Title: Overview
1(No Transcript)
2(No Transcript)
3(No Transcript)
4Overview
- Who Development team and investment principals
- Where Siting assessments for wind, energy,
waves, and environment - What Activities to accomplish and equipment
needed for power plant in-service - When In-service date
- How Vision roadmap work to overcome
obstacles
5Transformer
Turbine
Tower
Interconnection / Switchgear
Substation / Transformer
Buried or Covered Cable
Foundation
Anti-scour Protection
Graphic Courtesy of Walt Musial - NREL
6Offshore Wind Development-Design-Build Process
Roadmap
Power Purchase Agreement
Electrical Civil Engineering
Electrical Civil Construction
Bidding Procurement
Site Assessment
Operations Maintenance
Startup Commission
Permits
7Who
8Development Team
- Electricity offtaker
- Developer
- Turbine supplier
- Major equipment suppliers
- Engineering
- Construction
- Commissioning all of above
9Developer Responsibilities
- Secure interconnection agreement, PPA, and
financing - Secure permits/approvals
- Project management
- Schedule
- Hire engineering and construction
- Equipment procurement
10Developer Responsibilities - cont.
- Economics through careful project design
- Public acceptance
- Schedule
- Development, engineering, construction, and OM
cost estimates - Revenue estimates
11Needed in Hand
- Permits go ahead
- Turbine Agreement performance, cost, delivery
date, warranty, OM rider - Interconnection Agreement to grid
- Power Purchase Agreement (PPA) who is paying
for power
12Where
13Site Assessment Activities
- Environmental fatal flaws
- Permitting requirements (federal, state, local)
- Constructability review
- Who can do it
- What needs to be done
- How it can be done
- When (season) to construct
- Government relations
- Mapping / Renderings
Site Assessment
14Wind Interconnect Studies
- Wind resource
- Turbine energy production drives revenues
- Coordination of interconnect studies and
preliminary electrical design
Power Curve
15Macro-Turbine Placement A Balancing Act of
Interests
- Meteorological studies best wind
- Setbacks shoreline, conservation and fishing
areas - Environmental geologic, archaeological,
threatened and endangered species, migratory and
aquatic life - Other preferences shipping lanes, viewshed
16Turbine Placement Tradeoffs
- Better wind and viewshed further from shore vs.
increased cable costs and electrical losses to
transport power onshore - Space between turbines to minimize cable costs
vs. minimizing wake effects - A turbine in the wind shadow of another decreases
energy output, increases turbulence - Component life
17Environmental Activities
- Shoreline/wetlands
- Ocean floor
- Threatened and endangered species
- Avian and marine impacts
- Archaeological and cultural artifacts
- Transmission lines
Permits
18Public Acceptance
- Viewshed
- Property values
- Land use and zoning for interconnection and
construction laydown - Recreational fishing and boating
- Other land and water uses
19What
20Role of the Utility
- Buy the energy under a PPA or
- Utility Ownership of Assets Rate Base
- Self-build utility as General Contractor, like
other power plants, or - Turnkey purchase wind farm at in-service,
relying on others experience
Power Purchase Agreement
21Power Purchase Agreement Pricing
- Need project capital, operating, and OM costs
- Equipment and labor prices change quickly
timing is everything - Need energy production estimates
- Wind resource
- Turbine production curves
- Loss estimates
- Develop pro forma to negotiate PPA pricing
22Major Cost Components Offshore Wind Farm (2002)
- Onshore Turbines Tower are 80 of cost
- Foundations and installation are expensive on
water
23Electrical Engineering
- Collector system
- Substation design / power factor corrections
- Transport line
- Interconnection
- System protection
- Communications/SCADA
Electrical Civil Engineering
24Collector System
- Individual turbines are strung together on low
ampacity cable to form a circuit - Line losses are a consideration function of
distance and cable ampacity - A 200-MW wind farm can use 20 miles of cable in
the collector system circuits alone, not
including to-shore cabling
25Civil Engineering Site Specific
- Geotechnical investigations
- Foundation design
- Wind, water, and ocean floor loadings
- Thermal testing
- Substation/Interconnection civil design
- Environmental conditions vs. loads are key
Electrical Civil Engineering
26Bidding Procurement
- Onshore is sellers market affects price, high
demand - Availability plan ahead
- Long lead times one year for the transformer
after specification - Contract administration
- Construction quality assurance evaluate
equipment during manufacturing process catch
problems early, before construction - Procurement desire multiple vendors
Bidding Procurement
27Electrical Civil Construction
- Surveying, site work, roads, restoration
- Foundations, piers, concrete
- Electrical collector systems
- Substations and grid interconnections
- Turbine erection
- Equipment installation
- Control building
Electrical Civil Construction
28Courtesy of Vestas Wind
29Planning Scheduling
- Coordinate thousands of activities
- Start during bid process
- Logistics of labor and materials
- Cranes, barges, helicopters, equipment delivery
dates - Critical path items
- Relationship of tasks (predecessors/successors)
30Construction Cost Control
- More than price of materials, labor, delivery
- Track changes and how they affect costs
- Minimize delays, control schedule
- Look at costs in real time during construction
phase - Include wind/weather delay days
31Health Safety
- Key focus for each construction team
- Offshore wind farms are in high wind areas
- Added challenge of construction under and over
water
32Startup Commissioning
- Component measurements
- In situ cable testing, etc.
- Construction environmental compliance
- Energization
- Performance testing
Startup Commissioning
33Operations Maintenance
- Electrical distances to interconnection may be
long - Plan for towers as storm shelters
- Corrosion
- Wave action and ice barriers
- Scour inspections
Operations Maintenance
34Operations Maintenance Needs
- Operations and data management information
systems (SCADA) - Scheduled and emergency maintenance and repair
plans - Environmental risk management systems and
programs - Emergency planning and response programs
35When
36When in North America
- Ontario 2 years to in-service turned into
current moratorium - Texas Public acceptance, high energy economy,
existing platforms, get it done, different
regulatory body within 10 miles of shoreline 3
years to in-service, 2010 - New England New approvals, politics (blue vs.
red), public acceptance 5 years public policy to
in-service, 2012 - Southeast Coast Hard questions already
answered 8 years in-service, 2015 - Ohio Offshore Lake Erie being reviewed now
37Roadmap Schedule
Power Purchase Agreement
Electrical Civil Engineering
Electrical Civil Construction
Bidding Procurement
Site Assessment
Operations Maintenance
Startup Commissioning
Permits
2007 - 2009
2010 -2012
2012
2012
2013
2014
2015
38How
39Offshore Wind Energy Collaborative Recommendations
- Technology development foundations,
constructability, size turbines to meet economics - Environmental compatibility
- Economic and financial viability
- Regulation and government policies
- Leadership must have legislative
40Strategies for Leadership
- Create and maintain a vision of offshore wind as
part of a mainstream energy mix - Develop projected timetable for key milestones
- Site-specific implementation plan Utility and
State coordinated document
41Offshore Roadmap QA
- Who Development team and investment principals
- Where Siting assessments for wind, energy,
waves, and environment - What Activities to accomplish and equipment
needed for power plant in-service - When In-service date
- How Vision roadmap work to overcome
obstacles
42Questions?Diane Reinebach, M.S., PERMT, Inc.,
an Alliant Energy Affiliatediane.reinebach_at_rmtinc
.com