Title: A NEW TOLL ROAD COMES ON LINE
1A NEW TOLL ROAD COMES ON LINE
- Stephen D. Hogan
- Executive Director
- Northwest Parkway Public Highway Authority
- March 5, 2004
2What toll financing attitudes must be different
from those of a traditional highway project?
- Public/Private Partnerships must be viewed as a
solution to needs, not a last ditch option to
solve an immediate problem - Public Owners should not settle for traditional
scheduling, approval, contracting, and financing
processes and methods, to build new toll roads - Public Owners must not be afraid to be proactive,
instead of reactive - Public Owners need to identify a clear advocate,
a clear goal to achieve, and a clear reason to
move forward now even though others may say it
is not yet time - Public Owners must give complete support to those
who are charged to accomplish the task at hand
3What is the Northwest Parkway?
- 4 lane, limited access, expandable, interstate
standard, open road toll way - Connects I-25 and E-470 with U.S. 36 in Central
Colorado - Built to allow future mass transit to be
constructed in the median - Paralleled by perpetual open space and stringent
land use control
4What is the Northwest Parkway?
- 9.5 Miles of new toll road
- 2 major interchanges I-25 U.S. 287
- 26 Bridges Structures
- Toll Plaza/Administrative Office Building
- Automated Toll Collection System
- 2 Ramp Plazas
5What is the Northwest Parkway?
6What is the Northwest Parkway?
7Who built the Northwest Parkway?
- Members
- Ex Officio Associate Members
- Built with the further cooperation of the E-470
Public Highway Authority, the FHWA, the Corp of
Engineers, and the EPA
City CO - Broomfield
City of Lafayette
Weld County
City of Arvada
Regional Transportation District
Interlocken Metro District
Colorado Dept. of Transportation
Jefferson County
8Where is the Northwest Parkway?
9When was the Northwest Parkway Built?
- 1988 Public Vote Fails to Build the Road
- 1995 Broomfield and Boulder County identify a
possible future road corridor on maps - 1998 A non-profit corporation is formed to
advance the possibility of reviving the road - 1999 Design/Build Contractor is selected
- 1999 Northwest Parkway Public Highway Authority
is formed - June, 2001 Bonds sold to build the Parkway
- November, 2003 Road opens to traffic
10Why was the Northwest Parkway Built?
- To extend the Denver Beltway
- To avoid the cost of building new, or expanding
existing, local roads - To ensure that development occurred in specified
locations - To provide for a future mass transit service
corridor
11How did the Northwest Parkway conform to the
different toll financing actions?
- The Design/Build Contractor was selected through
a 1-1/2 page RFP - The Design/Build Contractor provided 9M in up
front costs for environmental work, traffic
revenue studies, and administrative support and
was repaid only from a successful financing (
through a success fee agreement) - In 1999, the Authority demanded, and received, a
four year completion schedule from selection to
open for traffic. - The price for the Design/Build contract was set
in 1999, and true change orders on the 190M
contract totaled less than 2. Both sides knew
change orders would not be well received when
presented, and both sides held to that
philosophy. - The Authority did not exist in June, 1999. In
June 2001, it issued over 410M in revenue bonds
in its own name the bonds were insured, and
therefore AAA rated.
12How did the Northwest Parkway conform to the
different toll financing actions? (Continue)
- The Authority did not buckle to demands for an
EIS, and instead conducted 2 EAS, and invented a
Corridor Environmental Review - The elected officials on the Board of Directors
of the Authority determined that the Chairman of
the Board and the Executive Director of the
Authority would be the talking heads for the
project. - The Board determined that the only publicity
during construction would be that generated by
the media itself. As a result, for some
opponents the Project came in under the radar.
The Project opened 6 weeks ahead of schedule. - Every time an opponent said the Project wasnt
needed, or was ahead of when it was needed, the
response was, for once, government is planning
for the future, rather than reacting to the
past. - The staffing philosophy of the Authority showed 3
employees when it was created, 4 employees when
the contract was signed, 5 employees at the
ground breaking, and only 3 more added over the
last three years. All employees are at-will. - The Board evaluates the Executive Director, and
the Executive Director runs the organization.
13What toll financing attitudes must be different
from those of a traditional highway project?
- Public/Private Partnerships must be viewed as a
solution to needs, not a last ditch option to
solve an immediate problem - Public Owners should not settle for traditional
scheduling, approval, contracting, and financing
processes and methods to build new toll roads - Public Owners must not be afraid to be proactive,
instead of reactive - Public Owners need to identify a clear advocate,
a clear goal to achieve, and a clear reason to
move forward now even though others may say it
is not yet time - Public Owners must give complete support to those
who are charged to accomplish the task at hand
14Who made the project work?
- Dick Fontane - George K. Baum Co. - Underwriter
- David Klinges Jim Taylor - Bear Stearns -
Underwriter - Ed Icenogle Erin Smith - Icenogle Norton Smith
Blieszner General Counsel, Design/Build
Contract and Right of Way - Pamela Bailey Campbell Carter Burgess -
Financial Officer - Norm Lovejoy Lovejoy Associates Specialized
Engineering Support - Bob Sakaguchi and Mark Shotkoski Carter
Burgess Environmental Studies and Project
Oversight Engineering - Terry Geohegan Bader Geohegan Operations
Support - Jim Allen UTS United Toll System
15Who made the project work?(Continue)
- Steve Bobrick Right of Way
- Richard Bauman Chief Engineer
- Jill Lamoureux Financial
- Benton Tempas IT
- Lina Kheng Contract Support
- Jamie Dawson Administrative
- Kerri Weaver Marketing
- Michelle Sinaka Administrative
- Gerry Nielsten Bill Ihlo Vollmer Associates
Traffic Revenue Studies - Matt Scott PBConsult Land Use Studies
- Rich Linford Washington Group Design/Build
Contractor - Jeff Kresl Kiewit Design/Build Contractor
- Steve Medina NPC Design/Build Contractor
16Points to Ponder
- Why bond a decreasing revenue stream, i.e. gas
tax? - Why use federal funds for new roads when there is
no requirement to do so? - Why build only toll projects which simply
encourage the double taxation argument, i.e. hot
lanes? - Why agree to an EIS, when an EA and other site
specific environmental review will accomplish the
same thing? - Why not encourage public/private financial
partnerships to help build new roads? - Why not encourage bonding based on tolls to build
new roads? - Why not encourage design/build?
- Why not encourage design/build/operate as a way
to get the private sector into the toll road
building business? - Why not be as creative in 2004 in searching for a
solution as the new Administration was in 1954,
when it decided to build the interstate highway
system?