Title: MDA Supply Chain Initiatives Presentation to GSFC Supply Chain Conference
1MDA Supply Chain Initiatives Presentation to
GSFC Supply Chain Conference
DISTRIBUTION STATEMENT A. Approved for public
release distribution is unlimited.
Ed JopsonMDA/QSI Division Chief28 October 2008
Approved for Public Release 07-MDA-3907 (14 OCT
08)
2A Sampling of Supply Chain Initiatives
- Assurance Improvement Action Plan (Stand-down,
Change Control, QPPRs, Audits) - Mission Assurance Reps (MARs) Supplier audits
- MDA/Industry Joint Industry (JIT) Initiative 2
3Current Interceptor Quality Status
- Interceptor supplier quality escapes impacted
2008 program performance - Recent issues identified the need to implement
additional product acceptance control processes
at lower tiers - Immediate Actions
- Conduct Quality Stand Down across Program
- Stop work at Supplier Sites. Senior
Leadership/Quality Staff to discuss quality,
escapes, attention to detail, failure to follow
processes, inadequate coordination/authorization
of product/process changes - Multiple Sessions at Prime, 2nd Tier Major
Sub-Contractors and Lower Tier Suppliers - 2. Institute Product and Process Change Control
- 3. Prime
- Conduct detailed Quality, Product Process
Reviews (QPPRs) All suppliers and integration
centers. - Conduct review and verification of training and
certification of manufacturing workforce.
4Product Assurance Improvement Action Plan
- Immediate Actions contd.
- 3. Prime
- Implement proactive Issue Identification Program
- Implement hardware/software pedigree review
process as part of Ship Readiness Review process - Implement incremental product and process
verification as part of standard supplier product
acceptance process - Prudently implement additional MAP/PMAP elements
- Conduct hardware pedigree inspections of in
stock product if product currently out of
production - Conduct baseline review across supply chain of
product acceptance and screening - MDA/QS Director, Deputy Director, Interim
Assurance Integration Manager and MAR arranged to
visit Supplier Sites, first as Meet and Greet,
then Walk the Floor, then to Audits 6 months
SAMPLING
Since early 2005, approx 30 Audits conducted
5Mission Assurance Rep (MAR) Supplier Audit Focus
6Purpose and Origin of the Assessment
- MARs are MDA/QS reps in-plant throughout supply
chain - Audits are performed on critical supply base to
assess and mitigate risk prior to incurring
detrimental programmatic impacts - Provides proactive team approach with Govt and
Contractor - The communications of Lessons Learned and Best
Practices is an important part of the overall
assessment process - Lessons Learned are adverse work practices of
experiences that are captured and shared to avoid
reoccurrence - Best Practices are good work practices or
innovative approaches that are captured and
shared to promote repeat application - Lessons Learned and Best Practices may or may not
be related to contractual requirements but are
offered in the spirit of making the Supplier,
Prime, and MDA more successful
Its All About Mission Success
7Plan for the Assessment
- MAR and Prime/1st Tier Supplier Quality selects
key suppliers for inclusion in the assessment
process for the upcoming year - Schedule is generated based upon priority and
risk, and is flowed and socialized with Govt and
Contractor Program Offices - Tentative schedule is agreed to and implemented
- Notification is provided one week prior to Audit
to Prime Contractors, subs and the program
offices
8Expectations of the Assessment Team
- Expeditious assessment of the disciplines being
reviewed - Constant communications with the company escorts
no surprises of findings and observations at
out-brief - A verbal out-brief of the findings and
observations, including any positive
observations, at the end of the onsite assessment
activity - Discrepancies must be based upon contractual
requirements - Observations are based upon best practices and
the MDA MAP - Recommendations will be made where ever practical
- Written follow-up of verbal out-brief within a
reasonable period of time (normally within two
weeks)
9Expectations of the Supplier
- Printed procedures / work instructions for the
disciplines being assessed (FOD Plan, ESD
Procedure, Contamination Control Plan, QMS
Manual, etc.) Access to other documents as
needed - Points of contact / escorts for each assessment
sub-team - Escorted access to the production areas and
personnel for assessors during assessment
activities - A working lunch at the suppliers facility in
order to make more efficient use of the time
allotted. (no off-site luncheon) - Attendance of an assessment out-brief at the end
of the assessment activity by senior management - Written response to all findings and observations
provided by the assessment team - Cooperation during follow-up verification
activities.
10Assessment Activity
- The assessment activity is conducted over a
one-to two-day period, depending upon supplier
facility size - Auditors are composed from MDA/QS, DCMA,
Prime/1st Tier and Govt Program Offices and
typically number 6-8 individuals - Auditors are chosen to represent a discipline
they are comfortable with and have in-depth
experience. In many cases, the individuals are
Subject Matter Experts (SMEs) - Daily status summary is e-mailed at the
conclusion of each day to QS, Program Offices,
prime contractor, supplier, and auditors so that
one story is conveyed and misinformation is
minimized
11Assessment Activity
- The disciplines that are assessed are as follows
(as applicable) - Foreign Object Elimination / Foreign Object
Damage Prevention - Contamination Control
- Tool Control
- Critical Lift/Move
- Electrostatic Discharge (ESD) Prevention
- Limited Life Materials management
- Calibration and control of tools / test equipment
- Supplier Management Requirements Flow-down
- Manufacturing Planning
- Non-Conforming Material
- Corrective Action Process
- Configuration Management
The assessment is based upon contractual
requirements and best practices
12Typical Audit Agenda
- Welcome and Introductions 800 815
- Review of Purpose of Assessment by Raytheon 815
830 - Company Overview re facility, MDA work by
Supplier 830 900 - Break / Assessment team meeting 900 915
- Assessment Activity 915 1145
- Lunch 1145 1230
- Assessment Activity 1230 400
- Assessment Team Meeting 400 430
- Out brief 430 500
- Day Two Agenda Adjusted According to Time Line
13Audit Record
- Documented within two weeks and released to the
supplier - Contractor has 30 days to respond
- Audit records are entered in the Prime/1st Tier
C/A system and tracked through closure - Closure requires concurrence from MDA MAR and
Government Program Office
14Out-Brief and Conclusion
- Supplier is provided a daily verbal out brief
from each team at the end of the day - Auditors document findings within two weeks post
audit - Findings are entered in Prime/1st Tier CA Web and
released to the supplier through Contracts - Supplier responds to findings
- Findings are routed to team members for review
and comment - Upon concurrence from MAR and Program Office,
findings are closed in CA Web
15 MDA Joint Industry Team (JIT) Energetic
Materials Supplier
16General Impressions from MA Audit
- Material control (conforming and nonconforming)
practices and situations identified during the
audit in the manufacturing and test areas are
inadequate - Management Corrective Action systems focus on
short term, reactive solutions and do not ensure
long term, proactive preventative action - Unapproved and uncontrolled changes to test and
build documentation - CM policies and practices do not provide adequate
management or control of the configuration of MDA
hardware - Numerous safety and OSHA compliance issues across
the enterprise - Very significant amount of FOD in the production
and test areas, static generators in ESD
sensitive areas, and lack of tool control along
with grounding and grounding verifications issues
17Conclusions
- This audit highlighted the need for immediate
action towards improving quality at supplier - Two locations provide products that are mission
critical to MDA strategic systems - Situation at both locations posed a significant
risk to MDA hardware - Immediate action required to implement a
containment strategy to prevent shipping of
non-conforming hardware - Immediate action required to assist supplier in
improving their manufacturing, quality,
engineering and management systems
18Actions (JIT)
- QS provided a full time lead to head up the
Industry stakeholder team (JIT) with the
responsibility for immediate resolution of all
audit findings - Full time team in plant at both sites
- Boeing, Raytheon, Orbital, ATK, Lockheed Martin
- Plus DCMA and MDA
- Rotating JIT senior/Executive Leads on site every
week - Implement a containment strategy in parallel with
working with PSEMC to improve their
manufacturing, quality, engineering, and
management systems - Surveillance of all in process product
inspections - Surveillance of targeted processes
19Actions (JIT)
- FOD/ESD/Safety Audits in all areas, all shifts
- Documentation/Build Paper Reviews
- Capture all observations on RAIL (Rolling Action
Item List) - RAILs get dispositioned every day
- Review of all closed RCCA documents for
legitimate RC and Effective CA - Work with Supplier to establish verify RCCA on
all MDA Audit Findings before submittal to the
MDA Pgm offices - Weekly reviews with Supplier leadership to make
sure the plan is being executed - Conduct a JIT corrective action assessment of
both sites to validate disposition of audit
findings before official CAA - Exit Criteria sustained metrics at zero