Installation of New CHP system at the Old Aberdeen Campus - PowerPoint PPT Presentation

About This Presentation
Title:

Installation of New CHP system at the Old Aberdeen Campus

Description:

The existing steam mains were increasingly leaking. ... This engine is capable of producing 1,630 kW of electricity and 1,700 kW of heat. ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 13
Provided by: XP479
Category:

less

Transcript and Presenter's Notes

Title: Installation of New CHP system at the Old Aberdeen Campus


1
Installation of New CHP system at the Old
Aberdeen Campus

2
Background
  • The Central Heating Station at the Old Aberdeen
    Campus was 30 years old and the boilers were due
    for replacement.
  • The existing steam mains were increasingly
    leaking.
  • The electricity supply to the site was through 3
    separate supplies, 2 at HV, 1 at LV.

3
Selection of New Plant
  • An Option Appraisal was carried out considering a
    number of replacement alternatives.
  • The decision was taken to replace the old Central
    Heating station with a new Combined Heat and
    Power station.
  • This would supply the Old Aberdeen Campus with
    both heating and electricity.

4
Scope of Works
  • A brand new heating station, to be built at
    Bedford Road.
  • New CHP engine, boilers and ancilliary equipment
    to be installed.
  • The existing steam pipe work to be removed and
    new LTHW pipe work to be installed forming a ring
    main.
  • Reinforcement of the 11kV equipment, and
    installation of an 11kV ring main.

5
Cost
  • Cost of the new installation
  • 10 Million pounds
  • (Of which 1.75 Million was a Community Energy
    Programme Grant from the Energy Savings Trust)

6
(No Transcript)
7
CHP engine details
  • The CHP engine installed is a Jenbacher 612, 12
    cylinder engine that is fired on natural gas.
  • This engine is capable of producing 1,630 kW of
    electricity and 1,700 kW of heat.
  • The engine is set up to supply the University
    only and there is no export of electricity to the
    grid.
  • The electrical output is sized to be able to meet
    the electrical baseload for the Old Aberdeen
    Campus which will give the maximum number of
    hours operation in this mode of operation.
  • This load corresponds to approximately half of
    the Old Aberdeen Campus peak electrical demand of
    3,300 kW. Over a year the engine is projected to
    produce over 60 of the Campus site electricity
    requirements

8
(No Transcript)
9
CHP engine details
  • By making use of the heat the overall efficiency
    of the engine is 83 which compares very
    favourably with power stations.
  • The result of this overall improvement of power
    generation efficiency is a substantial reduction
    in emissions, at the Old Aberdeen Campus, arising
    from use of electricity. Carbon dioxide emissions
    are reduced, and additionally oxide of nitrogen
    levels are reduced by 45.

10
(No Transcript)
11
Carbon Dioxide Emissions
  • The CHP unit has been running since May 2007 and
    has already reduced carbon dioxide emissions by
    over 1,200 tonnes from the University of
    Aberdeen.

12
Cost Saving
  • The projected cost saving for the year 2007/2008
    is
  • 500,000
Write a Comment
User Comments (0)
About PowerShow.com