Transcript and Presenter's Notes

Title: RADIOACTIVE ION BEAMS AT


1
RADIOACTIVE ION BEAMS AT
B.RANNOU W.MITTIG M.G.ST LAURENT (GANIL France)
2
plan
  • The GANIL and SPIRAL I RIBs facility
  • safety and radiation protection
  • 2. The LINAG project

3
GANIL
  • Stable beams
  • from C to U
  • Maximum energy 95 AMeV
  • Intensity 2.1013 pps (6 kW)
  • RIB production
  • in-flight method SISSI and LISE
  • ISOL method SPIRAL I (SIRa)

4
SPIRAL I
  • Primary beams
  • From C 95 AMeV to Kr 68 AMeV
  • Power max 6 kW (1.5 kW)
  • Target C
  • ECR ion source
  • 15 days of irradiation
  • Secondary beams
  • No restriction in mass
  • Emax 25 AMeV

5
SPIRAL I cave
6
SPIRAL I target source
7
Activation and Dose rate calculation (EPAX)
8
Dose rate measurement
calculation
Calculation measure
9
Cooling water activation
  • Dose rate 25 µSv/h at 30 cm during operation (13C
    75 AMeV 1.5kW)
  • After one year 45 kBq/l

10
Radioactive release
  • Normal conditions
  • Air activation by neutrons (radioactive gases
    short life)
  • Storage of gases from vacum system
  • Accidents
  • ? Air Ventilation system with high efficiency
    filtre
  • Impact of the SPIRAL facility 0.06 µSv/year

11
Airborne activation
neutron
Air activity
A max 4.107 Bq/m3 (gaz) and 60 Bq/m3 (aerosol)
for 1.5 kW 13C 75 AMeV beam After beam shut
traces (1 Bq/cm2)
12
LINAG project
13
Goals
  • Production of RIBs from fission products using
    ISOL method
  • Deuterons beam 40 MeV, 5 mA (200 kW)
  • C converter for neutron production
  • UCx production target gt 1013 fissions/s
  • Irradiation time 3 months

14
Converter and Target activation
  • Calculations performed with LAHET MCNP CINDER
    code
  • Total activity
  • Activity by radioactivity (?, ? and ?) and
    species (gases, )
  • Dose rate
  • During irradiation and after decay time

15
Converter and target calculation
U Target density 2.3 g/cm3 11 g/cm3
Total activity (Bq) 6.77 1013 3.64 1014
Total activity (Bq) after 1 year 1.44 1011 6.88 1011
? activity (Bq) 7.10 106 4.28 107
Tritium activity (Bq) 4.28 106 3.76 108
? Dose rate (µSv/h at 1 m) 6.83 106 3.20 107
? Dose rate (µSv/h at 1 m) after 1 year 6.76 103 3.39 104
16
Converter Plug
17
Containment of volatile radioactivity
18
Gases production
  • Noble gases and elements with T boiling gt 2000C
  • Define decay time for the releast

Time after beam shut (month) 0 1 12
Activity gases (Bq) 2.51 1013 6.9 1010 2.8 1010
19
Neutron production
20
General siting