Title: 3310: cProjects Implementation at Computer Associates Challenges
13310 cProjects Implementation at Computer
Associates- Challenges Solutions
- Alfredo Garza, CA Inc.
- Srinivasa Munagavalasa, CA, Inc.
- Susan Wong, CA, Inc.Raj Una, GyanSys, Inc.
2- CA, formerly known as Computer Associates
International, Inc., the world's largest
management software company, delivers software
and services across operations, security,
storage, life cycle and service management to
optimize the performance, reliability and
efficiency of enterprise IT environments. - Founded in 1976, CA today is a global company
with headquarters in the United States and 150
offices in more than 45 countries. We serve more
than 98 of Fortune 1000 companies, as well as
government entities, educational institutions and
thousands of other companies in diverse
industries worldwide. - Our product brands include
- Unicenter
- BrightStor
- AllFusion
- Advantage
- CleverPath
- eTrust
- CA also provides professional services, such as
consulting and education.
3CA Transformation
- Global rapid-implementation SAP initiative
targeted toward enabling the capabilities of SAP
ECC, CRM, SRM, BI, SEM, EP, cProjects and WFM
Core. The project fundamentally transforms both
the technology and process of CA operations in
North America, Europe, Asia / Pacific, and Latin
America. - The project is structured around 8 key delivery
work streams - Marketing
- Lead to Quote / Customer Interaction Center
- Order to Cash
- Procure to Pay
- Manage the Business
- Business Intelligence
- Human Resources
- Professional Services
- Business Readiness and Project Management are
other horizontal streams created to ensure
communication, quality and control across all
work areas.
4CA Transformation - Goals
- CAs main goal is to transform its IT strategy
and architecture so that the company and the CIO
gets the most return out of an integrated and
secure IT system. - These goals include
- Boosting sales and reducing operating costs
- Improving customer relationships and marketing
- Improving supplier relationship management and
procurement of indirect materials - Achieving the level of financial reporting
transparency to meet the requirements of the
recent Sarbanes-Oxley act - Improving product strategy, life-cycle management
and distribution
5Goals for Professional Services at CA
- Integrate system processes from lead to cash to
run the business efficiently - Automate Professional Services processes
- Segregation of duties between operational
resources and financial resources - Eliminate data redundancy and improve data
consistency - Use industry best practices to improve
Professional Services business processes - Improve partner relationships
- Improve client and services profitability
- Improve resource realization and utilization
- Growing the business
6cProjects Technical Infrastructure at CA
- Implementing the SAP Professional Services
solution for Pre-Sales and Services delivery
projects for the following areas - cProjects Suite 3.1/WFM Core 1.1 (CRM add-on)
- CRM 4.0
- ECC 5.0 (PS, FI/CO, MM, HR, SD and CATS)
- SRM 4.0
- BI 3.5
- EP 6.0
7Professional Services Challenges As Is
Landscape
8Professional Services Integrated System - To Be
Landscape
9Demand-side/Acquisition Business Process Flow
CRMOpportunityManagement
Quote
Quoting
Enter time/expensesfor Cost Collection
TimeExpense
High Level OpportunityPlanning
Activities Mgmt
Pre-Sales OpportunityExecution
Engage Presales Consultants NOTE Not All
Activities will Engage Pre-Sales
Collaboration among Internal Business partners
and external clients
Pre-Sales OpportunityMgmt
Create cProjectlinked to CRM Opportunity
NOTE Only when Pre-Sales is
engaged
Schedule Resources NOTE CA TS Resources can be
allocate
Opportunity/Resource Planning
10Supply-Side/Fulfillment Business Process Flow
ProjectManagement
Opportunity Mgmt
Bill
Milestones
High Level ProjectPlanning
ProjectMonitoring and Control
TimeExpense
Cost Calculation
Quote Final
Confirmation
ProjectExecution
RefineProjectPlanning
Soft booking
Capacitycheck
Signed Contracts
Budgeting
Refine ProjectPlanning
Resourcereallocation
Define Accounting Rules
Hard booking
Project Resource Planning
11Implementation Challenges at CA
- cProjects (Ver 3.1)
- Budgeting in cProjects no integration with
Project System for Cost and Revenue Planning - Services Billing single billing indicator at
top level WBS Element in Project System - Time Entry resource worklist for time entry
- Project System
- RRB for External Resources
- Complexities around Revenue Recognition
12Project Cost and Revenue Planning
- Enhancement
- Task-based replication to support the creation
and ongoing synchronization of WBS elements with
cProject tasks - Project revenue plan in cProjects by mimicking
Sales Pricing - The project rates used to create the revenue plan
is also used to create pricing records required
for quoting and billing - Cost rate determination enhanced to mimic costs
configured in ECC. - Project billable and non-billable expenses
entered in cProject as a total amount for project
cost planning - Business Benefit
- Reduced manual effort from Services Accounting
- Configuration for cost rate and bill rate in one
place, and consistency in rates used for planning
13Billing Plan and Milestones
- Enhancement
- For fixed price projects, it is necessary to
assign a billing plan to the project. The billing
plan can be for either the scheduled billing
dates or for the completion of milestones - Project Managers has the flexibility to create
and maintain project bill plan with ease on
portal screen - Business Benefit
- Consistent entry point Portal
- Eliminates access to financial-oriented fields -
SOX compliant
14Time Sheet Worklist and Validation
- Enhancement
- The worklist section of CATS will display the
valid WBS elements (cProjects tasks) that are
assigned to the resource entering time - Internal and external resources enter actual
project hours in the consistent manner by
entering it against the project task WBS element
through CATS - Time sheet cannot be saved if resource enters
time against a WBS Element not in the worklist - Business Benefit
- Reduced error in time entered against projects
- Streamlined time entry for resources
15CATS Actual Time Update to cProjects
- Enhancement
- Synchronize the actual start date and the actual
number of hours based on the approved CATS time
entries in cProjects - Reflect in cProjects any time adjustments made in
CATS - Business Benefit
- Eliminate Project Manager data entry effort for
actual start date and actual number of hours - Accurate reporting of project percentage of
completion available to Project Managers in
cProjects
16Inherent Data on Debit Memo Request
- Enhancement
- Make available on the billing invoice details the
employee/partner that performed the work - Accounts for multiple consultants working in the
same role, and/or where the invoicing period
covers multiple timesheets - Business Benefit
- Provides clear accountability to the customer of
the hours approved and the corresponding amounts
to be invoiced - Business and the customer can have a clear
visibility
17Detailed Revenue Reporting
- Enhancement
- Three primary steps
- Select appropriate reporting characteristics in
cProjects - Replicate these attributes to ECC
- Manipulate, aggregate or split, the settlement
rules data is used during settlement to ECC
CO-PA, and as a result, accounted for in
subsequent extraction to BW - Example standard and custom key fields and
characteristics - Person Responsible
- Type of Service
- Product Family
- Practice, Sub-practice
- Business Unit and Geography
- Business Benefit
- The centralization of this information including
department revenue and profitability will reduce
the effort to support reporting for internal
financial reporting - Tying reporting characteristics to the task level
will enable professional services management to
accurately collect reporting information
18cProjects Other Enhancements
- cProjects System Numbering
- Internal number generated
- Field for number assignment in display mode only,
no external numbering allowed - Contribution Margin Report
- Project manager plans each task and role of
cProject with start date, end date and number of
hours - Based on these values, system creates cost plan
and revenue plan - Enhancement is to calculate the NOM and
contribution margin from the cost plan and
revenue plan - This report is required to get the approval on
the quotation - Consultant View of project bookings for Business
Partners - Calendar view of appointments by week and month,
not just by day - Allocation information can be viewed, but in a
relatively user-friendly format
19Benefits of cProjects at CA
- Single point of data entry for project planning
- Web based project management tool
- Resource scheduling
- Traffic light reports and alerts (evaluations)
- Project version management
- Integration with SAP core modules
- Segregation of duties (Project Managers, Resource
Coordinators, Services Accounting) - Data flow across modules
20Key Lessons Learned at CA
- Integration with other work streams
- Global design for global rollout
- Complexity in currency and language
- Overcome numerous SOX non-compliant issues
created by changing business economics and SEC
requirements due to integration with multiple
work streams - Process Control
- Authorization
- Industrial Best practices
- Tight integration between cProjects and ECC
- Synchronization time/resources.
- Project planning and pricing at controlled
source, cProjects - Workflow