Stone Creek Floodplain Letter of Map Revision LOMR - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Stone Creek Floodplain Letter of Map Revision LOMR

Description:

... allows the modification or revision of FEMA's Flood Insurance Rate Maps (FIRMs) ... The floodplain contains Base Flood Elevations (BFE) for accurately ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 13
Provided by: lachie
Category:

less

Transcript and Presenter's Notes

Title: Stone Creek Floodplain Letter of Map Revision LOMR


1
Stone Creek Floodplain Letter of Map Revision
(LOMR)
  • July 28, 2009

2
Background
  • Letter of Map Revision (LOMR) is a FEMA process
    that allows the modification or revision of
    FEMAs Flood Insurance Rate Maps (FIRMs)
  • All LOMR requests must be signed by the
    Communitys Chief Executive Officer (CEO) as
    designated by FEMA.
  • Peter Runyon is Eagle Countys CEO

3
Project Partners
  • Colorado Water Conservation Board (50 Grant)
  • Eagle-Vail Metropolitan District (10)
  • Eagle-Vail Property Owners Association (10)
  • Stone Creek Committee (13.3)
  • Eagle County (16.7)

Total Budget 50,000
4
Project Timeline
  • Contract to Matrix Design Group, Inc. in October
    2008 to complete LOMR
  • Floodplain Information Report and LOMR Request
    received in July 2009
  • Submission to FEMA, anticipate 6-9 month
    timeframe until maps are revised (no later than
    April 30, 2010)
  • FEMA has 60 days for completeness
  • 90 day public review and comment period

5
Project History
  • Original Mapping for Stone Creek performed in
    late 70s/early 80s
  • Accuracy issues with regards to the Eagle-Vail
    Subdivision
  • Areas of Elk Lane, Deer Blvd, and other areas
    shown in regulatory floodplain
  • Regulatory floodplain completely outside of Stone
    Creek Golf Club Creek

6
Existing Conditions
48 Structures/108 Owners within regulatory
floodplain
7
Proposed Conditions
65 Structures/121 Owners within Shaded Zone X NOT
A REGULATORY FLOODPLAIN
12 Structures/15 Owners within regulatory
floodplain
8
Summary of Existing and Proposed Conditions
The existing conditions does not have a Shaded
Zone X
9
Community Outreach
  • Project Website
  • Over 80 registered individuals
  • Receive emails when the site is updated
  • Steering Committee Meetings
  • Two meetings held in May 2009
  • Average attendance 10-12

10
Community Outreach (cont.)
  • Public Stakeholder Meeting
  • Over 350 letters mailed to residents adjacent to
    the existing and proposed floodplains
  • Staffed by county, consultant, and FEMA
    representatives
  • Approximately 40 individuals in attendance
  • Project Updates
  • EVPOA on July 6th, 2009
  • EVMD on July 16th, 2009
  • BoCC on July 28th, 2009
  • Future Public Stakeholder Meeting
  • Letters to mailed to relevant properties
  • Date TBD in mid-September, 2009

11
Commissioner Options
  • Approve the Stone Creek Floodplain LOMR without
    conditions, and direct Peter Runyon, Community
    CEO for Eagle County, to sign the LOMR or
  • Approve the Stone Creek Floodplain LOMR with
    conditions, and direct Peter Runyon, Community
    CEO for Eagle County, to sign the LOMR or
  • Deny the Stone Creek Floodplain LOMR or
  • Table the Stone Creek Floodplain LOMR, to fully
    evaluate the request, and give specific direction
    to staff.

12
Next Steps
  • Public Comment
  • County Staff Response
  • Deliberation