started)
  • DC Power installation (contractor work) (not yet
    started)
  • Liebert Cooler installation. (not yet started)
  • Racks installation. (not yet started)
  • ESTIMATED DATE OF COMPLETION
  • 6 weeks (from Oct 11th).