Title: Caltrans%20Bridge%20Construction%20Forum%202007


1
Caltrans Bridge Construction Forum2007
  • Structure Economics
  • Rich Hebert, C.C. Myers, Inc. Ken Bocchicchio,
    Caltrans
  • So. Cal. Chief Engineer Area Construction
    Manager

2
GENERAL THEME
  • Does the timeliness of payments significantly
    affect the cost of doing business with Caltrans?

3
TRUCTURE ECONOMIC
  • Estimates
  • Cash Flow
  • Partial Payments
  • CCOS

4
TRUCTURE ECONOMIC
  • Problems/Challenges/Complaints
  • Changes you would like to see.
  • Processes that work well.
  • What can be automated?

5
TRUCTURE ECONOMIC
  • Estimates
  • Have you experienced?
  • Pay items missed?
  • Lump sum change orders missed?
  • Supplemental estimates too much time and effort?
  • Payment withheld for QC issues in excess of fair
    value?

6
TRUCTURE ECONOMIC
  • Estimates
  • Suggestions?
  • Establish automated monthly pay request similar
    to EWB?
  • More Final Pay Qs vs. Field Measured Qs?

7
TRUCTURE ECONOMIC
  • Cash Flow
  • Are these significant?
  • Job delay or suspension?
  • Length of PFE process?
  • DRB decisions with CT rejection results in no
    payment until completion of claim process.

8
TRUCTURE ECONOMIC
  • Partial Payments
  • How can MOH process be simplified?
  • Falsework and shoring partial payments or
    schedule of values desired?
  • What other materials should be included?
  • Details of monthly partial payments shown on
    estimate?
  • State is owner of materials on hand

9
TRUCTURE ECONOMIC
  • CCOS
  • Have you struggled with?
  • Recognition of changed conditions or work
  • Negotiation methods- Lack of knowledge regarding
    rules of entitlement/engagement
  • Entitlement first, dollars second
  • Electronic EWB processing working?
  • Signing tentative work agreements.

10
TRUCTURE ECONOMIC
  • Other current Caltrans business practices, which
    if changed, would
  • lower the cost of doing Caltrans work?
  • Result in lower bid prices?
  • Result in less risk?

11
Discussion?
  • Estimates
  • Cash Flow
  • Partial Payments
  • CCOS

12