Title: By: Mike Muchard, P'E'
1Drilled Shaft Quality Assurance Testing
- By Mike Muchard, P.E.
- Applied Foundation Testing, Inc.
AFT
2Drilled Shaft Quality Assurance Test Methods
- Before
- Good Construction / Inspection Practice
- After
- Crosshole Sonic Logging (CSL)
- Singlehole Sonic Logging (SSL)
- Crosshole Tomography
- Sonic Echo (SE)
- Gamma-Gamma
3QA Methods During Construction
4Drilled Shaft Quality Assurance
- Most Common Construction
- Wet Method
- Temp Casing Method
- Slurry Management
- Mineral Attapulgite and Bentonite
- Slurry Testing Density, Viscosity, PH, Sand
- Bottom Cleanliness
- Tremie
- On bottom
- No Breach
- 12 hour Time lime open excavation
- Concrete slump min 4 - 7 to 9 Best
5ShaftInspectionDevice(SID)
6Passing Criteria
- 1 over the Base for Misc. Drilled Shafts
7Calibrate Feel of Weighted Tape
8Use Submersible Pump andFlat Bottom Cleanout
BucketTo Get Better Cleanliness
9(No Transcript)
10Post ConstructionMethods
11Crosshole Sonic Logging (CSL)And Derivatives
12(No Transcript)
13CSL Tubes
14CSL Tube Prep
- Steel Tubes Preferred over PVC for CSL
- PVC De-bonds Quicker
- Tubes Mounted on Inside of Cage
- Typically 1 Tube per Foot of Diameter
- Tubes Capped at Top and Bottom
- Filled With Water Before Pouring Concrete
15Good CSL Result
16Concrete Velocity Based Criteria
17Crosshole Sonic Logging Case History
Slightly Delayed Arrival Time
18Tomography to Better Define a Low Velocity Zone
19Crosshole Sonic Logging Case History
Major Loss Of Signal
20Soft Toe CSL Remedial Grouting Shaft Toe
21Crosshole Sonic Logging Case History
- PVC Tube De-Bonding - 2 day, 4 day and 11 day
Tests
22CSL Limitations
- Can Only Evaluate Inside of Cage
- Dependent on Bonding Condition of Tubes
- Dependent on Engineering Interpretation
23Gamma- Gamma Logging
24Sonic Echo / Impulse Response
25Good Result
26Shows Enlarged Bulge Near Toe (Still Good)
27Pulse Echo Limitations
- Can Be Inconclusive.
- Unable to Detect Flaws Smaller Than 25 of Cross
Section - Not Able to Detect Soft Bottom
- Heavily Dependent on Test Operator
28Good Construction Practice is Solution Thank
You