Title: NSTX BL2 Upgrade: Management Activities


1
NSTX BL2 Upgrade Management Activities
  • CDR Requirements Outline generated with
    assignments.
  • Job numbers opened for major elements of NBI
    upgrade.
  • Initial Work Planning Forms submitted and
    approved.
  • Some Engineering resources (Cog Engineers
    designers) identified and assigned work,
    including the BL Services and Cryogenics
    Mechanical Engineer from original BL Upgrade.
  • More to go to cover all of the major elements.
  • Comprehensive NBI Upgrade Task List generated.
  • A General Arrangement drawing update of the NSTX
    Test Cell has been requested for use with NBI BL2
    Upgrade requirements.
  • The Head of PPPL Hoisting and Rigging has been
    requested to evaluate best methods for the NBI
    Beamline Relocation effort to move the
    refurbished BL from the NBI Test Cell to the NSTX
    Test Cell and install it on its support stand.
  • Resources and scope identified and costs
    estimated for FY09 effort to arrive at CDR by
    11/09.
  • Design work and Decon effort on track so far for
    CDR in November.

1
NSTX BL 2 Upgrade Status 3/09
2
NSTX BL2 Upgrade Power Systems Controls
  • Power systems from TFTR BL4 A,B, C have been
    chosen for NSTX NBI Upgrade BL2 due to their
    proximity to existing systems and controls
    already in use.
  • Evaluation of the routing of cables and trays has
    begun with some very promising options already
    discovered. (Existing routing though the MER
    looks complicated and expensive so better routes
    are being sought.)
  • Evaluation of the removals of N4 High Voltage
    Enclosures from the TCB has begun. This work will
    be slated for an NSTX outage when active water
    lines can be shut off.
  • Power and Controls Engineering assignments have
    been made and detailed estimates started.
  • Preliminary contacts with vendors of the high
    voltage triax and connectors indicate that these
    components are available for purchase.

2
NSTX BL 2 Upgrade Status 3/09
3
NSTX BL2 Upgrade NBI Decon Activities
  • Initial BL Tritium surveys characterizing BL
    completed. Ongoing surveys will be performed
    periodically to assess progress.
  • Airborne and smearable contamination is
    reasonable and as expected
  • External smears completed to allow work.
  • NBI Test Cell access has been reviewed and
    restricted for Decon effort.
  • Three procedures have been completed for removals
    and pumpout.
  • All three transmission lines have been removed
    and lowered to TCB for storage.
  • Lid Stand engineering sketches have been started
    to fabricate a new stand.
  • Pumpout of the BL to the stack with air vent of
    the beamline to begin air exchanges is imminent
    and may start as soon as next week

3
NSTX BL 2 Upgrade Status 3/09
4
NSTX BL2 Upgrade NBI Decon, cont.
Lid stand holding BL lid with cryo manifolds and
panels (photo circa 1980)
TFTR BL4 area prepared for work
4
NSTX BL 2 Upgrade Status 3/09
5
NSTX BL2 Upgrade NBI Decon, cont.
  • Source platform (lower) decon performed.
  • Transmission line removals completed.
  • Transmission lines stored in TCB for reuse.

5
A. vonHalle
November 10, 2008
6
NSTX BL2 Upgrade Duct/ Pumpduct/ Vacuum Vessel
  • Modeling has begun to lay out BL2, the Beam Duct,
    the TVPS pumpduct appendage, and Bay K Vacuum
    Vessel modifications for wider aiming angles.

6
NSTX BL 2 Upgrade Status 3/09
7
NSTX BL2 Upgrade Summary
  • CDR Requirements effort is in progress.
  • Resources have been assigned with a few more to
    go.
  • Design work has begun.
  • BL Decon work is in progress. Levels are
    reasonable.
  • NBI Upgrade effort on track so far for November
    2009 CDR.

7
NSTX BL 2 Upgrade Status 3/09
Write a Comment