Title: Carbon Dioxide Flooding in Wyoming Reservoirs
1Carbon Dioxide Flooding in Wyoming Reservoirs
- Brian F. Towler
- Enhanced Oil Recovery Institute
2(No Transcript)
3Minimum Miscibility Pressure
4Minimum Miscibility Pressure in Hall-Gurney LKC
Tertiary Oil Recovery Project
5Overall Objective
- Verify technical and economic viability of the
application of CO2 miscible flooding to Wyoming
fields - Critical element Demonstrate sufficient field
performance(oil in the tank) to justify the
development of a carbon dioxide pipeline into
Central Powder River Basin
6Lease Scale Economic Variables-CO2 Flooding
CO2 cost 1/mcf Oil price 20/bbl Capital
cost 4,000,000/sec CO2 utilization 5/10
mcf/bbl (net/gross) Recovery 30 Primary
Secondary Operations 400-600M/yr/sec NRI
84
Kansas Geological Survey
7CO2 Costs vs. Oil Price for 20 IRR
Base Case 20/bbl Oil 1.00/mcf CO2 12 OOIP
Kansas Geological Survey
8Sensitivity to Oil Price
Base Case 20/bbl Oil 1.00/mcf CO2 12 OOIP
Kansas Geological Survey
9Required Recovery for 20 IRR
20 Oil Recovery Required 2,500 gross
BO/acre Recovery Factor Resource Threshold 30
PS 8,500 BO/acre 25 PS 10,200 BO/acre 25
Oil Recovery Required 1,650 gross
BO/acre Recovery Factor Resource Threshold 30
PS 5,500 BO/acre 25 PS 6,600 BO/acre
Kansas Geological Survey
10Project Economics
- Total Project 5.4 million
- 2.0M CO2 Purchase, transport, recycling
- 1.5M Research, Technology Transfer
- 1.1M Capital Costs (wells, etc.)
- 0.8M Operations (6 years)
- Funding
- 2.4M Kinder-Morgan CO2 Co. LP and Murfin
Drilling Company - 1.9M U.S. Department of Energy
- 1.0M KGS and TORP
- 0.1M Kansas Department of Commerce
11Demonstration Design Summary
- 55 acre, nine-spot
- 2 CO2 injectors
- 7 Producers
- 5 Containment Water Injectors
- 0.843 BCF CO2 injected-WAG
- 4.6 year operating life
- gt80,000 BO estimated recovery during DOE
- gt20,000 BO in 3 years after DOE Project
12Pipeline Cost Estimates
- Distance is 220 miles to Hall-Gurney
- Other LKC areas would require 110 miles of
lateral lines - Pipeline cost is 22,000/inch-mile
- Ten year amortization of capital cost at 10
based on 80 of line capacity
William Flanders, Transpetco Engineering
13Pipeline Considerations
- CO2 oil recovered is 25 of Primary and
Secondary, usually it is higher than this - Net CO2 required is 4 mcf/BO
14William Flanders
15(No Transcript)
16Tertiary Flood (CO2 Injection)
- Used residual oil saturation distribution at end
of secondary - Used Compositional Model to simulate performance
- Developed PVT behavior of reservoir oil
- Simulated performance with injection wells in
different pattern locations
17Injection Sequence
- 2-4 months of pressure buildup
- 2 month Water-Alternating-Gas (WAG) injection
cycle - 3 years of WAG
- 2 years of post-CO2 waterflood
18Summary of Model Performance
Model T22 Model T18
Model T20 CO2 Injection wells NEWCO2N
NEWCO2N NEWCO2S
Colliver 18 NEWCO2S
Colliver 18 Cumulative Injection Total
CO2, MMSCF 599.5 763.57
606.91 Cumulative Production Oil, MSTB
77 70
62 CO2 end year 3, MMSCF 143 310
267 CO2 end year 5, MMSCF 317
493 422 Recovery ( OOIP)
7.56 6.87 6.08 Utilization
Factors Gross (MMSCF/STB) 7.8
10.9 9.8 Net (MMSCF/STB)
5.9 6.5 5.5
19(No Transcript)
20(No Transcript)
21Assessment of Hartzog Draw Field
- Hartzog Draw is located in the central Powder
River Basin - 40 miles NNE of Salt Creek field.
- Discovered in 1975
- Produces from the Shannon sandstone at depths
between 9000-10000 feet. - 350 MMSTB of oil initially in place
- initial pressure of 5000 psia.
22(No Transcript)
23- The maximum primary production was in March 1978
at 35,194 STB/day. - A water flood pilot began in 1981 shortly before
the reservoir pressure had dropped to 1000 psia
and primary production had fallen to 6182 STB/day
(in July 1982). - The waterflood response commenced in September
1983 and production peaked again in March 1987 at
18,973 STB/day.
24- Infill drilling and polymer injection from 1996
to 1999 temporarily arrested the decline but by
March 2004 the production had again declined to
3616 STB/day with a water-oil ratio of 0.692
BW/BO.
25- As of June 2004 there are 211 producers and 143
injectors completed in an approximate forty acre
line drive pattern. - To March 2004 108,212,683 STB of oil has been
produced representing about 31 of the original
oil in place. - Decline curve analysis indicates that at the
field abandonment rate of 500 STB/day the
ultimate primary and secondary recovery will be
126.7 MMSTB representing a recovery factor of
36.2.
26- Using decline curve analysis 36.0 MMSTB (10.3)
are primary reserves and 90.7 MMSTB (25.9) are
secondary reserves. - This leaves 213.3 MMSTB still in place to be
recovered and, of this, it is estimated that
50-100 MMSTB can be recovered by CO2 flooding. - Screening indicates that this field is well
suited to CO2 flooding. Its depth, oil gravity,
and response to waterflood are all conducive to a
positive carbon dioxide flood. - At this time there are 212 producers and 143
injectors as well as 28 dormant wells in the
field.
27- There are numerous cretaceous fields that would
be similar candidates for CO2 flooding - There are also numerous Minnelusa fields that
would also be good candidates
28- Fields need to be assessed using lab MMP data and
simulation - Full field compositional simulation studies need
to be carried out - Preliminary assessment can also be done with
simple models such as the DOEs CO2 Prophet