Overview - PowerPoint PPT Presentation

1 / 42
About This Presentation
Title:

Overview

Description:

Where: Siting assessments for wind, energy, waves, and environment ... Diane Reinebach, M.S., PE. RMT, Inc., an Alliant Energy Affiliate. diane.reinebach_at_rmtinc.com ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 43
Provided by: stacey47
Category:

less

Transcript and Presenter's Notes

Title: Overview


1
(No Transcript)
2
(No Transcript)
3
(No Transcript)
4
Overview
  • Who Development team and investment principals
  • Where Siting assessments for wind, energy,
    waves, and environment
  • What Activities to accomplish and equipment
    needed for power plant in-service
  • When In-service date
  • How Vision roadmap work to overcome
    obstacles

5
Transformer
Turbine
Tower
Interconnection / Switchgear
Substation / Transformer
Buried or Covered Cable
Foundation
Anti-scour Protection
Graphic Courtesy of Walt Musial - NREL
6
Offshore Wind Development-Design-Build Process
Roadmap
Power Purchase Agreement
Electrical Civil Engineering
Electrical Civil Construction
Bidding Procurement
Site Assessment
Operations Maintenance
Startup Commission
Permits
7
Who
8
Development Team
  • Electricity offtaker
  • Developer
  • Turbine supplier
  • Major equipment suppliers
  • Engineering
  • Construction
  • Commissioning all of above

9
Developer Responsibilities
  • Secure interconnection agreement, PPA, and
    financing
  • Secure permits/approvals
  • Project management
  • Schedule
  • Hire engineering and construction
  • Equipment procurement

10
Developer Responsibilities - cont.
  • Economics through careful project design
  • Public acceptance
  • Schedule
  • Development, engineering, construction, and OM
    cost estimates
  • Revenue estimates

11
Needed in Hand
  • Permits go ahead
  • Turbine Agreement performance, cost, delivery
    date, warranty, OM rider
  • Interconnection Agreement to grid
  • Power Purchase Agreement (PPA) who is paying
    for power

12
Where
13
Site Assessment Activities
  • Environmental fatal flaws
  • Permitting requirements (federal, state, local)
  • Constructability review
  • Who can do it
  • What needs to be done
  • How it can be done
  • When (season) to construct
  • Government relations
  • Mapping / Renderings

Site Assessment
14
Wind Interconnect Studies
  • Wind resource
  • Turbine energy production drives revenues
  • Coordination of interconnect studies and
    preliminary electrical design

Power Curve
15
Macro-Turbine Placement A Balancing Act of
Interests
  • Meteorological studies best wind
  • Setbacks shoreline, conservation and fishing
    areas
  • Environmental geologic, archaeological,
    threatened and endangered species, migratory and
    aquatic life
  • Other preferences shipping lanes, viewshed

16
Turbine Placement Tradeoffs
  • Better wind and viewshed further from shore vs.
    increased cable costs and electrical losses to
    transport power onshore
  • Space between turbines to minimize cable costs
    vs. minimizing wake effects
  • A turbine in the wind shadow of another decreases
    energy output, increases turbulence
  • Component life

17
Environmental Activities
  • Shoreline/wetlands
  • Ocean floor
  • Threatened and endangered species
  • Avian and marine impacts
  • Archaeological and cultural artifacts
  • Transmission lines

Permits
18
Public Acceptance
  • Viewshed
  • Property values
  • Land use and zoning for interconnection and
    construction laydown
  • Recreational fishing and boating
  • Other land and water uses

19
What
20
Role of the Utility
  • Buy the energy under a PPA or
  • Utility Ownership of Assets Rate Base
  • Self-build utility as General Contractor, like
    other power plants, or
  • Turnkey purchase wind farm at in-service,
    relying on others experience

Power Purchase Agreement
21
Power Purchase Agreement Pricing
  • Need project capital, operating, and OM costs
  • Equipment and labor prices change quickly
    timing is everything
  • Need energy production estimates
  • Wind resource
  • Turbine production curves
  • Loss estimates
  • Develop pro forma to negotiate PPA pricing

22
Major Cost Components Offshore Wind Farm (2002)
  • Onshore Turbines Tower are 80 of cost
  • Foundations and installation are expensive on
    water

23
Electrical Engineering
  • Collector system
  • Substation design / power factor corrections
  • Transport line
  • Interconnection
  • System protection
  • Communications/SCADA

Electrical Civil Engineering
24
Collector System
  • Individual turbines are strung together on low
    ampacity cable to form a circuit
  • Line losses are a consideration function of
    distance and cable ampacity
  • A 200-MW wind farm can use 20 miles of cable in
    the collector system circuits alone, not
    including to-shore cabling

25
Civil Engineering Site Specific
  • Geotechnical investigations
  • Foundation design
  • Wind, water, and ocean floor loadings
  • Thermal testing
  • Substation/Interconnection civil design
  • Environmental conditions vs. loads are key

Electrical Civil Engineering
26
Bidding Procurement
  • Onshore is sellers market affects price, high
    demand
  • Availability plan ahead
  • Long lead times one year for the transformer
    after specification
  • Contract administration
  • Construction quality assurance evaluate
    equipment during manufacturing process catch
    problems early, before construction
  • Procurement desire multiple vendors

Bidding Procurement
27
Electrical Civil Construction
  • Surveying, site work, roads, restoration
  • Foundations, piers, concrete
  • Electrical collector systems
  • Substations and grid interconnections
  • Turbine erection
  • Equipment installation
  • Control building

Electrical Civil Construction
28
Courtesy of Vestas Wind
29
Planning Scheduling
  • Coordinate thousands of activities
  • Start during bid process
  • Logistics of labor and materials
  • Cranes, barges, helicopters, equipment delivery
    dates
  • Critical path items
  • Relationship of tasks (predecessors/successors)

30
Construction Cost Control
  • More than price of materials, labor, delivery
  • Track changes and how they affect costs
  • Minimize delays, control schedule
  • Look at costs in real time during construction
    phase
  • Include wind/weather delay days

31
Health Safety
  • Key focus for each construction team
  • Offshore wind farms are in high wind areas
  • Added challenge of construction under and over
    water

32
Startup Commissioning
  • Component measurements
  • In situ cable testing, etc.
  • Construction environmental compliance
  • Energization
  • Performance testing

Startup Commissioning
33
Operations Maintenance
  • Electrical distances to interconnection may be
    long
  • Plan for towers as storm shelters
  • Corrosion
  • Wave action and ice barriers
  • Scour inspections

Operations Maintenance
34
Operations Maintenance Needs
  • Operations and data management information
    systems (SCADA)
  • Scheduled and emergency maintenance and repair
    plans
  • Environmental risk management systems and
    programs
  • Emergency planning and response programs

35
When
36
When in North America
  • Ontario 2 years to in-service turned into
    current moratorium
  • Texas Public acceptance, high energy economy,
    existing platforms, get it done, different
    regulatory body within 10 miles of shoreline 3
    years to in-service, 2010
  • New England New approvals, politics (blue vs.
    red), public acceptance 5 years public policy to
    in-service, 2012
  • Southeast Coast Hard questions already
    answered 8 years in-service, 2015
  • Ohio Offshore Lake Erie being reviewed now

37
Roadmap Schedule
Power Purchase Agreement
Electrical Civil Engineering
Electrical Civil Construction
Bidding Procurement
Site Assessment
Operations Maintenance
Startup Commissioning
Permits
2007 - 2009
2010 -2012
2012
2012
2013
2014
2015
38
How
39
Offshore Wind Energy Collaborative Recommendations
  • Technology development foundations,
    constructability, size turbines to meet economics
  • Environmental compatibility
  • Economic and financial viability
  • Regulation and government policies
  • Leadership must have legislative

40
Strategies for Leadership
  • Create and maintain a vision of offshore wind as
    part of a mainstream energy mix
  • Develop projected timetable for key milestones
  • Site-specific implementation plan Utility and
    State coordinated document

41
Offshore Roadmap QA
  • Who Development team and investment principals
  • Where Siting assessments for wind, energy,
    waves, and environment
  • What Activities to accomplish and equipment
    needed for power plant in-service
  • When In-service date
  • How Vision roadmap work to overcome
    obstacles

42
Questions?Diane Reinebach, M.S., PERMT, Inc.,
an Alliant Energy Affiliatediane.reinebach_at_rmtinc
.com
Write a Comment
User Comments (0)
About PowerShow.com