Slug Handling System on NQ Platform A Case Study for CSeries Pipeline Offshore Engineering Services - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Slug Handling System on NQ Platform A Case Study for CSeries Pipeline Offshore Engineering Services

Description:

Slug flow is a two-phase flow pattern which is characterized by a sequence of ... Unless sized appropriately, the slug flow may cause operational imbalance and ... – PowerPoint PPT presentation

Number of Views:127
Avg rating:3.0/5.0
Slides: 31
Provided by: msTimes
Category:

less

Transcript and Presenter's Notes

Title: Slug Handling System on NQ Platform A Case Study for CSeries Pipeline Offshore Engineering Services


1
Slug Handling System on NQ Platform - A Case
Study for C-Series Pipeline Offshore
Engineering ServicesONGC Ltd.Mumbai
2
Back Ground
  • C - Series fields lie 60 km. West of Daman.
  • Comprises of mainly Gas bearing structures
    viz. C-39-8, C-39-6, C-39-1, C-26, C-24, C-23,
    C-22, B-12-7 and B-12-1.
  • Water depth variation 19m-30m.
  • Each structure has limited production capacity
  • Short production life.

3
Facilities to be created
  • The Scheme shall be completed in three phases
  • Total Unmanned Well Platforms 8 Nos.
  • Phase I - 4 ( C-22, C-24, C-39-1 C-39-A)
  • Phase I (except pipelines) commissioned in April
    2009
  • Phase II (5th Year) - 2 ( C-23 B-12-7 )
  • Phase III (11th Year) - 2 ( C-26 B-12-1 )

4
Pipeline network for C-Series
C-39-A
C-39-1
Phase-I
8X 2.5 km
22 X 60 km C-39-A to C-24
Phase-II
C-23
Phase-III
8 X 3 km
C-22
C-24
8 X 2.5 km
8 X 2 km
C-26
B-12-1
C-24 to NQG 28 X 115 km
8 X 3 km
8 X 2 km
B-12-7
Existing
NQG
Proposed
Uran
5
Production Scenario(Peak Rate)
  • Gas, MMSCMD Condensate, M3/HR
  • Phase I - 3.20
    28.33
  • Phase II (5th year) - 3.58
    67.00

6
Brief Description of the Pipeline System
  • C-Series pipeline is 175 km. long having diameter
    of 22 28
  • The pipeline starts from C-39-A and runs upto
    C-24 with a diameter of 22 and distance of 60
    Km. The line further starts from C-24 and ends at
    NQG with a diameter of 28 and distance of 115
    Km.
  • Seabed on the pipeline route slopes down
    gradually from 20 m at C-series end to 60 m at
    NQG end
  • The pipeline has been designed to transport 3.58
    MMSCMD gas and 67 m3/hr condensate from the
    marginal fields to NQ process complex.

7
Bathemetry of Pipeline route
8
Slug Flow
  • What is slug flow ?
  • Slug flow is a two-phase flow pattern which is
    characterized by a sequence of packs of liquid
    separated by long gas bubbles flowing over a
    liquid film inside the pipe and is normally
    associated with high pressure-drops.
  • How slug is formed ?
  • Slug formation is a phenomenon which is normally
    observed in long distance pipelines having uneven
    terrain (called terrain sluging) and/ or pipeline
    id much higher than that required for normal
    through-put (called hydrodynamic slugging)
  • Implications of slug flow on receiving facilities
  • Unless sized appropriately, the slug flow may
    cause operational imbalance and even cause
    production loss or facilities shut down

9
Study Description
  • A dynamic simulation of the pipeline was carried
    out through Scand Power Technology, Dubai using
    their Olga Software to ascertain the possibility
    of slugging of the pipeline under various
    operating scenario.
  • The objective of the study were to determine the
    slugging of the pipeline under various operating
    scenario like reduced flow, shut down, re-start
    and production ramp-up.

10
Simulation Scenarios
  • In order to optimise the number of simulations,
    following typical cases were simulated using Olga
    software.
  • Constant production rates Considering 25, 50,
    75 and 100 of maximum production rates for
    Phase-I Phase-II.
  • Turn down Simulation Reducing the production
    rates under Phase-II from 100 to 75, 75 to
    50, 50 to 25
  • Shut-in Simulation Shutting down the Production
    under Phase-II of each source simultaneously from
    25 to non flowing condition.
  • Re-start Simulation Restarting the production
    from non-flowing condition to 25 and non-flowing
    condition to 100.
  • Ramp-up Simulation Increasing the production
    from 25 to 50, 50 to 75, 75 to 100 and 25
    to 100.

11
Result of various scenarios simulated
  • CONSTANT PRODUCTION RATES
  • 1) It is observed that higher the production
    rate, lower is the liquid content in the
    pipeline.
  • Mild terrain slugging was observed at upstream
    ends i.e. well heads, for 25 production rate
    for both, Phase-I and Phase-II. Maximum liquid
    content observed in the pipeline ( 2764 m3 in
    Phase-I and 3295 m3 in Ph-II).
  • No slugging was observed at the downstream end at
    NQG and fluid arrival rate at NQG was found to be
    well within the handling capacity of NQG topside
    facilities.
  • 4) Slug flow resulted in well head pressure
    fluctuations of approx. 1 bar. The slug frequency
    was approx. 1 slug per day for Phase-I and 2.8
    slugs per day for Phase-II.
  • Contd.

12
Result of various scenarios simulated (contd.)
  • TURN DOWN SIMULATION
  • It is observed that higher the turndown, higher
    is the time for liquid content to get stabilized.
  • 265 hrs. (11 days) are required for liquid
    content to get stabilized in 28 C-24-NQG
    pipeline when production rate is reduced from
    100 to 25. Whereas stabilization takes around
    70 hrs. (3 days) when production rate is reduced
    from 100 to 75.
  • No slugging was observed during the stabilization
    period for any turndown case.


13
Result of various scenarios simulated (contd.)
  • SHUT IN SIMULATION
  • It is observed that after the wellheads were
    shut-in for 11.5 hrs, the riser base towards NQG
    was completely filled up with liquid due to down
    slope geometry of the pipeline towards NQG.
  • After 24 hours shut-in, the liquids had
    completely filled section from KP 110.63 to riser
    base having pipe volume 175 m3. Moreover, the
    pipe from KP 108.85 to KP 110.63 was partially
    filled accounted for 273 m3 liquid from KP 108.85
    to the riser base.
  • The liquid accumulation towards riser base at NQG
    gives rise to slug upon restart. It was also
    observed that higher the period of shutdown,
    higher is the volume of slug upon restart.

14
Result of various scenarios simulated (contd.)
  • RESTART SIMULATION
  • 1) Both 100 and 25 restart resulted in slug
    flow and were beyond the NQG handling capacity.
    Reduced restart flow rate does not have much
    impact except prolonging the arrival rate of
    slug.
  • 2) Liquid slug was also followed by gas surge of
    magnitude much higher than the design capacity of
    the topside facilities.
  • 3) For restart to 100 production case, the
    liquid rate surged to a peak value after 3 hours
    had passed since flow was resumed. The total
    liquid surge volume in excess of handling
    capacity (100 m3/hr) was 269 m3 and the
    processing time required was 3 hrs. A gas surge
    of magnitude 16 MMSCMD (for a short duration)
    followed by liquid slug of 12758 m3/hr (for a
    short duration) was also observed. Subsequent
    surges were found to be within the handling
    capacity.
  • Contd.


15
Result of various scenarios simulated (contd.)
  • RESTART SIMULATION
  • For restart to 25 production case, the liquid
    rate surged to a peak value after 9.3 hours had
    passed since flow was resumed. The total liquid
    surge volume in excess of handling capacity (100
    m3/hr) was 286 m3 and the processing time
    required was 3.5 hrs. A gas surge of magnitude 11
    MMSCMD (for a short duration). followed by liquid
    slug of 16688 m3/hr (for a short duration) was
    also observed. A subsequent gas surge of equal
    magnitude was observed at10th hour.
  • It is also observed that any shutdown greater
    than 1 hour will produce slug on restart.
    However, additional restart simulation is
    required to quantify the same.
  • Contd


16
Result of various scenarios simulated (contd.)
  • RESTART SIMULATION
  • 6) Experienced velocities exceeding erosional
    velocity ratio by a factor of 1.1 in C-24 22
    riser during 100 restart operation. However,
    erosional velocity limit was not exceeded in the
    pipeline network.
  • 7) Experienced velocities exceeding erosional
    velocity ratio by a factor of 1.4 in C-24 22
    riser during 25 restart operation. The average
    velocity did not exceed the erosional velocity
    limit but due to slug flow, the gas velocity
    instantaneously surged beyond the erosional
    velocity.


17
Result of various scenarios simulated (contd.)
  • RAMP-UP SIMULATION
  • Ramp-up in steps i.e. increasing the production
    from 25 to 50, 50 to 75 and 75 to 100
    allowing the flow to stabilize after each
    increment do not cause any slug flow at NQG. Such
    ramp-up from 25 flow rate to maximum production
    rate could be achieved in 3 days.
  • The liquid surge for 25 to 100 ramp-up was
    found to be greatest volume of ramp-up surges
    analyzed. The liquid surge volume produced was in
    excess of NQG handling capacity.
  • During 25 to 100 ramp-up, erosional velocity
    limit was exceeded for few segments of pipeline
    network.
  • During sequential ramp-up, erosional velocity
    limit was only exceeded in C-24 22 riser.


18
Recommendations for possible remedial measures
  • Increasing handling capacity leading to reduction
    in time required to process liquid surges.
  • Implementation of topside choke leading to
    reduction in surge volumes within the current
    vessel volumes and handling capacity rates.


19
Implementation of the Scheme
  • Since the platform facilities have already been
    put in place, any addition of facilities for
    increasing capacity would involve time and cost.
    This would result in delay in commissioning the
    plant or shutdown for long duration.
  • Containing the surge flow at the inlet with choke
    / control valve for the duration that the surge
    is anticipated is most reasonable solution to the
    problem.
  • The PID (Piping and Instrumentation Diagram) of
    the process before the slug control scheme is
    implemented is shown in the next slide.

20
Implementation of the Scheme (Before Slug
Control)


21
Implementation of the Scheme


22
Implementation of the Scheme (contd.)
  • A combination of the shutdown valve and control
    valve on the bypass line would ensure safe
    operation during the start-up of the line after a
    shutdown.
  • 6 control valve has been found suitable for the
    control of the slug flow and intermittent gas
    flow. Any lower size would become a constraint
    for the quantity of the gas flow envisaged
    intermittently during the slug flow.
  • In addition, inlet shutdown valve is provided
    upstream of control valve to shutdown facilities
    during for upset condition during slug flow.

23
Implementation of the Scheme
  • The 6 SDV shall be opened manually for START-UP
    at site. (The control valve is kept crack open
    during this activity).
  • The 24 SDV will remain in closed condition
    during slug flow until it is safe to open for
    normal operation once the slug is cleared.
  • To ensure above, independent local pneumatic
    selector pull-in / reset type 3-way selector
    valve is provided for both SDVs.
  • Once the slug flows ceases, 24 SDV shall be
    opened and then 6 SDV shall be closed.
  • Schematic for manual selection of the SDV is
    shown in next slide.

24
Implementation of the Scheme Control Schematic


25
Implementation of the Scheme Control Valve
  • The 6 Control Valve has a Hand wheel for on
    site manual operations of the valve if necessary.
  • Operation of the control valve can be done from
    control room, using the Controller being provided
    for this valve. Manual or Auto operation mode is
    operator selectable.
  • To begin with, the operation of start up is
    envisaged to be manual with a pre determined
    Crack opening (up to 20 opening). Once the line
    pressure starts dropping from 26 kg/cm2g to 11
    kg/cm2g, the valve may be opened further
    gradually over a period of time and level of KOD
    downstream is continuously monitored alongwith
    inlet pressure.
  • The KOD has its own level controller which shall
    maintain the KOD level. When there is liquid
    inflow (Slug) which is more than the valve can
    handle, (i.e. LCV full open), the operator shall
    start to close the SCV gradually to reduce inflow
    and maintain the KOD level.


26
Implementation of the Scheme Control Valve
(contd.)
  • FEEDBACK CONTROL METHODS
  • SSIC shall keep the SCV sufficiently open to
    allow 80 M3 /Hr flow to maintain KOD level
    stable. This opening () will be known better
    with experience over a period of time.
  • The level controller (LIC) for KOD level control
    (Condensate level) is utilized for determining
    the operation of the SCV in feed back mode. LIC
    output shall become PV (Process Variable) for
    the SSIC. Set point of SSIC shall be set at a
    value in the range 75 to 80 (i.e. 16 to 17mA in
    4-20mA). Any increase in the PV value of SSIC
    beyond this shall start to close SCV.
  • SSIC shall keep SCV open for all PV values up-to
    the SET-POINT value.

27
Implementation of the Scheme Control Scheme


28
Implementation of the Scheme Control Valve
(contd.)
  • Alternately, LT output (KOD level) can be used
    as PV (Process Variable) for SSIC. Set point is
    set at a value in the range 75 to 80 (i.e. 16mA
    to 17mA in 4-20mA). Any increase in the PV value
    of SSIC beyond this shall start to close SCV.

29
Conclusion
  • It is observed that the adopted method of slug
    control for maintaining KOD level is most
    appropriate as it is not dependent on complicated
    software which use assumed conditions and
    predictive methods for slug control.

30
Thanks
Write a Comment
User Comments (0)
About PowerShow.com