Title: IBEX Science Operations Center ISOC Status
1SWT
IBEX Science Operations Center (ISOC) --
Status Nathan A. Schwadron
Southwest Research Institute3/9/09
2Orbit Orientation Good for Science
Apr 1
- Good orientation for Global ENA maps
- Hole from magnetospheric obscuration opposite the
line of apsides (apogee to Earth) - Good orientation for Interstellar Oxygen and
Helium measurements - From day 10-60 (spring viewing)
- From day 255 - 290 (fall viewing)
- The orbit orientation is a change from planned
launch during Summer 08
Int. Flow Vector
Jan 1
July 1
Oct 1
3IBEX Trajectory
4Apogee Perigee Altitudes
5View time per Pixel for 2 year Mission
Reduction in view time due to magnetosphere
obscuration
6IBEX Doses
- Perigee optimized (higher perigee altitude) for
lower doses
7ISOC Computing Hardware
- All Computers Up and Running
- BU RAID had some problems
- The RAID has been replaced and is currently being
configured - Considering a Hot Swap solution at BU
8Data Flow
9ISOC to MOC Interface
- Secure ftp connection to MOC has been stable
- No problems in retrieving data from the MOC
- Science Tasking Files have been extremely useful
and successful - Fairly automated facility for generating and
incorporating special payload commands -
10Data Product Foundation Science Telemetry Types
11Data Product Hierarchy
12Archiving and Distribution
- ISOC (BU)
- Telemetry Archive ?
- Housekeeping Archive ?
- Science Archive with web distribution ?
- Mirrored Archives at SwRI ?
- SPDF and NSSDC
- Level 1,2 to SPDF
- Validated Level 0-2 data for permanent archive
- Virtual Heliospheric Observatory (VHO)
13ISOC Security
- No programmatic risks associated with Science
- No Security Issues have arisen
14Backup Systems
- Currently 7 Complete IBEX Data Sets on 5 Machines
at 3 Separate Locations - BU ISOC mirrored at SwRI
- RAID system mirrored at each site
- One RAID recently replaced and under
configuration - BU system backed up internally on a weekly basis
(BU Information and Technology Center) - We are reassessing which drives are backed up
- SwRI system backed on a weekly basis
- Computers under warrantee (3 years)
15ISOC SW Development
- Point Release of Build 3 at Launch - Done
- S/W Build 4 (Mission Rehearsal 3) - Done
- Refinement of software
- Additional tools for housekeeping data
- S/W Build 5 (Half Sky Map)
- 3 Months of Science Data, currently in work
- S/W Build 6 (Full Sky Map) - 6 Months of Science
Data
16PLFW Status
- PLFW fully Designed, Integrated Tested
- ISOC Testing of PLFW Complete
- 8-day exercise revealed no significant PLFW
anomalies - Build 5.1 loaded to Spacecraft June 12, 2008
- Adds 15 Margin
- Build 6.0 (30 Margin) Designed and Tested
- To be used only if required
- Currently Considering Software Change To Optimize
Science from IBEX-Lo Direct Events - Macros uploaded (early Jan) that allow more
flexibility in IBEX-Hi and IBEX-Lo Operation - The sensors are now brought up independently and
IBEX-Hi collimator voltages can be reduced when
in the quiet solar wind
17Science Software Development
- Development currently through Level 3.3
- Intense focus currently on
- web tools
- plotting software
- new capabilities for event sorting
- Software for global maps
18Changes as a Result of Commissioning
- IBEX-Lo uses only its negative collimator in a
much lower setting (-400 V) - Lo ascending macro (HVSCI) occurs well after
IBEX-Hi ascending macro - IBEX-Lo has a large number of electron counts
- Software change to prevent electron counts from
swamping the telemetry - IBEX-Hi collimator voltages lowered in solar wind
to prevent the solar wind from entering the
instrument - Change to the operation plan to trigger a
transition from higher to lower collimator
voltages - ACS Software updated to fix problems with Spin
Pulse Timing
19Trending and Housekeeping
- A set of trending and housekeeping plots have
been developed - Trending data posted weekly by C. Prested
- PL Teams, CEU Team Review Data and Provide
Feedback - All systems nominal
20The Solar Wind Background (1/3)
- Deflected Solar Wind Incident on the IBEX-Hi
Sensor creates a sizable background
21The Solar Wind Background (2/3)
- SW background highly correlated to the SW
deflection angles
Double Triples
Deflection y
Deflection z
22The Solar Wind Background (3/3)
- Correspondence between incident solar wind flux
and ena rate
23Strategy for Map Making
- Identify periods of low background in each orbit
for IBEX-Lo and IBEX-Hi - Paul Janzen keeper of the IBEX-Hi list
- David Heirtzler keeper of the IBEX-Lo list
- Subtract out a realtively constant background in
IBEX-Hi - 0.057 Hz
- Correct for
- Moving SC frame
- ENA deflection by radiation pressure
- ENA loss through Ionization
- ENA energy change through heliospheric
transmission
24ESA Step 1
25ESA Step 2
26ESA Step 3
27ESA Step 4
28ESA Step 5
29ESA Step 6
30Nose vs Tail
Nose
Tail
31North vs South
North
32A quick comparison
33Conclusions
- Science Operations are going well!
- Recovering First Maps Energy Distributions
34Energy Distribution Mapping
35(No Transcript)
36Acronyms
- BU - Boston University
- Cal - Calibration
- CEU - Central Electronics Unit
- CPT - Comprehensive Performance Test
- CRaTER - Cosmic Ray Telescope for Effects of
Radiation - Def. - Define
- Dict - Dictionary
- Dutils - Data Utilities
- DE - Direct Event
- ENA - Energetic Neutral Atom
- H/K - Housekeeping
- I/F - Interface
- ISOC - IBEX Science Operations Center
- LANL - Los Alamos National Lab
- LMATC - Lockheed Martin Advanced Technology Center
37Acronyms
- ME - Meta Event
- MOC - Mission Operations Center
- NSSDC - National Space Science Data Center
- P/L - Payload
- PLFW - Payload Firmware
- S/C - Spacecraft
- SCB - Spacecraft Bust
- SOC - Science Operations Center
- SPDF - Space Physics Data Facility
- SwRI - Southwest Research Institute
- SW - Software
- Tlm - Telemetry
- VHO - Cirtual Heliospheric Observatory
38BACKUP
39PLFW LUT Upload Testing
- PLFW and LUT has been successfully uploaded onto
the Spacecraft and FlatSat on several occasions
with no issues - MOC procedures for PLFW LUT in-flight upload
have been run with designated flight controller
personnel awaiting final release - Spacecraft Uploads
- Build 5.1 associated LUT successfully uploaded
into CEU EEPROM 6/11-12/08 and verified by CPT - Additional run time on S/C 7/17/08
- Successful upload of PLFW partial LUT into SRAM
as part of CEU LV Commissioning Procedure - FlatSat Uploads
- Pre-Build 5.1 Installation on S/C
- Mission Rehearsal 2 6/17/08
- Additional run time on FlatSat (ongoing)
40PLFW LUT Upload Testing
- Spacecraft Uploads
- Build 5.1 Installation 6/11-12/08
- Build 5.1 associated LUT successfully uploaded
into S/C EEPROM - Upload verified by P/L CPT (TP6205_A), LVSCI test
applicable part of ACS (TP4630) CDH CPT - Additional Runtime on S/C 7/17/08
- Build 4.0 partial LUT successfully uploaded
into SRAM (S924-31801_A CEU LV Commissioning
Procedure) - FlatSat Uploads
- Pre-Build 5.1 Installation on S/C
- Build 5.1 LUT upload performed first on FlatSat
- Upload verified by P/L CPT (TP6205_A), LVSCI test
applicable part of ACS (TP4630) CDH CPT - Mission Rehearsal 2 6/17/08
- Build 4.0 partial LUT successfully uploaded
into SRAM (S924-31801_A CEU LV Commissioning
Procedure) - Additional Runtime on FlatSat (ongoing)
- Many pre-MR2 iterations of upload into SRAM with
CEU team, Flight Director both Flight
Controllers during Friday procedure walkthroughs
from MOC (S924-31801_A CEU LV Commissioning
Procedure) - Build 5.1 Upload additional testing with Flight
Controller for procedure release - Partial LUT Upload testing with Flight Controller
for procedure release
41ISOC Elements
- SwRI Mirror ISOC
- SOC Computer Mirrors
- RAID Array
- Maestro Station, GSEOS Laptops
- Hardware at SwRI
- SCB Sim (3'x2'x4')
- CEU Sim
- IBEX-Hi Sim
- IBEX-Lo Sim
- BU ISOC
- SOC Computers
- RAID Array
- Web Server
- BU Facilities
- Secure Computer Room
- ISOC Center Lab
- Undergraduate Area
All facilities up and running
42Configuration Control
- All Software is under Subversion (SVN) control
- Use process for capturing and regression testing
releases - Releases can be patched or new releases rolled
out - All the data analysis carried out with reference
to a specific software release - Results under one release can be
directly compared with other releases - All telemetry data is captured with cryptographic
checksums and processing starts - Difficult if not impossible to hack the data
- Data and processing are duplicated at 2 sites (BU
SwRI) far enough apart to withstand disasters
43Global Forward Mapping
44Energy Distribution Mapping
45Global Forward Mapping