PROJECT INTEGRATION MANAGEMENT PROCESS - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

PROJECT INTEGRATION MANAGEMENT PROCESS

Description:

PROJECT INTEGRATION MANAGEMENT PROCESS. LYNDA ERLYDIA. JULIA USENKO. 5 ... General management skills. Product skill and knowledge. Work ... Project Management ... – PowerPoint PPT presentation

Number of Views:181
Avg rating:3.0/5.0
Slides: 34
Provided by: WSE9185
Category:

less

Transcript and Presenter's Notes

Title: PROJECT INTEGRATION MANAGEMENT PROCESS


1
PROJECT INTEGRATION MANAGEMENT PROCESS
  • LYNDA ERLYDIA
  • JULIA USENKO

2
5 Basic Process Groups
  • Initiating Processes
  • Planning Processes
  • Executing Processes
  • Controlling Processes
  • Closing Processes

3
Links Among Process Groups in Phase
Source PMI PMBOK 2000, Vijay Kanabar 2004
4
How to Baseline
http//www.global-pmp.com/hult/
5
Methodology of Project Integration Management
http//www.global-pmp.com/hult/
6
Project Plan Development
http//www.global-pmp.com/hult/
7
Project Plan
  • A formal, approved document used to guide
    both project execution and project control. The
    primary uses of the project plan are to document
    planning assumptions and decisions, facilitate
    communication among stakeholders, and document
    approved scope, cost, and schedule baselines. A
    project plan may be summary or detailed

PMBOK Guide, 2000 Edition, Glossary
8
Project Plan Contents
9
Project Plan Components
http//www.global-pmp.com/hult/
10
Kickoff Meeting
  • Participants
  • Project Sponsor
  • Project Manager
  • Sub-project Manager
  • Resource Owners
  • Key Human resources
  • Purpose
  • Clarification of the project
  • Individual roles responsibilities
  • Interdependence with other projects
  • Points of contact
  • Commit to the success of the project

http//www.projectmagazine.com/may00/kick1.html
11
Preparation!!!
  • Introduction
  • Presentation of participants
  • Project overview
  • Project goals and objectives
  • Project organization
  • Project Plan
  • Project methods and tools
  • Work methods and tools
  • Communications management
  • Risk analysis
  • Summing up
  • Team building activity

http//www.projectmagazine.com/may00/kick1.html
12
Project Plan Execution
  • The primary process for carrying out the project
    plan
  • Tools
  • General management skills
  • Product skill and knowledge
  • Work Authorization System
  • Status Review meetings
  • PMI and organizational procedures

13
Execution Process
  • Project plan execution
  • Quality assurance
  • Team development
  • Information distribution
  • Solicitation
  • Source selection
  • Contract administration

14
Work Authorization System
  • A formal procedure to sanction project work
    so that it is done at the proper time and in the
    proper sequences

15
Status Review Meeting
  • The results of meetings which should be
    reported and scheduled regularly, including
    meeting minutes and status/progress reports, for
    all project team members as well as management of
    stakeholder areas

16
Integrated Change Control
  • A control process coordinating changes across
    the entire project and the effective change
    control require
  • Maintaining the integrity of the performance
    measurement baseline
  • Ensuring that changes to the product scope are
    reflecting in the definition of the project scope
  • Coordinating changes across knowledge areas

17
Change Control Process
  • Source http//www.global-pmp.com/hult/documents/
    PlanningControlClosing.pdf

18
Change Control
  • Tools Techniques
  • Change control system
  • Changes to document
  • Change to control board (CCB)
  • Approval
  • Contract implications
  • Configuration management
  • Functional baseline
  • Change control
  • Record report changes
  • Audit to verify conformance
  • Review performance adjust
  • schedule/budget accordingly
  • Additional planning
  • Project Management Information System

19
Configuration Management
  • The system is used to ensure that the
    description of the projects product is corrected
    and complete.
  • Basic steps of the configuration management
  • Identify and document the functional and physical
    characteristics of an item or system
  • Control any changes to such characteristics
  • Record and report the changes and its
    implementation status
  • Audit the items and system to verify conformance
    to requirements

20
Project Management Information System
  • The system which is an all-encompassing phase
    to mean the system set up in advance that keeps
    the project manager informed of the status of all
    project task which may use A Gantt Chart

21
Tracking Gantt Chart
22
Closing Process
There are no facilitating processes for the
Closing Process
PMBOK Guide, 2000 Edition, Figure 3-8.
23
Exam Questions
  • You are a new project manager who has never
    managed a project before and you have been asked
    to plan a new project. It would be BEST in this
    situation to rely on -------------------- during
    planning in order to improve your chance of
    success.
  • A. Your Intuition
  • B. Your training
  • C. Historical information
  • D. Responsibility chart

24
Explanation of Answer
  • Answer Q 1 C
  • Explanation Because you have no experience,
    you will have to look at the experience of
    others. This information is captured in the
    historical records of previous projects

25
Question 2
  • Your company just won a major new project. It
    will begin three months and is valued at US
    2,000,000. You are the project manager for an
    existing projet. What is the FIRST thing you
    should do once you hear of the new project?
  • A. Ask management how the new project will use
    resources
  • B. Resource level your project
  • C. Crash your project
  • D. Ask management how the new project will affect
    your project

26
Explanation of Answer
  • Answer Q 2 D
  • Explanation As you work on a project, you need
    to constantly re-evaluate the project goals and
    how the project relates to other concurrent
    projects. Taking into account corporate goals, is
    your project still in line with them ? If the
    other project will impact yours, you need to be
    proactive and work on options now

27
Question 3
  • You are assigned to be the project manager in the
    middle of the project. The project is within
    tolerances for the baseline, but the customer is
    not happy with the performance of the project.
    What is the FIRST thing you should do ?
  • A. Discuss it with the project team
  • B. Recalculate baselines
  • C. Renegotiate the contract
  • D. Meet with customer

28
Explanation of Answer
  • Answer Q3 D
  • Explanation First you need to find out why the
    customer is not happy. Then you meet with the
    team and determine options

29
Question 4
  • During the project execution, the project manager
    determines that a change is needed to material
    purchased for the project. The project manager
    calls a meeting of the team to plan how to make
    the change. This is an example of
  • A. Management by objectives
  • B. Lack of a change control system
  • C. Good team relations
  • D. Lack of a clear work breakdown structure

30
Explanation of Answer
  • Answer Q4 B
  • Explanation The project manager is asking how to
    make a change. The procedures, forms, sign-offs
    and other similar requirements for handling
    changes should have already been determined in
    the change control system (choice B). Because
    they werent, the project manger will waste
    valuable work time trying to figure it out after
    the fact.

31
Question 5
  • The client demands changes to the product
    specification that will add two weeks to the
    critical path. The project manager should
  • A. Crash the project to recover the two weeks
  • B. Fast Track the project to recover the two
    weeks
  • C. Consult management before proceeding
  • D. Advise the client of the impact of the change

32
Explanation of Answer
  • Answer Q5 D
  • Explanation To handle changes, the project
    manager must evaluate the impact to the project,
    look at options and then discuss the impact and
    options with the stakeholders. There is no way to
    know if fast tracking (choice B) or crashing
    (choice A) is the best way to solve this problem.
    The project manager should take action to
    evaluate before they go to management with
    options (choice C). D is the most correct answer.

33
Bibliography
  • PMI PMBOK 2000, Vijay Kanabar 2004
  • PMP Exam Prep Course, 4th edition, Rita Mulcahy,
    PMP
  • PMBOK Guide 2000 Edition
  • http//www.projectmagazine.com/may00/kick1.html
  • http//www.dof.ca.gov/HTML/IT/PMM/OPTIMIZED/PM4.5
    20Project20Startup20Kickoff.pdf
Write a Comment
User Comments (0)
About PowerShow.com