Production and Scheduling

Jack Fowler
2
Production Scheduling
  • LOB - Line of Balance
  • Scheduling technique used to compare planned vs
    actual
  • All components in module production have LOB
  • LOB monitored monthly by TRT project engineering
    office at BNL
  • Due to delays in part procurement Recovery Plan
    developed
  • Recovery Plan approved at Lehman Review Sep
    2000
  • All LOBs are driven by Microsoft Project master
    schedule

3
Type 2 - LOB Recovery Plan
4
Type 3 - LOB Recovery Plan
5
Duke Production Schedule
6
Type 2 Schedule Times
  • Current estimate to complete a type 2 module is
    50 days
  • 18 days mechanical
  • 22 days stringing
  • 10 days testing
  • Module 2.1 took 46 days without final testing
  • 20 days mechanical
  • 26 days stringing
  • Module 2.2
  • 19 days mechanical

7
Type 3 Schedule Times
  • Current estimate to complete a type 3 module is
    62 days
  • 21 days mechanical
  • 26 days stringing
  • 15 days testing

8
Production Scheduling
  • One production line is fully operational
  • Second production line will be operational in Oct
    2000
  • Currently have 3 full time technicians
  • Will have all 6 of the technicians by end of 2000

9
Module Completion Summary
  • 2000 - 4 Type 2
  • 2001 - 19 Type 2 and 7 Type 3
  • 2002 - 14 Type 2 and 10 Type 3
  • All modules will be completed by end of 2002

10