Project Phases and Management Tools - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

Project Phases and Management Tools

Description:

Network Analysis requires breaking down the project into ... BD. BE ... A company is about to undertake a project about wihcih the following data is available. ... – PowerPoint PPT presentation

Number of Views:223
Avg rating:3.0/5.0
Slides: 49
Provided by: JohnFo5
Category:

less

Transcript and Presenter's Notes

Title: Project Phases and Management Tools


1
Project Phases and Management Tools
  • ACCA Lecture 1g

2
Project Phases and Management Tools Network
Analysis
  • Network Analysis or Critical Path Analysis
  • Network Analysis requires breaking down the
    project into tasks, arranging them into a logical
    sequence and estimating the duration of each.
  • This Enables the series of tasks that determines
    the minimum possible duration of the project to
    be found. These are the critical paths
  • CPA aims to minimise time scale

3
Project Phases and Management Tools Network
Analysis
  • Pinpoints on the critical path would delay
    project completion
  • Assist in allocating resources
  • The events and activates form a diagram
  • Drawing the diagram or chart involves the
    following steps
  • Estimate the time needed to complete each
    individual activity or task that makes up a part
    of the project.
  • Sorting out what activites must be done one after
    each after another, and which can be done at the
    same time, if required.

4
Project Phases and Management Tools Network
Analysis
  • Representing these in a network diagram
  • Estimating the critical path, which is the
    longest sequence of consecutive activities
    through the network
  • The duration of the whole project will be fixed
    by the time to complete the largest path through
    the network. This path is called the critical
    path and activities on it are know as critical
    activities.
  • Activities on the critical path must be started
    and completed on time.

5
Project Phases and Management Tools Network
Analysis
  • Network Analysis shows the sequence of tasks and
    how long they are going to take. The diagrams are
    drawn from left to right.

6
Project Phases and Management Tools Network
Analysis
  • Events (eg 1 and 2) are represented by circles.
    Tasks (eg A) connect events.
  • The critical path is represented by drawing an
    extra line or a thicker line between the tasks on
    the path. It is the minimum amount of time that
    the project will take.
  • It is the convention to note the earliest start
    date of any task in the top right hand corner or
    the circle.
  • We can then work backwards identifying the latest
    date when tasks have to start. These we insert in
    the bottom right quarter of the circle
  • The critical path in this diagram is AEG. Note
    the float time of five days for the Activity F.
    Activity F can begin at any time between days 4
    and 9, thus giving the project manager a degree
    of flexibility.

7
Project Phases and Management Tools Activity on
Node
  • Microsoft Project software package
  • Example Activity on Node
  • Suppose that a project includes activities, C, D
    and E. Neither activity D nor E can start until
    activity C is completed, but D and E could be
    done simultaneously if required.
  • This would be represented as follows.

D
C
E
8
Project Phases and Management Tools Activity on
Node
  • Note the following
  • An activity with a network is represented by a
    rectangular box (each box is a node).
  • The flow of activities in the diagram should be
    from left to right.
  • The diagram clearly shows that D and E must
    follow C.
  • A second possibility is that an activity cannot
    start until two or more activities have been
    completed. If activity H cannot start until
    activities G and F are both complete, then we
    would respresent the situation like this.

9
Project Phases and Management Tools Activity on
Node
F
H
G
  • In some conventions an extra node is introduced
    at the start and end of a network, we recommend
    that you do not do it.

10
Project Phases and Management Tools Activity on
Node
  • Example Starts and Ends
  • Draw a diagram for the following project. The
    project is finished when both D and E are
    complete.

11
Project Phases and Management Tools Activity on
Node
12
Project Phases and Management Tools Activity on
Node
  • Any network can be analysed into a number of
    different paths or routes. A path is simply a
    sequence of activities which can take you from
    the start to the end of the network. In the
    example above, there are just three routes or
    paths.
  • ACD
  • BD
  • BE
  • The time needed (duration) to complete each
    individual activity in a project must be
    estimated.

13
Project Phases and Management Tools Activity on
Node
Example The Critical Path
What are the paths through the network? What is
the critical path duration?
14
Project Phases and Management Tools Activity on
Node
Solution The Critical Path
15
Project Phases and Management Tools Activity on
Node
  • We could list the paths through the network and
    their overall completion times as follows.

16
Project Phases and Management Tools Activity on
Node
  • The critical path is the longest, BFH, with a
    duration of 12 weeks. This is the minimum time
    needed to complete the project.
  • The critical path is indicated by a thick or
    double line.
  • Listing Paths easy enough for small networks,
    long and tedious task for bigger and more complex
    networks.
  • Conventionally it has been recognised as useful
    to calculate the earliest and latest times for
    activities to start and finish.

17
Project Phases and Management Tools Activity on
Node
  • Project management software packages offer a much
    larger variety of techniques than can easily be
    done by hand. Microsoft Project allows each
    activity to be assigned to any one of a variety
    of types start as late as possible, finish no
    earlier than, finish no later than etc..
  • In real life, activity times can be shortened or
    the may be constrained.

18
Project Phases and Management Tools Activity on
Node
  • Example Earliest and Latest Start Times
  • These sections record the following things.
  • The name for example Task A.
  • An ID number
  • The Duration
  • The Earliest Start Time
  • The Latest Start Time

19
Project Phases and Management Tools Activity on
Node
  • The earliest start times, always start with
    activities that have no predecessors.
  • The work along each path from left to right
    through the diagram calculating the earliest time
    that the next activity can start.
  • To calculate an activities earliest time, simply
    look at the box for the preceding activity and
    add the bottom left figure to the top right
    figure.
  • If two or more activities precede an activity
    take the highest figure.

20
Project Phases and Management Tools Activity on
Node
  • The latest start times, are the latest times at
    which each activity can start if the project as a
    whole is to be completed in the earliest possible
    time, in other words in 12 weeks in our example.
  • Work backwards from right to left through the
    diagram calculating the latest time at which the
    activity can start, if it is to be completed at
    the latest finishing time. For example the latest
    start time for activity H is 12-3 week9 and for
    activity E is 12-5 week7.
  • Activity F might cause difficulties as two
    activities, H and I, lead back to it. We take the
    lower figure.

21
Project Phases and Management Tools Activity on
Node
22
Project Phases and Management Tools Activity on
Node
  • The latest start times, are the latest times at
    which each activity can start if the project as a
    whole is to be completed in the earliest possible
    time, in other words in 12 weeks in our example.
  • Work backwards from right to left through the
    diagram calculating the latest time at which the
    activity can start, if it is to be completed at
    the latest finishing time. For example the latest
    start time for activity H is 12-3 week9 and for
    activity E is 12-5 week7.
  • Activity F might cause difficulties as two
    activities, H and I, lead back to it. We take the
    lower figure.

23
Project Phases and Management Tools Activity on
Node
  • Critical activities are those activities which
    must be started on time, otherwise the total
    project time will be increase. It follows that
    each event on the critical path for the above
    network is therefore BFH.
  • Criticisms of critical path/network analysis
  • It is not always possible to devise an effective
    WBS for a project
  • It assumes a sequential relationship between
    activities
  • There are problems in estimation
  • Does not appear to develop plans for
    contingencies, other than crashing time.
  • CPA assumes a trade-off between time and cost.
    This may not be the case where a substantial
    portion of the cost is indirect overheads.

24
Project Phases and Management Tools Activity on
Node
  • Example Gantt Charts and Resources
  • This example is provided as an illustration of
    the use of Gantt chats to manage resources
    efficiently.
  • A company is about to undertake a project about
    wihcih the following data is available.

25
Project Phases and Management Tools Activity on
Node
  • There is a multi-skilled workforce of nine
    workers available, each capable of working on any
    activities.
  • Draw the network to establish the duration of the
    project and the critical path. Then draw a Gantt
    Chart, using the critical path as a basis,
    assuming that jobs start at the earliest possible
    time.

26
Project Phases and Management Tools Activity on
Node
27
Project Phases and Management Tools Activity on
Node
  • It can be seen that if all activates start at
    their earliest times, as many as 15 workers will
    be required on any one day (days 6-7) whereas on
    other days there would be idle capacity (days
    8-12).
  • The problem can be reduced, or removed, by using
    up spare time on non-critical activities. Suppose
    we deferred the start of activities D and F until
    the latest possible days. These would be days 8
    and 9, leaving four days to complete the
    activities by the end of day 12.

28
Project Phases and Management Tools Activity on
Node
  • The Gantt chart would be redrawn as follows

29
Project Phases and Management Tools PERT
  • PERT (Project evaluation and review technique) is
    a technique for allowing for uncertainty in
    determining project duration. Each task is
    assigned a best, worst and most probable
    completion time estimate, These estimates are
    used to determine the average completion time.
    The average times are used to establish the
    critical path and the standard deviation of
    completion times for the entire project.
  • PERT is a modified form of network analysis
    designed to account for uncertainty, For each
    activity in the project, optimistic, most likely
    and pessimistic estimates of times are made.
    These estimates are converted into a mean time
    and also a standard deviation.

30
Project Phases and Management Tools PERT
  • Estimate the critical path using expected (mean)
    activity times.
  • Estimate the standard deviation of the total
    project time.
  • Exam focus
  • PERT has not been mentioned in the syllabus, so
    we have not included a worked example. Just be
    aware that it exists and that it is designed to
    build in an allowance for time uncertainity.

31
Project Phases and Management Tools Resource
Histogram
  • Resource Histogram
  • A useful planning tool that shows the amount and
    timing of the requirement for a resource (or
    range of resources) is a resource histogram.
  • A Resource Histogram shows a view of project data
    in which resource requirements, usage, and
    availability are shown against a time scale.

32
Project Phases and Management Tools Resource
Histogram
33
Project Phases and Management Tools Resource
Histogram
  • Some organisations add another bar (or a separate
    line) showing resource availability.

34
Project Phases and Management Tools Resource
Histogram
  • Floating time is built into allow for unforeseen
    circumstances
  • Total Float on a job is the time available
    (earliest start date to latest finish date) less
    time needed for the job.
  • Free Float is the delay possible in an activity
    on the assumption that all preceding jobs as
    early as possible and all subsequent jobs also
    start at the earliest time.
  • Independent Float is the delay possible if all
    preceding jobs have finished as late as possible,
    and all succeeding jobs have started as early as
    possible.

35
Project Phases and Management Tools Project
Management Software
  • Microsoft Project, Micro Planner X-Pert.
  • Software might be used for a number of purposes
  • Planning
  • Estimating
  • Monitoring
  • Reporting
  • Identifying the main steps, breaking these down
    further into specific tasks.

36
Project Phases and Management Tools Project
Management Software
  • A typical project management package requires
    four inputs.
  • The length of time required for each activity of
    the project.
  • The logical relationship between each activity.
  • The resources available.
  • When the resources are available.

37
Project Phases and Management Tools Project
Management Software
38
Project Phases and Management Tools Resource
Histogram
  • Two disadvantages of project management software
    are
  • Some packages are difficult to use.
  • Some project managers become to interested in
    producing perfect plans that they spend to much
    time producing documents and not enough time
    managing the project.

39
Project Phases and Management Tools
Documentation and Reports
  • The name allocated to documents will vary across
    different organisations. What is constant is the
    need for clear and relevant documentation that
    helps monitor and control the project.
  • Not a substitute for one-on-one communication.
  • When outlining possible content of documents some
    duplication of items occurs.
  • It is likely that the Project Initiation Document
    will evolve until it is ultimately incorporated
    into the Project Management Plan, sometimes
    referred to as the Project Quality Plan.

40
Project Phases and Management Tools
Documentation and Reports
  • The Project Plan
  • The project manager should also develop a Project
    Plan.
  • The Project Plan is used to guide both project
    execution and project control. It outlines how
    the project will be planned, monitored and
    implemented.
  • The project plan should include
  • Project objectives and how they will be achieved
    and verified.
  • How any changes to these procedures are to be
    controlled.
  • The management and technical procedures and
    standards to be used.
  • Details of the quality budget.
  • The budget and time-scale.
  • Safety, health and environmental policies.
  • Inherent risks and how they will be managed.

41
Project Phases and Management Tools
Documentation and Reports
  • The project plan evolves over time. A high level
    plan for the detailed plan for the current and
    following stage.
  • At each subsequent lstage a detailed plan is
    produced.
  • The Project Quality Plan outlines the quality
    strategy to be followed and links this to any
    formal quality management approach the
    organisation has chosen to follow.
  • Distinction between a project management plan and
    a quality plan is becoming increasingly blurred.
  • Key elements of a quality plan include
  • The formal stages of the project
  • Standards to be used throughout the project
  • Controls that aim to ensure quality
  • Checks to ensure quality

42
Project Phases and Management Tools
Documentation and Reports
  • Case Example
  • Project Name
  • Project Manager
  • Purpose/Business Need
  • Product Description and Deliverables
  • Assumptions, Constraints and Risks
  • Resources
  • Financial
  • Explanation of standards program
  • Personnel/Volunteers
  • Mandatory
  • As Possible
  • Approach

43
Project Phases and Management Tools
Documentation and Reports
  • Case Example cont.
  • Communication and Reporting
  • Monthly Status Report
  • Monthly Resources Reports
  • Financial Resources
  • Human Resources
  • Milestone and Critical Reports
  • Acceptance
  • Change Management
  • Plan Acceptance
  • By PMI Standards Program Team
  • By Project Manager

44
Project Phases and Management Tools
Documentation and Reports
  • Example Extract from a call centre software
    implementation Project Plan
  • Introduction
  • Project roles
  • Communication plan
  • Training plan
  • Change management plan
  • Quality management
  • Project documentation
  • Financial management
  • Programme management

45
Project Phases and Management Tools
Documentation and Reports
  • Progress Report
  • A Progress Report shows the current status of the
    project, usually in relation to planned status.
  • Frequency and contents of progress reports will
    vary depending
  • The report is a control tool
  • One for planned time, one for actual
  • Additional content will depend on the format
    adopted. Some organisations include only raw
    facts in the report, as a basis for discussion.
  • Other organisations (particularly those involved
    in long, complex projects) produce more
    comprehensive progress reports, with more
    explanation and comment.
  • A milestone is a significant event in the
    project, usually completion of a major
    deliverable.

46
Project Phases and Management Tools
Documentation and Reports
  • Another way of monitoring progress, milestone
    slip chart.
  • The milestone slip chart compares planned and
    actual progress towards milestones. Planned
    progress is shown on the X-axis and actual
    progress on the Y-axis. Where actual progress is
    slower than planned progress slippage has
    occurred.

47
Project Phases and Management Tools
Documentation and Reports
48
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com