ABP/RTL
  • Main RTL Activities for 2007/8-
  • Shutdown Co-ordination and Planning for PSB, PS,
    LEIR, TT2, AD, SPS, TT40 TI8
  • CTF3 and CLEX installation
  • 3 MeV test stand installation
  • LHC Installation (Including TI2)
  • Preparation for LINAC4 construction
  • AB Consolidation project
  • TSO support for accelerators and service
    buildings

2
ABP/RTL
  • Simon Baird  Section Leader AB Consolidation
  • Raymond Brown PS 
  • Sven De Man PSB  LHC Installation
  • Nicolas Gilbert SPS, TT40, TI2 TI8
  • Christian Lacroix LEIR, TT2, AD  3MeV test stand
  • José Monteiro CTF3, CLEX Planning support
  • Bernard Pires SPS Surface buildings 
  • Rosario Principe PS, 3MeV test stand LINAC4
  • Michel Samson SPS, TI2 installation, AB Space
    Management for ADM
  • (CLIC Experimental Area)

3
Shutdown/Installation Co-ordination
  • 2006/7 Shutdown
  • 8 PS main magnets renovated re-installed
  • Some MTE preparatory work was completed but the
    main MTE work will still take place in the 2007/8
    shutdown
  • 76 SPS main magnet water manifolds repaired
  • INB cable loop installed at the SPS
  • Major tunnel repairs in TT2
  • New beam stopper in BTP line
  • PSB main magnet water cooling renovation
  • CTF3 Combiner ring ejection line completed
  • CLEX building completed (June 07)

4
Shutdown/Installation Co-ordination
  • 2007/8 Shutdown (Minimum length 12 weeks)
  • MTE installation
  • Essential for full CNGS beam operation
  • PS Main magnet renovation (8 units?)
  • SPS main magnet manifold repairs (80 planned)
  • Move 8 PSB wire scanners?
  • 3MeV test stand installation
  • CTF
  • Installation of CLEX equipment
  • Installation of the TL2 line (from the Combiner
    Ring to the CLEX)
  • LINAC4
  • Choice of site
  • Technical coordination for the project

5
  • AB Consolidation
  • There are 44 active Work Units in 2007
  • By the end of 2007 a total of 36.8 MCHF
    will/should have been spent (total budget at
    present is 50 MCHF )
  • A full review of all outstanding Consolidation
    items has been completed-
  • White Paper request for 27 MCHF 70 FTEs
  • Waiting for the green light
  • TSOs for Accelerators and the Service Buildings
  • LHC activities
  • One RTL section member is detached (60) to TS
    for the Coordination of LHC installation
    activities
  • TI2 installation and commissioning coordination
  • No decision on How an LHC shutdown will be
    managed