Title: Case Study: Impact of Above Ground
1Case Study Impact of Above Ground Spent Fuel
Storage on Nearby Meteorological Systems
NUMUG Meeting Charlotte, NC June 2008
Jim Holian SAIC
2 Study
Evaluate the proposed Independent Spent Fuel
Storage Facility Installation (ISFSI) on the
meteorological monitoring system at the Cooper
Nuclear Station, Brownville, Nebraska
3 Background
- Spent fuel pool near capacity
- Four potential ISFSI sites identified
- Numerous configurations examined
- Three sites eliminated after soils study
- Site selected is closest to Met Tower
- SAIC task with determining any potential impact
4(No Transcript)
5(No Transcript)
6(No Transcript)
7(No Transcript)
8(No Transcript)
9(No Transcript)
10ISFSI Facility
- 450-feet northeast of the Met Tower
- Concrete base elevated 10-feet
- 46 Horizontal Storage Modules (HSMs)
- Each HSM 10W X 20L X 18H
- Overall size is 40W X 260L
- 511sq-ft Storage Building south end
11- Impacts on Meteorological Data
12Meteorological Data Used in Analyses
- Five years of onsite data (2001-2005)
- 97 data availability
- Annual Wind Roses
- Joint Frequency Distributions (JFDs) for
stability classification
13(No Transcript)
14ISFSI Structure Impacts
- HSMs extend up to 28 feet above met tower base
- Distance to tower is approximately 450 feet
- Distance to height ratio of 161
- Structure impacts felt with wind direction from
045-080 degrees (NE-ENE) - Frequency is only 5.3 (5-year average)
15ISFSI Thermal Impacts
- NUHOMS TN-61BT HSMs to be installed
- By design, HSMs dissipate heat by natural
conduction - Air enters two openings at base, circulates, and
vents out the top
16Two Specific Scenarios Studied
- (1) 46 HSMs with maximum heat load of 18.3
kilowatts (kW) - (2) 8 HSMs loaded first two years only
- Vary heat load from 18.3 kW to 9 kW
- Vary wind speeds from 1.0 m/s to 4 m/s
- Vary stability
175-Year Stability at CNS
18Thermal Plume
- G stability truncated cone volume and cross
sectional area at met tower is 2,061,044 ft3 and
8,500 ft2 respectively. (no ground reflection) - D stability truncated cone volume and cross
sectional area at met tower is 11,392,137 ft3 and
46,700 ft2 respectively (with ground reflection)
19Assumptions
- HSM air temperature is linear to heat load (based
on 51F rise at 24 kW load in NUHOMS ISFSI
UFSAR) - No conduction loss to ground around ISFSI
- No plume meander or mixing at edges (entrainment)
20Results
21Estimated Met Tower ?T (F) 46 HSM Casks Loaded
G Stability
HSM Heat kW Wind Speed (m/s) Wind Speed (m/s) Wind Speed (m/s) Wind Speed (m/s)
1 2 3 4
18.3 1.70 0.90 0.57 0.45
15 1.40 0.74 0.47 0.37
12 1.10 0.55 0.37 0.28
9 0.83 0.41 0.28 0.21
22Estimated Met Tower ?T (F) 46 HSM Casks Loaded
D Stability
HSM Heat kW Wind Speed (m/s) Wind Speed (m/s) Wind Speed (m/s) Wind Speed (m/s)
1 2 3 4
18.3 0.31 0.16 0.10 0.08
15 0.25 0.13 0.08 0.07
12 0.20 0.10 0.07 0.05
9 0.15 0.07 0.05 0.04
23Estimated Met Tower ?T (F) 8 HSM Casks Loaded
G Stability
HSM Heat kW Wind Speed (m/s) Wind Speed (m/s) Wind Speed (m/s) Wind Speed (m/s)
1 2 3 4
18.3 1.30 0.70 0.43 0.34
15 1.10 0.56 0.36 0.28
12 0.80 0.42 0.28 0.21
9 0.63 0.31 0.21 0.16
24Estimated Met Tower ?T (F) 8 HSM Casks Loaded
D Stability
HSM Heat kW Wind Speed (m/s) Wind Speed (m/s) Wind Speed (m/s) Wind Speed (m/s)
1 2 3 4
18.3 0.12 0.06 0.04 0.03
15 0.10 0.05 0.03 0.03
12 0.08 0.04 0.03 0.02
9 0.06 0.03 0.02 0.01
25Frequency of Occurrence of NE through ENE Sector
Wind
- G Stability - 0.5 with average wind speed of
2.0 m/s - D Stability 2.3 with average wind speed of 2.9
m/s - All Stabilities 5.3 with average wind speed of
2.7 m/s
26Impacts
- Minimal over 95 of the time
- Separate study at CNS demonstrated that raising
the 10-meter temperature 0.4 F changed the peak
predicted downwind radiological doses by 90
(worst case)
27Mitigation Options
- Move ISFSI site? no other acceptable location
- Move met tower? not practicable
- Erect new met tower in an acceptable location
that preserves the long term meteorological data
record - Risk acceptable, do nothing
28CNS Decision
- Erect a new 100-meter tower
- Select an area that best reflects the original
existing tower location - Take into account current and future expansion of
the plant - Preserve the long term data record
29(No Transcript)
30(No Transcript)
31(No Transcript)
32New 100-meter Tower
- New 100-meter tower will be nearly identical to
existing tower and equipment - Dual elevator system with sonic sensors
- Construction to begin 8/1/08
- 6 month comparison of data with existing
100-meter tower to begin 9/15/08 - New tower to be declared operational by 4/1/09
33Then came the floods of 2008!
34(No Transcript)
35(No Transcript)
36(No Transcript)
37Questions?