The Improvement of ALARA for the Steam Generator Maintenance - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

The Improvement of ALARA for the Steam Generator Maintenance

Description:

shielded the hot spot (manway retainer plate) with lead blanket - before ... radiation waste probe into the lead shield cask promptly and dispatched the cask ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 16
Provided by: jne2
Category:

less

Transcript and Presenter's Notes

Title: The Improvement of ALARA for the Steam Generator Maintenance


1
The Improvement of ALARA for the Steam Generator
Maintenance
  • Radiation Safety Department
  • The 3rd Plant, Ulchin Nuclear Power Site

2
CONTENTS
  • Background
  • Summary
  • Review of ALARA
  • The main improvements and effects
  • Conclusions

3
BACKGROUND
ALARA performed focusing on the SG
maintenance during the 2nd overhaul of
Ulchin Unit 5 in 2006. ? the highest occupational
exposure ? the greatest spread of contamination ?
in particular with poor radiation work
environment
4
SUMMARY
Flow chart of SG Maintenance
5
SUMMARY
  • Radiation work dose
  • ? work duration 9/11/200610/4/2006 (24 days)
  • ? workers 92 persons (932 man-days)
  • ? radiation dose

- Individual dose mSv/person
limit average maximum maximum remarks
limit average work dose accumulated dose remarks
16 (20) 0.55 3.61 15.31 worker of ECT
regulatory limits
6
SUMMARY
  • - Collective dose (man-mSv)

SG maintenance planned real remarks
manway (open/close) 9 6.58 - 2.42
nozzle dam (install/remove) 9 8.86 - 0.14
ECT 38.5 28.02 - 10.48
lancing FOSAR 12 6.25 - 5.75
total 69.5 49.71 - 19.79
ECT maintenance dose was 16.6 of the total
dose for overhaul (298.7 man-mSv/34days)
7
REVIEW OF ALARA
  • SG cooling method before the year 2006
  • ? Tube and chamber cooled and dried by air
    blower after reactor coolant water made them
    cooled
  • - Took a long time to reach the proper
    temperature (about 30?)
  • - The maintenance should be performed in the
    work environment
  • with high temperature and humidity to meet the
    overhaul
  • schedule.
  • ? The temporary manway cover did not completely
    seal the hole of SG manway due to a decrease the
    function of the air blower to dry and purify the
    contamination and humidified air inside SG tube.

8
REVIEW OF ALARA
Radiation protection ? Work planning ? Source
of radiation ? Protection of radiation worker ?
Area contamination control ? Environmental
condition of work place
9
THE MAIN IMPROVEMENTS EFFECTS
  • Efficient maintenance minimized the radiation
    dose by modifying the cooling method of SG
  • ? Cooling to utilize the heat exchanger of the
    SG blow down system
  • - cooling time about 46 hours
  • - outlet temp of cooling water 15?
  • ? Installing the manway temporary cover-only to
    seal the hole of SG manway (hot leg and cold leg)
  • - dimension (dia.) 700 (T) 3 mm
  • - air exhaust hole (dia.) 50 (H) 80 mm
  • - spray nozzle hole (dia.) 50 (T) 2 mm
  • - material SS304

10
THE MAIN IMPROVEMENTS EFFECTS
Cooling Flow
11
THE MAIN IMPROVEMENTS EFFECTS
The manway temporary cover-only
BEFORE
AFTER
12
THE MAIN IMPROVEMENTS EFFECTS
  • Results
  • ? Optimization of working environment
  • - working hours were shorter and the
    troubles of ECT
  • equipment were less than those of the
    previous SG
  • maintenance
  • ? Comparison to 2005

items 2005 (the 1st OH) 2006 (the 2nd OH) remarks
work duration 18 days 14 days - 4 days
temperature in chamber about 80? less than 30 ? - 50 ?
replacement of ECT probe 176 ea 117 ea - 59 ea
work dose man-mSv 72.07 49.71 - 22.36
13
THE MAIN IMPROVEMENTS EFFECTS
  • Reduction of radiation dose and prevention of
    contamination
  • ? Dose rate reduction of work area
  • ? shielded the hot spot (manway retainer plate)
    with lead blanket
  • - before shielding 4.0 mSv/hr
  • - after shielding 0.9 mSv/hr
  • ? put the high radiation waste probe into the
    lead shield cask promptly and dispatched the cask
    to the temporary stored area.
  • ? decontaminated quickly when the surface over
    the work area was contaminated from the high
    contaminations such as the sludge of the waste
    ECT equipment probe.

14
THE MAIN IMPROVEMENTS EFFECTS
  • Prevention of internal and external
    contamination
  • ? worn respirator
  • - air supplied respirator for jumper
  • - full-face mask for ECT and manway working
  • ? should not touch own face and head
  • Preventing the spread of contamination
  • ? wore the safety shoes for work place-only
  • ? kept the step barrier when going in and out
  • ? monitored the trend of surface contamination
    level and air borne activity
  • ? used the tools and equipment with proper
    packing, and installed the
  • cable for ECT to the upper side
  • ? periodically checked contamination of safety
    shoes and exchanged as
  • necessary
  • Decontaminated and cleaned overall area such
    as floor, pipes, grating etc in the end of
    overhaul

15
CONCLUSIONS
  • Our plant could successfully achieve the
    reduction
  • in radiation dose as well as raising the
    quality of
  • maintenance by optimizing the work
    environment
  • such as improvement of the SG cooling method,
  • and decreasing the dose rate of work area.
  • Preventing the spread of contamination through
  • absolute analysis for ALARA from the
    preparation
  • to the beginning of SG maintenance.
Write a Comment
User Comments (0)
About PowerShow.com