Title: Learning from the Mistakes of Others
1Learning from the Mistakes of Others
American Bar Association Forum on the
Construction Industry
2007 Mid Winter Meeting
- When Design-Build Has Gone Awry
Thomas L. Rosenberg Roetzel Andress
Kerry L. Kester Woods Aitken LLP
Deborah J. Mackay Faegre Benson LLP
2(No Transcript)
3Learning from the Mistakes of Others
American Bar Association Forum on the
Construction Industry
2007 Mid Winter Meeting
- When Design-Build Has Gone Awry
Thomas L. Rosenberg Roetzel Andress
Kerry L. Kester Woods Aitken LLP
Deborah J. Mackay Faegre Benson LLP
4Design-Build Gone Awry
- Overview
- Distill Lessons Learned
- Identify Recurring Themes
- Apply Lessons to Participant Roles
5 I skimped a little on the foundation, But no one
will ever know it
6Design-Build Gone Awry
- Recurring Failure Themes
- Proposal Phase Responsibilities
- Obligate Designers to Meet Performance Specs
- Coordinating Diffused Design
- Schedule Impact of Design
- Integrating Design and Construction
7CASE STUDYOld Dominion Electric v. Ragnar
Benson, Inc.
- Key Facts
- EPC Power Plant
- No EPC Power Plant Experience
- Site plan, permits approvals
- Rock/Site Investigation
- Limited Owner Design Approval
8Old DominionAssembling the Design Build Team
- The Issue
- Procurement Phase Landmines
- Experience / Qualifications
9Old DominionAssembling the Design Build Team
- More Key Facts
- Design Builder Lacks EPC Experience
- Late Engagement of Designer
- Responsibility for Owner-Procured Equipment
10Old DominionAssembling the Design Build Team
- What Went Wrong?
- Compressed Design Phase
- Design Based on Erroneous / Inadequate Info
- Design Schedule Delayed Permitting
- Deficient Design Delayed Project
- Mismanaged Turbine P.A.
11Old DominionCoordinating Diffused Design
- The Issue
- Diffused Design
- Coordination
- Responsibility
12Old DominionCoordinating Diffused Design
- More Key Facts
- Schedule for Pre-Construction Activities
- Rock / Subsurface Information
- Coordination Meetings
- Quality / Quantity of Design Information
13Old DominionCoordinating Diffused Design
- What Went Wrong?
- Late Plan Approval and Permits
- No Meetings with Designer
- Disastrous Field Conditions
- Failed to Recognize Importance of Subsurface Info
- Waste / Redesign
14Old DominionIntegrating Design and Construction
- The Issue
- The Master Builder Concept
- Different Roles and Relationships
- Different Process
15Old DominionIntegrating Design and Construction
- More Key Facts
- 100 Subcontracted by Design Builder
- No Constructability Review / Input
- Failed to Integrate Design and Construction
Schedules - Reduced Supervision / Communication /
Collaboration
16Old DominionIntegrating Design and Construction
- What Went Wrong?
- Complete Lack of Collaboration / Problem Solving
17Lessons from Old Dominion
Issue - Assembling Team
- Problem
- Lack of Design-builder Experience
- Late Design Involvement
- Failure to Manage Key Equipment PA
- Next Time
- Consider Joint Venture with Experienced Partner
- Obtain Design Services Immediately Upon Award (if
not already in place) - Identify/Manage Key PAs
18Lessons from Old Dominion
Issue - Coordinating Design
- Problem
- Late Approvals / Permits
- No Design Meetings
- Subsurface Issues
- Next Time
- Identify Critical Design Input
- Plan and Schedule Design to Support Project
- Identify / Collaborate re Project Critical Info
19Lessons from Old Dominion
Issue - Coordinating Design
- Problem
- Waste Rework / Redesign
- Next Time
- Honest Design Review
- Quality Design Info
- Pertinent Design Info
20Lessons from Old Dominion
Issue - Integrating Design Construction
- Problem
- Disconnect between design construction
- Next Time
- Construction Input
- Constructability Reviews / Collaboration
21CASE STUDYC.L. Maddox, Inc. v. Benham Group, Inc.
- Key Facts
- Design Build Remodel of Power Plant Coal
Processing System - Design Deficiencies
- Bid Errors / Huge Cost Overruns
22Maddox v. BenhamDefining Designers Proposal
Phase Responsibilities
- Issue
- Role Reversals in Design Build
- Historic View of New Partners
- Conceptual Bidding in Fixed Price World
23Maddox v. BenhamDefining Designers Proposal
Phase Responsibilities
- More Key Facts
- Fixed Price Proposal
- Design Builder Subcontracted Engineering and
Material Estimates - No Written Agreement for Proposal Phase Services
24Maddox v. BenhamDefining Designers Proposal
Phase Responsibilities
- What went wrong
- No Agreement Defining Purpose of Engineering
Deliverables - No Risk Allocation for Deficiencies in Estimates
/ Pre-Bid Services - Pre-Bid Engineering Errors Resulted in Overrun
Claims Over 5M
25Maddox v. Benham Coordinating Diffused Design
- Issue
- Fast Track Design Deliverables
- Dispersed Sources of Key Design Information
- Scheduling of Design
- Design to Support Pricing
26Maddox v. Benham Coordinating Diffused Design
- More Key Facts
- Delays in Design Review and Approval
- Late Vendor Drawings
- Lack of Design Experience
- Designer Duty to Support Lump Sum Pricing
27Maddox v. Benham Coordinating Diffused Design
- What Went Wrong
- Late Vendor Information
- Late / Deficient Design
- Inaccurate Quantities / Costs
28Lessons Learned from MaddoxIssue - Designer Role
/ Responsibilities
- Problem
- Responsibility for Pre-Bid Engineering Errors not
Defined
- Next Time
- Formal Agreement with Designer at Proposal Stage
- Include Risk Allocation Mechanism
29Lessons from Maddox
Issue - Coordinating Design
- Problem
- Lack of Design Experience
- Next Time
- Team Qualification and Selection
30Lessons from Maddox
Issue - Coordinating Design
- Problem
- Late Vendor Input
- Next Time
- Recognize Key Design Sources
- Communicate Early
- Plan Design Process
31Lessons from Maddox
Issue - Coordinating Design
- Problem
- Late / Deficient Design
- Next Time
- Define Content of Design Deliverables (Fast
Track) - Schedule Design Deliverables
- Manage Review / Approval Process
32CASE STUDYPlayskool v. Elsa Benson, Inc.
- Key Facts
- Ragnar Benson (RBI) is Design Builder for Two
Story Warehouse - RBI Hires CST to Design, Supply, and Install
Precast Beams and Structural Components - CST Hires Midwest Concrete and Blakeslee to
Design and Manufacture Portions of Work
33Playskool v. Elsa Benson, Inc.
- More Key Facts
- RBI Approves Shop Drawings and Monitors All
Subcontractors - After Occupancy, Separation Between Outside Walls
and Floor - Spalling, Concrete Separates From Beam and Falls
to Floor
34Playskool v. Elsa Benson, Inc.
- Issue
- RBI Attempts to Shift Liability to Its
Subcontractors - Passive Negligence Theory
- RBI Seeks Indemnity from Subcontractors
35Playskool v. Elsa Benson, Inc.
- What Went Wrong?
- RBI was Architect of Record
- Ultimate Responsibility for Design Accuracy
- RBI Had Power and Duty of Approval
- RBI Had Duty to Stop Work and Reject Materials
36Lessons from Playskool
Issue Coordinating Design
- Problem
- Review and Approval Process
- Next Time
- Communicate and Assign Liability
37Lessons from Playskool
Issue Monitoring and Supervision of Construction
- Problem
- Right to Stop Work and/or Reject Materials
- Next Time
- Communicate and Assign Liability
38CASE STUDYIn re Donahue Electric
- Key Facts
- Design Build V.A. Contract
- Scope Fix Existing Building Code Deficiencies
- VA to Provide Bridging to Design Team
- VAs Designer to be on Team
- Change to Competitive Procurement No Team
39Donahue ElectricCoordinating Design - Bridging
- The Issue
- The Bridging Complication
- Impact on Single Point Responsibility
- Impact on Design Coordination
40Donahue ElectricCoordinating Design - Bridging
- More Key Facts
- VA Bars Communication with Key Bridging
Consultant - Bridged Design Based On Larger Project Than
Awarded - Specified Boiler Capacity
- Omitted Bridging Consultant Design Assumptions
- VA Said Drawings are For Info Only
41Donahue ElectricCoordinating Design - Bridging
- What Went Wrong?
- No Access to Bridging Consultants Key Info
- Defective Design
- Owner Design Liability
42Lessons from Donahue
Issue Coordinating Bridged Design
- Problem
- No Access to Key Design Information
- Next Time
- Evaluate Bridging Info
- Provide the Supporting Info
43Lessons from Donahue
Issue Coordinating Bridged Design
- Problem
- Defective Bridged Specs
- No Communication on Pricing
- Next Time
- Design Review
- Owner Must Provide Basic Project Parameters and
Assumptions
44Lessons from Donahue
Issue Coordinating Bridged Design
- Problem
- Owner Design Liability
- Next Time
- Single Point Responsibility?
45(No Transcript)
46American Bar Association Forum on the
Construction Industry
2007 Mid Winter Meeting
Break