Learning from the Mistakes of Others - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

Learning from the Mistakes of Others

Description:

Old Dominion Electric v. Ragnar Benson, Inc. Key Facts. EPC Power Plant ... RBI Had Power and Duty of Approval. RBI Had Duty to Stop Work and Reject Materials ... – PowerPoint PPT presentation

Number of Views:51
Avg rating:3.0/5.0
Slides: 47
Provided by: edjo9
Category:

less

Transcript and Presenter's Notes

Title: Learning from the Mistakes of Others


1
Learning from the Mistakes of Others
American Bar Association Forum on the
Construction Industry
2007 Mid Winter Meeting
  • When Design-Build Has Gone Awry

Thomas L. Rosenberg Roetzel Andress
Kerry L. Kester Woods Aitken LLP
Deborah J. Mackay Faegre Benson LLP
2
(No Transcript)
3
Learning from the Mistakes of Others
American Bar Association Forum on the
Construction Industry
2007 Mid Winter Meeting
  • When Design-Build Has Gone Awry

Thomas L. Rosenberg Roetzel Andress
Kerry L. Kester Woods Aitken LLP
Deborah J. Mackay Faegre Benson LLP
4
Design-Build Gone Awry
  • Overview
  • Distill Lessons Learned
  • Identify Recurring Themes
  • Apply Lessons to Participant Roles

5

I skimped a little on the foundation, But no one
will ever know it
6
Design-Build Gone Awry
  • Recurring Failure Themes
  • Proposal Phase Responsibilities
  • Obligate Designers to Meet Performance Specs
  • Coordinating Diffused Design
  • Schedule Impact of Design
  • Integrating Design and Construction

7
CASE STUDYOld Dominion Electric v. Ragnar
Benson, Inc.
  • Key Facts
  • EPC Power Plant
  • No EPC Power Plant Experience
  • Site plan, permits approvals
  • Rock/Site Investigation
  • Limited Owner Design Approval

8
Old DominionAssembling the Design Build Team
  • The Issue
  • Procurement Phase Landmines
  • Experience / Qualifications

9
Old DominionAssembling the Design Build Team
  • More Key Facts
  • Design Builder Lacks EPC Experience
  • Late Engagement of Designer
  • Responsibility for Owner-Procured Equipment

10
Old DominionAssembling the Design Build Team
  • What Went Wrong?
  • Compressed Design Phase
  • Design Based on Erroneous / Inadequate Info
  • Design Schedule Delayed Permitting
  • Deficient Design Delayed Project
  • Mismanaged Turbine P.A.

11
Old DominionCoordinating Diffused Design
  • The Issue
  • Diffused Design
  • Coordination
  • Responsibility

12
Old DominionCoordinating Diffused Design
  • More Key Facts
  • Schedule for Pre-Construction Activities
  • Rock / Subsurface Information
  • Coordination Meetings
  • Quality / Quantity of Design Information

13
Old DominionCoordinating Diffused Design
  • What Went Wrong?
  • Late Plan Approval and Permits
  • No Meetings with Designer
  • Disastrous Field Conditions
  • Failed to Recognize Importance of Subsurface Info
  • Waste / Redesign

14
Old DominionIntegrating Design and Construction
  • The Issue
  • The Master Builder Concept
  • Different Roles and Relationships
  • Different Process

15
Old DominionIntegrating Design and Construction
  • More Key Facts
  • 100 Subcontracted by Design Builder
  • No Constructability Review / Input
  • Failed to Integrate Design and Construction
    Schedules
  • Reduced Supervision / Communication /
    Collaboration

16
Old DominionIntegrating Design and Construction
  • What Went Wrong?
  • Complete Lack of Collaboration / Problem Solving

17
Lessons from Old Dominion
Issue - Assembling Team
  • Problem
  • Lack of Design-builder Experience
  • Late Design Involvement
  • Failure to Manage Key Equipment PA
  • Next Time
  • Consider Joint Venture with Experienced Partner
  • Obtain Design Services Immediately Upon Award (if
    not already in place)
  • Identify/Manage Key PAs

18
Lessons from Old Dominion
Issue - Coordinating Design
  • Problem
  • Late Approvals / Permits
  • No Design Meetings
  • Subsurface Issues
  • Next Time
  • Identify Critical Design Input
  • Plan and Schedule Design to Support Project
  • Identify / Collaborate re Project Critical Info

19
Lessons from Old Dominion
Issue - Coordinating Design
  • Problem
  • Waste Rework / Redesign
  • Next Time
  • Honest Design Review
  • Quality Design Info
  • Pertinent Design Info

20
Lessons from Old Dominion
Issue - Integrating Design Construction
  • Problem
  • Disconnect between design construction
  • Next Time
  • Construction Input
  • Constructability Reviews / Collaboration

21
CASE STUDYC.L. Maddox, Inc. v. Benham Group, Inc.
  • Key Facts
  • Design Build Remodel of Power Plant Coal
    Processing System
  • Design Deficiencies
  • Bid Errors / Huge Cost Overruns

22
Maddox v. BenhamDefining Designers Proposal
Phase Responsibilities
  • Issue
  • Role Reversals in Design Build
  • Historic View of New Partners
  • Conceptual Bidding in Fixed Price World

23
Maddox v. BenhamDefining Designers Proposal
Phase Responsibilities
  • More Key Facts
  • Fixed Price Proposal
  • Design Builder Subcontracted Engineering and
    Material Estimates
  • No Written Agreement for Proposal Phase Services

24
Maddox v. BenhamDefining Designers Proposal
Phase Responsibilities
  • What went wrong
  • No Agreement Defining Purpose of Engineering
    Deliverables
  • No Risk Allocation for Deficiencies in Estimates
    / Pre-Bid Services
  • Pre-Bid Engineering Errors Resulted in Overrun
    Claims Over 5M

25
Maddox v. Benham Coordinating Diffused Design
  • Issue
  • Fast Track Design Deliverables
  • Dispersed Sources of Key Design Information
  • Scheduling of Design
  • Design to Support Pricing

26
Maddox v. Benham Coordinating Diffused Design
  • More Key Facts
  • Delays in Design Review and Approval
  • Late Vendor Drawings
  • Lack of Design Experience
  • Designer Duty to Support Lump Sum Pricing

27
Maddox v. Benham Coordinating Diffused Design
  • What Went Wrong
  • Late Vendor Information
  • Late / Deficient Design
  • Inaccurate Quantities / Costs

28
Lessons Learned from MaddoxIssue - Designer Role
/ Responsibilities
  • Problem
  • Responsibility for Pre-Bid Engineering Errors not
    Defined
  • Next Time
  • Formal Agreement with Designer at Proposal Stage
  • Include Risk Allocation Mechanism

29
Lessons from Maddox
Issue - Coordinating Design
  • Problem
  • Lack of Design Experience
  • Next Time
  • Team Qualification and Selection

30
Lessons from Maddox
Issue - Coordinating Design
  • Problem
  • Late Vendor Input
  • Next Time
  • Recognize Key Design Sources
  • Communicate Early
  • Plan Design Process

31
Lessons from Maddox
Issue - Coordinating Design
  • Problem
  • Late / Deficient Design
  • Next Time
  • Define Content of Design Deliverables (Fast
    Track)
  • Schedule Design Deliverables
  • Manage Review / Approval Process

32
CASE STUDYPlayskool v. Elsa Benson, Inc.
  • Key Facts
  • Ragnar Benson (RBI) is Design Builder for Two
    Story Warehouse
  • RBI Hires CST to Design, Supply, and Install
    Precast Beams and Structural Components
  • CST Hires Midwest Concrete and Blakeslee to
    Design and Manufacture Portions of Work

33
Playskool v. Elsa Benson, Inc.
  • More Key Facts
  • RBI Approves Shop Drawings and Monitors All
    Subcontractors
  • After Occupancy, Separation Between Outside Walls
    and Floor
  • Spalling, Concrete Separates From Beam and Falls
    to Floor

34
Playskool v. Elsa Benson, Inc.
  • Issue
  • RBI Attempts to Shift Liability to Its
    Subcontractors
  • Passive Negligence Theory
  • RBI Seeks Indemnity from Subcontractors

35
Playskool v. Elsa Benson, Inc.
  • What Went Wrong?
  • RBI was Architect of Record
  • Ultimate Responsibility for Design Accuracy
  • RBI Had Power and Duty of Approval
  • RBI Had Duty to Stop Work and Reject Materials

36
Lessons from Playskool
Issue Coordinating Design
  • Problem
  • Review and Approval Process
  • Next Time
  • Communicate and Assign Liability

37
Lessons from Playskool
Issue Monitoring and Supervision of Construction
  • Problem
  • Right to Stop Work and/or Reject Materials
  • Next Time
  • Communicate and Assign Liability

38
CASE STUDYIn re Donahue Electric
  • Key Facts
  • Design Build V.A. Contract
  • Scope Fix Existing Building Code Deficiencies
  • VA to Provide Bridging to Design Team
  • VAs Designer to be on Team
  • Change to Competitive Procurement No Team

39
Donahue ElectricCoordinating Design - Bridging
  • The Issue
  • The Bridging Complication
  • Impact on Single Point Responsibility
  • Impact on Design Coordination

40
Donahue ElectricCoordinating Design - Bridging
  • More Key Facts
  • VA Bars Communication with Key Bridging
    Consultant
  • Bridged Design Based On Larger Project Than
    Awarded
  • Specified Boiler Capacity
  • Omitted Bridging Consultant Design Assumptions
  • VA Said Drawings are For Info Only

41
Donahue ElectricCoordinating Design - Bridging
  • What Went Wrong?
  • No Access to Bridging Consultants Key Info
  • Defective Design
  • Owner Design Liability

42
Lessons from Donahue
Issue Coordinating Bridged Design
  • Problem
  • No Access to Key Design Information
  • Next Time
  • Evaluate Bridging Info
  • Provide the Supporting Info

43
Lessons from Donahue
Issue Coordinating Bridged Design
  • Problem
  • Defective Bridged Specs
  • No Communication on Pricing
  • Next Time
  • Design Review
  • Owner Must Provide Basic Project Parameters and
    Assumptions

44
Lessons from Donahue
Issue Coordinating Bridged Design
  • Problem
  • Owner Design Liability
  • Next Time
  • Single Point Responsibility?

45
(No Transcript)
46