Title: Project Phases and Management Tools
1Project Phases and Management Tools
2Project Phases and Management Tools Network
Analysis
- Network Analysis or Critical Path Analysis
- Network Analysis requires breaking down the
project into tasks, arranging them into a logical
sequence and estimating the duration of each. - This Enables the series of tasks that determines
the minimum possible duration of the project to
be found. These are the critical paths - CPA aims to minimise time scale
3Project Phases and Management Tools Network
Analysis
- Pinpoints on the critical path would delay
project completion - Assist in allocating resources
- The events and activates form a diagram
- Drawing the diagram or chart involves the
following steps - Estimate the time needed to complete each
individual activity or task that makes up a part
of the project. - Sorting out what activites must be done one after
each after another, and which can be done at the
same time, if required.
4Project Phases and Management Tools Network
Analysis
- Representing these in a network diagram
- Estimating the critical path, which is the
longest sequence of consecutive activities
through the network - The duration of the whole project will be fixed
by the time to complete the largest path through
the network. This path is called the critical
path and activities on it are know as critical
activities. - Activities on the critical path must be started
and completed on time.
5Project Phases and Management Tools Network
Analysis
- Network Analysis shows the sequence of tasks and
how long they are going to take. The diagrams are
drawn from left to right.
6Project Phases and Management Tools Network
Analysis
- Events (eg 1 and 2) are represented by circles.
Tasks (eg A) connect events. - The critical path is represented by drawing an
extra line or a thicker line between the tasks on
the path. It is the minimum amount of time that
the project will take. - It is the convention to note the earliest start
date of any task in the top right hand corner or
the circle. - We can then work backwards identifying the latest
date when tasks have to start. These we insert in
the bottom right quarter of the circle - The critical path in this diagram is AEG. Note
the float time of five days for the Activity F.
Activity F can begin at any time between days 4
and 9, thus giving the project manager a degree
of flexibility.
7Project Phases and Management Tools Activity on
Node
- Microsoft Project software package
- Example Activity on Node
- Suppose that a project includes activities, C, D
and E. Neither activity D nor E can start until
activity C is completed, but D and E could be
done simultaneously if required. - This would be represented as follows.
D
C
E
8Project Phases and Management Tools Activity on
Node
- Note the following
- An activity with a network is represented by a
rectangular box (each box is a node). - The flow of activities in the diagram should be
from left to right. - The diagram clearly shows that D and E must
follow C. - A second possibility is that an activity cannot
start until two or more activities have been
completed. If activity H cannot start until
activities G and F are both complete, then we
would respresent the situation like this.
9Project Phases and Management Tools Activity on
Node
F
H
G
- In some conventions an extra node is introduced
at the start and end of a network, we recommend
that you do not do it.
10Project Phases and Management Tools Activity on
Node
- Example Starts and Ends
- Draw a diagram for the following project. The
project is finished when both D and E are
complete.
11Project Phases and Management Tools Activity on
Node
12Project Phases and Management Tools Activity on
Node
- Any network can be analysed into a number of
different paths or routes. A path is simply a
sequence of activities which can take you from
the start to the end of the network. In the
example above, there are just three routes or
paths. - ACD
- BD
- BE
- The time needed (duration) to complete each
individual activity in a project must be
estimated.
13Project Phases and Management Tools Activity on
Node
Example The Critical Path
What are the paths through the network? What is
the critical path duration?
14Project Phases and Management Tools Activity on
Node
Solution The Critical Path
15Project Phases and Management Tools Activity on
Node
- We could list the paths through the network and
their overall completion times as follows.
16Project Phases and Management Tools Activity on
Node
- The critical path is the longest, BFH, with a
duration of 12 weeks. This is the minimum time
needed to complete the project. - The critical path is indicated by a thick or
double line. - Listing Paths easy enough for small networks,
long and tedious task for bigger and more complex
networks. - Conventionally it has been recognised as useful
to calculate the earliest and latest times for
activities to start and finish.
17Project Phases and Management Tools Activity on
Node
- Project management software packages offer a much
larger variety of techniques than can easily be
done by hand. Microsoft Project allows each
activity to be assigned to any one of a variety
of types start as late as possible, finish no
earlier than, finish no later than etc.. - In real life, activity times can be shortened or
the may be constrained.
18Project Phases and Management Tools Activity on
Node
- Example Earliest and Latest Start Times
- These sections record the following things.
- The name for example Task A.
- An ID number
- The Duration
- The Earliest Start Time
- The Latest Start Time
19Project Phases and Management Tools Activity on
Node
- The earliest start times, always start with
activities that have no predecessors. - The work along each path from left to right
through the diagram calculating the earliest time
that the next activity can start. - To calculate an activities earliest time, simply
look at the box for the preceding activity and
add the bottom left figure to the top right
figure. - If two or more activities precede an activity
take the highest figure.
20Project Phases and Management Tools Activity on
Node
- The latest start times, are the latest times at
which each activity can start if the project as a
whole is to be completed in the earliest possible
time, in other words in 12 weeks in our example. - Work backwards from right to left through the
diagram calculating the latest time at which the
activity can start, if it is to be completed at
the latest finishing time. For example the latest
start time for activity H is 12-3 week9 and for
activity E is 12-5 week7. - Activity F might cause difficulties as two
activities, H and I, lead back to it. We take the
lower figure.
21Project Phases and Management Tools Activity on
Node
22Project Phases and Management Tools Activity on
Node
- The latest start times, are the latest times at
which each activity can start if the project as a
whole is to be completed in the earliest possible
time, in other words in 12 weeks in our example. - Work backwards from right to left through the
diagram calculating the latest time at which the
activity can start, if it is to be completed at
the latest finishing time. For example the latest
start time for activity H is 12-3 week9 and for
activity E is 12-5 week7. - Activity F might cause difficulties as two
activities, H and I, lead back to it. We take the
lower figure.
23Project Phases and Management Tools Activity on
Node
- Critical activities are those activities which
must be started on time, otherwise the total
project time will be increase. It follows that
each event on the critical path for the above
network is therefore BFH. - Criticisms of critical path/network analysis
- It is not always possible to devise an effective
WBS for a project - It assumes a sequential relationship between
activities - There are problems in estimation
- Does not appear to develop plans for
contingencies, other than crashing time. - CPA assumes a trade-off between time and cost.
This may not be the case where a substantial
portion of the cost is indirect overheads.
24Project Phases and Management Tools Activity on
Node
- Example Gantt Charts and Resources
- This example is provided as an illustration of
the use of Gantt chats to manage resources
efficiently. - A company is about to undertake a project about
wihcih the following data is available.
25Project Phases and Management Tools Activity on
Node
- There is a multi-skilled workforce of nine
workers available, each capable of working on any
activities. - Draw the network to establish the duration of the
project and the critical path. Then draw a Gantt
Chart, using the critical path as a basis,
assuming that jobs start at the earliest possible
time.
26Project Phases and Management Tools Activity on
Node
27Project Phases and Management Tools Activity on
Node
- It can be seen that if all activates start at
their earliest times, as many as 15 workers will
be required on any one day (days 6-7) whereas on
other days there would be idle capacity (days
8-12). - The problem can be reduced, or removed, by using
up spare time on non-critical activities. Suppose
we deferred the start of activities D and F until
the latest possible days. These would be days 8
and 9, leaving four days to complete the
activities by the end of day 12.
28Project Phases and Management Tools Activity on
Node
- The Gantt chart would be redrawn as follows
29Project Phases and Management Tools PERT
- PERT (Project evaluation and review technique) is
a technique for allowing for uncertainty in
determining project duration. Each task is
assigned a best, worst and most probable
completion time estimate, These estimates are
used to determine the average completion time.
The average times are used to establish the
critical path and the standard deviation of
completion times for the entire project. - PERT is a modified form of network analysis
designed to account for uncertainty, For each
activity in the project, optimistic, most likely
and pessimistic estimates of times are made.
These estimates are converted into a mean time
and also a standard deviation.
30Project Phases and Management Tools PERT
- Estimate the critical path using expected (mean)
activity times. - Estimate the standard deviation of the total
project time. - Exam focus
- PERT has not been mentioned in the syllabus, so
we have not included a worked example. Just be
aware that it exists and that it is designed to
build in an allowance for time uncertainity.
31Project Phases and Management Tools Resource
Histogram
- Resource Histogram
- A useful planning tool that shows the amount and
timing of the requirement for a resource (or
range of resources) is a resource histogram. - A Resource Histogram shows a view of project data
in which resource requirements, usage, and
availability are shown against a time scale.
32Project Phases and Management Tools Resource
Histogram
33Project Phases and Management Tools Resource
Histogram
- Some organisations add another bar (or a separate
line) showing resource availability.
34Project Phases and Management Tools Resource
Histogram
- Floating time is built into allow for unforeseen
circumstances - Total Float on a job is the time available
(earliest start date to latest finish date) less
time needed for the job. - Free Float is the delay possible in an activity
on the assumption that all preceding jobs as
early as possible and all subsequent jobs also
start at the earliest time. - Independent Float is the delay possible if all
preceding jobs have finished as late as possible,
and all succeeding jobs have started as early as
possible.
35Project Phases and Management Tools Project
Management Software
- Microsoft Project, Micro Planner X-Pert.
- Software might be used for a number of purposes
- Planning
- Estimating
- Monitoring
- Reporting
- Identifying the main steps, breaking these down
further into specific tasks.
36Project Phases and Management Tools Project
Management Software
- A typical project management package requires
four inputs. - The length of time required for each activity of
the project. - The logical relationship between each activity.
- The resources available.
- When the resources are available.
37Project Phases and Management Tools Project
Management Software
38Project Phases and Management Tools Resource
Histogram
- Two disadvantages of project management software
are - Some packages are difficult to use.
- Some project managers become to interested in
producing perfect plans that they spend to much
time producing documents and not enough time
managing the project.
39Project Phases and Management Tools
Documentation and Reports
- The name allocated to documents will vary across
different organisations. What is constant is the
need for clear and relevant documentation that
helps monitor and control the project. - Not a substitute for one-on-one communication.
- When outlining possible content of documents some
duplication of items occurs. - It is likely that the Project Initiation Document
will evolve until it is ultimately incorporated
into the Project Management Plan, sometimes
referred to as the Project Quality Plan.
40Project Phases and Management Tools
Documentation and Reports
- The Project Plan
- The project manager should also develop a Project
Plan. - The Project Plan is used to guide both project
execution and project control. It outlines how
the project will be planned, monitored and
implemented. - The project plan should include
- Project objectives and how they will be achieved
and verified. - How any changes to these procedures are to be
controlled. - The management and technical procedures and
standards to be used. - Details of the quality budget.
- The budget and time-scale.
- Safety, health and environmental policies.
- Inherent risks and how they will be managed.
41Project Phases and Management Tools
Documentation and Reports
- The project plan evolves over time. A high level
plan for the detailed plan for the current and
following stage. - At each subsequent lstage a detailed plan is
produced. - The Project Quality Plan outlines the quality
strategy to be followed and links this to any
formal quality management approach the
organisation has chosen to follow. - Distinction between a project management plan and
a quality plan is becoming increasingly blurred. - Key elements of a quality plan include
- The formal stages of the project
- Standards to be used throughout the project
- Controls that aim to ensure quality
- Checks to ensure quality
42Project Phases and Management Tools
Documentation and Reports
- Case Example
- Project Name
- Project Manager
- Purpose/Business Need
- Product Description and Deliverables
- Assumptions, Constraints and Risks
- Resources
- Financial
- Explanation of standards program
- Personnel/Volunteers
- Mandatory
- As Possible
- Approach
43Project Phases and Management Tools
Documentation and Reports
- Case Example cont.
- Communication and Reporting
- Monthly Status Report
- Monthly Resources Reports
- Financial Resources
- Human Resources
- Milestone and Critical Reports
- Acceptance
- Change Management
- Plan Acceptance
- By PMI Standards Program Team
- By Project Manager
44Project Phases and Management Tools
Documentation and Reports
- Example Extract from a call centre software
implementation Project Plan - Introduction
- Project roles
- Communication plan
- Training plan
- Change management plan
- Quality management
- Project documentation
- Financial management
- Programme management
45Project Phases and Management Tools
Documentation and Reports
- Progress Report
- A Progress Report shows the current status of the
project, usually in relation to planned status. - Frequency and contents of progress reports will
vary depending - The report is a control tool
- One for planned time, one for actual
- Additional content will depend on the format
adopted. Some organisations include only raw
facts in the report, as a basis for discussion. - Other organisations (particularly those involved
in long, complex projects) produce more
comprehensive progress reports, with more
explanation and comment. - A milestone is a significant event in the
project, usually completion of a major
deliverable.
46Project Phases and Management Tools
Documentation and Reports
- Another way of monitoring progress, milestone
slip chart. - The milestone slip chart compares planned and
actual progress towards milestones. Planned
progress is shown on the X-axis and actual
progress on the Y-axis. Where actual progress is
slower than planned progress slippage has
occurred.
47Project Phases and Management Tools
Documentation and Reports
48(No Transcript)