Title: APC InfraStruXureTM
1APC InfraStruXureTM
Thomas Lam Senior District Manager, APC HK (852)
8200-8564 Thomas.lam_at_apcc.com
2Agenda
- DataCenter Challenges
- Introduction to InfraStruXure
- Rack - Cooling
- Power - Services
- ISX Reference Sites
- When do you need ISX?
- Open Discussion
3NCPI 4 Availability Layers
4Server Room/ Datacentre Challenges
5Data Center ChallengesBackground Information
- Voice of Customers
- 500 Client Visits
- Engineering User Groups
- IT Managers/consultants
- Consulting Engineers
- Facility Managers
- Project Managers
- Electrical Contractors
- Professional 3rd Party Consultants
- Availability Consulting Services
6What are the top three things you would change
about your data center infrastructure if you
could?
7Data Center Basic Design
8Top Data Center Challenges
9Top Data Center Challenges
- 1. Optimize capital investment and available
space - We made 100 investment on Infrastructure
although we needed only 20 infrastructure at the
beginning. - Lack of scalable solutions
- Cannot right size
- High maintenance / service costs
- Infrastructure takes too much space
10Top Data Center Challenges
- 2. Adapt to ever-changing requirements
- I consolidated five servers into one more
powerful high-availability server. The new
server has 2 / 3 power supplies and my
infrastructure cannot support that - Small changes require too much planning
- Todays infrastructure is difficult to re-locate
- Increasing power density causing heat issues (42
servers in one rack!) - New Servers do not fit into old Racks
11Top Data Center Challenges
- 3. Plan for a power density that is increasing
and unpredictable. - Servers are continuing to get smaller. I
continue to bring in more power and cooling as my
IT equipment changes. - Future power densities cannot be predicted
- Power infrastructure should be as flexible as IT
systems - Manage heat to avoid downtime
12Top Data Center Challenges
- 4. Accelerate speed of deployment
- I need a new computer room in two weeks and
it takes me six months to get it built. - Customization leads to long design time
- Multiple vendor interfaces make planning
difficult - High level consulting required
- Installation needs long planning and is labor
intensive
13Top Data Center Challenges
- 5. Lower the cost of service contracts
- I bought the 3-phase UPS system at a great
price, but I was locked into an expensive service
contract. - Servicing a UPS should be as easy as IT equipment
- Preventative failure analysis
- Service costs should be right sized and match
the current infrastructure being used.
14Top Data Center Challenges
- 6. Increase availability per dollar
- If I want redundancy in my power
infrastructure it takes twice the space and
cost. - Infrastructure Availability lower than IT systems
Availability - Redundancy too expensive (dollars and space)
- Long runtime expensive for whole data center
- Spend or sacrifice are todays choices
- Need targeted availability
15Top Data Center Challenges
- 7. Decrease Mean-Time-To-Recovery (MTTR)
- Failure of my data center infrastructure
means we will never achieve our availability
goals. - Build in redundancy like RAID
- Make systems smart
- Self-diagnosing
- Predictive failure analysis
- Make systems easy to service
16(No Transcript)
17Top Data Center Challenges
- 8. Minimize points of failure between the UPS and
critical load - Even though my computer room is supported by
a centralized UPS, I still see downtime when
problems occur in the distribution panel feeding
my racks. - Reducing the number of components between the UPS
and the critical load will increase availability
18Integrated Power, Cooling, and Rack
Infrastructure for Critical Networks
Increase availability while decreasing your total
cost of ownership
19 20Have you ever seen a site like this...?
21(No Transcript)
22What is APCs Rack System?
23NetShelter VX Core Advantages
- Cooling
- Power Distribution
- Cable Management
- Management
- Guaranteed Compatibility
24CompatibilityFits like a Glove Guarantee
- All EIA-310 19 equipment will fit in NetShelter
VX or your money back. - APC is committed to ensuring that all RM
equipment physically fits into the NetShelter VX.
25Integrated Cable Management
26 27Power Protection Methodologies in the Data Center
Point-of-Use (Rack) - one UPS used to protect a
single device or rack
Centralized (Room) - one UPS and/or central or
distinct location of the UPS
28Power Protection Methodologies in the Data Center
- Zone (Row)
- a UPS (along with other components) powering a
row(s) of racks - or a group of non-racked equipment
29Scalable Data Center Architecture for
Infrastructure On-DemandTM
APC has 3 standard solutions types depending on
the size of the Zone
30Scalable Data Center Architecture for
Infrastructure On DemandTM
Symmetra PX 10 - 40 kW
- 40kVA/40kW capacity in 10kVA/10kW power module
increments - power factor corrected input
- fully rated inverter
- Power modules arranged in N1 configuration
- Battery modules arranged in a parallel
redundant configuration - All modules are hot-swappable
- Housed in a 870mm NetShelter VX enclosure
- H x L x D 2070mm x 610mm x 870mm
- 125 continuous rated, static switch module
- XR frames available for longer runtime
requirements
31Power Distribution System
- Replaces
- Isolation Transformer
- Service Bypass Panel
- Output Panel, Cabling, Wiring
- Standard 19 cabinet footprint
-
32(No Transcript)
33On-demand Scalable, Manageable, Pre-engineered
Solutions
- Availability Tiers
- Choose your level
- N1
- N1 with External Redundancy
- Arrayed Redundant
34Tier I - N1 Design
Statistical Availability 99.99
35Tier II - External Redundant Design
Statistical Availability 99.999
36Tier III - Arrayed Redundant Design
Statistical Availability 99.99999
37(No Transcript)
38(No Transcript)
39 40Rack Air Distribution Unit (ADU)
- 2U rack-mounted fan unit that delivers cool air
to the equipment contained in a rack enclosure. - ADU helps to eliminate temperature differences
between the top and bottom of the enclosure. - Prevents hot exhaust air from re-circulating to
the inlet of the enclosure. - Best suited for racks with load densities up to
3kW.
41(No Transcript)
42Air Removal ARU
ARU
43NetworkAIR Air Removal Unit (ARU)
- Applications
- Densely-populated racks in small data rooms to
large data centers - IT enclosures with cabling that blocks air
exhaust in the rear - Enclosures that exceed 3.5 kW load capacity
- 8.0 kW heat removal capacity at 1200 cfm (2040
m³/h) design airflow with one fan as redundancy
and 11C temperature rise across servers - Drop ceiling environments where the A/C
efficiencies can benefit from higher return
temperatures
44NetworkAIR FM
- Floor mounted precision air conditioning for IT
and data center environments in 35, 40 and 50 kW
modules. (10, 12, 15 tons) - The next generation in precision cooling systems.
- More efficient
- More reliable
- Less expensive to maintain
- More intelligent
45 46ISX Reference - HK
- Disney Hong Kong
- NRI Limted
- Poly University
- City University
- Education Dept.
- Agile Software Ltd.
- Radio HK
- Kerry Logistics
- Macau Customs
- Department of Health
- Gold Quest
- Hospital Authority (EMSD)
47Thank You!
Open Discussion !