Title: Slug Handling System on NQ Platform A Case Study for CSeries Pipeline Offshore Engineering Services
1Slug Handling System on NQ Platform - A Case
Study for C-Series Pipeline Offshore
Engineering ServicesONGC Ltd.Mumbai
2Back Ground
- C - Series fields lie 60 km. West of Daman.
- Comprises of mainly Gas bearing structures
viz. C-39-8, C-39-6, C-39-1, C-26, C-24, C-23,
C-22, B-12-7 and B-12-1. - Water depth variation 19m-30m.
- Each structure has limited production capacity
- Short production life.
3Facilities to be created
- The Scheme shall be completed in three phases
- Total Unmanned Well Platforms 8 Nos.
- Phase I - 4 ( C-22, C-24, C-39-1 C-39-A)
- Phase I (except pipelines) commissioned in April
2009 - Phase II (5th Year) - 2 ( C-23 B-12-7 )
- Phase III (11th Year) - 2 ( C-26 B-12-1 )
4Pipeline network for C-Series
C-39-A
C-39-1
Phase-I
8X 2.5 km
22 X 60 km C-39-A to C-24
Phase-II
C-23
Phase-III
8 X 3 km
C-22
C-24
8 X 2.5 km
8 X 2 km
C-26
B-12-1
C-24 to NQG 28 X 115 km
8 X 3 km
8 X 2 km
B-12-7
Existing
NQG
Proposed
Uran
5Production Scenario(Peak Rate)
- Gas, MMSCMD Condensate, M3/HR
- Phase I - 3.20
28.33 -
- Phase II (5th year) - 3.58
67.00
6Brief Description of the Pipeline System
- C-Series pipeline is 175 km. long having diameter
of 22 28 - The pipeline starts from C-39-A and runs upto
C-24 with a diameter of 22 and distance of 60
Km. The line further starts from C-24 and ends at
NQG with a diameter of 28 and distance of 115
Km. - Seabed on the pipeline route slopes down
gradually from 20 m at C-series end to 60 m at
NQG end - The pipeline has been designed to transport 3.58
MMSCMD gas and 67 m3/hr condensate from the
marginal fields to NQ process complex.
7 Bathemetry of Pipeline route
8Slug Flow
- What is slug flow ?
- Slug flow is a two-phase flow pattern which is
characterized by a sequence of packs of liquid
separated by long gas bubbles flowing over a
liquid film inside the pipe and is normally
associated with high pressure-drops. - How slug is formed ?
- Slug formation is a phenomenon which is normally
observed in long distance pipelines having uneven
terrain (called terrain sluging) and/ or pipeline
id much higher than that required for normal
through-put (called hydrodynamic slugging) - Implications of slug flow on receiving facilities
- Unless sized appropriately, the slug flow may
cause operational imbalance and even cause
production loss or facilities shut down
9Study Description
- A dynamic simulation of the pipeline was carried
out through Scand Power Technology, Dubai using
their Olga Software to ascertain the possibility
of slugging of the pipeline under various
operating scenario. - The objective of the study were to determine the
slugging of the pipeline under various operating
scenario like reduced flow, shut down, re-start
and production ramp-up. -
-
10Simulation Scenarios
- In order to optimise the number of simulations,
following typical cases were simulated using Olga
software. - Constant production rates Considering 25, 50,
75 and 100 of maximum production rates for
Phase-I Phase-II. - Turn down Simulation Reducing the production
rates under Phase-II from 100 to 75, 75 to
50, 50 to 25 - Shut-in Simulation Shutting down the Production
under Phase-II of each source simultaneously from
25 to non flowing condition. - Re-start Simulation Restarting the production
from non-flowing condition to 25 and non-flowing
condition to 100. - Ramp-up Simulation Increasing the production
from 25 to 50, 50 to 75, 75 to 100 and 25
to 100. -
-
11Result of various scenarios simulated
- CONSTANT PRODUCTION RATES
- 1) It is observed that higher the production
rate, lower is the liquid content in the
pipeline. - Mild terrain slugging was observed at upstream
ends i.e. well heads, for 25 production rate
for both, Phase-I and Phase-II. Maximum liquid
content observed in the pipeline ( 2764 m3 in
Phase-I and 3295 m3 in Ph-II). - No slugging was observed at the downstream end at
NQG and fluid arrival rate at NQG was found to be
well within the handling capacity of NQG topside
facilities. - 4) Slug flow resulted in well head pressure
fluctuations of approx. 1 bar. The slug frequency
was approx. 1 slug per day for Phase-I and 2.8
slugs per day for Phase-II. - Contd.
-
-
12 Result of various scenarios simulated (contd.)
- TURN DOWN SIMULATION
- It is observed that higher the turndown, higher
is the time for liquid content to get stabilized. - 265 hrs. (11 days) are required for liquid
content to get stabilized in 28 C-24-NQG
pipeline when production rate is reduced from
100 to 25. Whereas stabilization takes around
70 hrs. (3 days) when production rate is reduced
from 100 to 75. - No slugging was observed during the stabilization
period for any turndown case. -
-
13 Result of various scenarios simulated (contd.)
- SHUT IN SIMULATION
- It is observed that after the wellheads were
shut-in for 11.5 hrs, the riser base towards NQG
was completely filled up with liquid due to down
slope geometry of the pipeline towards NQG. - After 24 hours shut-in, the liquids had
completely filled section from KP 110.63 to riser
base having pipe volume 175 m3. Moreover, the
pipe from KP 108.85 to KP 110.63 was partially
filled accounted for 273 m3 liquid from KP 108.85
to the riser base. - The liquid accumulation towards riser base at NQG
gives rise to slug upon restart. It was also
observed that higher the period of shutdown,
higher is the volume of slug upon restart. -
-
14 Result of various scenarios simulated (contd.)
- RESTART SIMULATION
- 1) Both 100 and 25 restart resulted in slug
flow and were beyond the NQG handling capacity.
Reduced restart flow rate does not have much
impact except prolonging the arrival rate of
slug. - 2) Liquid slug was also followed by gas surge of
magnitude much higher than the design capacity of
the topside facilities. - 3) For restart to 100 production case, the
liquid rate surged to a peak value after 3 hours
had passed since flow was resumed. The total
liquid surge volume in excess of handling
capacity (100 m3/hr) was 269 m3 and the
processing time required was 3 hrs. A gas surge
of magnitude 16 MMSCMD (for a short duration)
followed by liquid slug of 12758 m3/hr (for a
short duration) was also observed. Subsequent
surges were found to be within the handling
capacity. - Contd.
15 Result of various scenarios simulated (contd.)
- RESTART SIMULATION
- For restart to 25 production case, the liquid
rate surged to a peak value after 9.3 hours had
passed since flow was resumed. The total liquid
surge volume in excess of handling capacity (100
m3/hr) was 286 m3 and the processing time
required was 3.5 hrs. A gas surge of magnitude 11
MMSCMD (for a short duration). followed by liquid
slug of 16688 m3/hr (for a short duration) was
also observed. A subsequent gas surge of equal
magnitude was observed at10th hour. - It is also observed that any shutdown greater
than 1 hour will produce slug on restart.
However, additional restart simulation is
required to quantify the same. - Contd
16Result of various scenarios simulated (contd.)
- RESTART SIMULATION
- 6) Experienced velocities exceeding erosional
velocity ratio by a factor of 1.1 in C-24 22
riser during 100 restart operation. However,
erosional velocity limit was not exceeded in the
pipeline network. - 7) Experienced velocities exceeding erosional
velocity ratio by a factor of 1.4 in C-24 22
riser during 25 restart operation. The average
velocity did not exceed the erosional velocity
limit but due to slug flow, the gas velocity
instantaneously surged beyond the erosional
velocity.
17 Result of various scenarios simulated (contd.)
- RAMP-UP SIMULATION
- Ramp-up in steps i.e. increasing the production
from 25 to 50, 50 to 75 and 75 to 100
allowing the flow to stabilize after each
increment do not cause any slug flow at NQG. Such
ramp-up from 25 flow rate to maximum production
rate could be achieved in 3 days. - The liquid surge for 25 to 100 ramp-up was
found to be greatest volume of ramp-up surges
analyzed. The liquid surge volume produced was in
excess of NQG handling capacity. - During 25 to 100 ramp-up, erosional velocity
limit was exceeded for few segments of pipeline
network. - During sequential ramp-up, erosional velocity
limit was only exceeded in C-24 22 riser.
18Recommendations for possible remedial measures
- Increasing handling capacity leading to reduction
in time required to process liquid surges. - Implementation of topside choke leading to
reduction in surge volumes within the current
vessel volumes and handling capacity rates. -
-
19Implementation of the Scheme
- Since the platform facilities have already been
put in place, any addition of facilities for
increasing capacity would involve time and cost.
This would result in delay in commissioning the
plant or shutdown for long duration. - Containing the surge flow at the inlet with choke
/ control valve for the duration that the surge
is anticipated is most reasonable solution to the
problem. - The PID (Piping and Instrumentation Diagram) of
the process before the slug control scheme is
implemented is shown in the next slide. -
-
20Implementation of the Scheme (Before Slug
Control)
21Implementation of the Scheme
22Implementation of the Scheme (contd.)
- A combination of the shutdown valve and control
valve on the bypass line would ensure safe
operation during the start-up of the line after a
shutdown. - 6 control valve has been found suitable for the
control of the slug flow and intermittent gas
flow. Any lower size would become a constraint
for the quantity of the gas flow envisaged
intermittently during the slug flow. - In addition, inlet shutdown valve is provided
upstream of control valve to shutdown facilities
during for upset condition during slug flow.
23Implementation of the Scheme
- The 6 SDV shall be opened manually for START-UP
at site. (The control valve is kept crack open
during this activity). - The 24 SDV will remain in closed condition
during slug flow until it is safe to open for
normal operation once the slug is cleared. - To ensure above, independent local pneumatic
selector pull-in / reset type 3-way selector
valve is provided for both SDVs. - Once the slug flows ceases, 24 SDV shall be
opened and then 6 SDV shall be closed. - Schematic for manual selection of the SDV is
shown in next slide.
24Implementation of the Scheme Control Schematic
25Implementation of the Scheme Control Valve
- The 6 Control Valve has a Hand wheel for on
site manual operations of the valve if necessary.
- Operation of the control valve can be done from
control room, using the Controller being provided
for this valve. Manual or Auto operation mode is
operator selectable. - To begin with, the operation of start up is
envisaged to be manual with a pre determined
Crack opening (up to 20 opening). Once the line
pressure starts dropping from 26 kg/cm2g to 11
kg/cm2g, the valve may be opened further
gradually over a period of time and level of KOD
downstream is continuously monitored alongwith
inlet pressure. - The KOD has its own level controller which shall
maintain the KOD level. When there is liquid
inflow (Slug) which is more than the valve can
handle, (i.e. LCV full open), the operator shall
start to close the SCV gradually to reduce inflow
and maintain the KOD level.
26Implementation of the Scheme Control Valve
(contd.)
- FEEDBACK CONTROL METHODS
- SSIC shall keep the SCV sufficiently open to
allow 80 M3 /Hr flow to maintain KOD level
stable. This opening () will be known better
with experience over a period of time. - The level controller (LIC) for KOD level control
(Condensate level) is utilized for determining
the operation of the SCV in feed back mode. LIC
output shall become PV (Process Variable) for
the SSIC. Set point of SSIC shall be set at a
value in the range 75 to 80 (i.e. 16 to 17mA in
4-20mA). Any increase in the PV value of SSIC
beyond this shall start to close SCV. - SSIC shall keep SCV open for all PV values up-to
the SET-POINT value.
27Implementation of the Scheme Control Scheme
28Implementation of the Scheme Control Valve
(contd.)
- Alternately, LT output (KOD level) can be used
as PV (Process Variable) for SSIC. Set point is
set at a value in the range 75 to 80 (i.e. 16mA
to 17mA in 4-20mA). Any increase in the PV value
of SSIC beyond this shall start to close SCV.
29Conclusion
- It is observed that the adopted method of slug
control for maintaining KOD level is most
appropriate as it is not dependent on complicated
software which use assumed conditions and
predictive methods for slug control.
30Thanks