Title: Parking Study Overview:
1Parking Study Overview
- Available Alternate Parking Capacity
- Determination of Shortfall at 20,000 Students
- Alternative Studies Design Options
- Evaluation, Ranking, Changes and Recommendations
2Available Alternate Parking Options to capture
parking spaces at peak times
-
- 1a b Soccer Field lawn (not paved) 394
- 2 Football at down ramp 71
- 3a 2-Way Loop Road with parallel parking 88
- ______
- Net Captured Parking 553
3Adjusted Parking InventoryAnd Determination of
Shortfall
- Existing spaces 3,907
- Less spaces lost due to construction (172)
- _____
- A. Net Remaining 3,735
- B. Number Spaces Needed 5,091
- at 20,000 Students, Week 2 _____
- SHORTFALL B A spaces short 1,356
- Less Net Captured Parking
( 553) - Net Shortage at Build Out 803
-
4Parking Alternatives
5College Meetings Held to Review Material
- 9/15/05 Combined Planning Budget Council and
Facilities Committee meeting to discuss
parking alternatives and finalize needed
parking count - 9/21/05 - Facilities Committee meeting to review
options make recommendations to PB
Council - 9/27/05 ASGC Board Meeting to Discuss Parking
Options and feasibility studies with Students - 9/29/05 Planning Budget Council meeting,
discuss Facilities Committee
recommendations, made funding Plan
request
6(No Transcript)
7SOCCER FIELD
8Soccer Field Parking StructureProject Cost
Estimate Per Space Estimated Cost
- Disadvantages with this option include
- The soccer field is already counted in the
alternate parking plan, so structure would have
to add 1200 spaces to include parking
augmentation spaces. - Some minor EIR issues, update College EIR
- Extended walking distance to the central campus.
- Loss of instructional and athletics space during
construction - Cost of constructing soccer field on top level,
(possibly 4th level) - Aesthetics issues, extremely tall structure at
high point of campus - Fill area that would require significant
earthwork - Possible exiting issues with all parking exiting
through parking lot 4A - Advantages with this option include
- Would minimize disruption of the campus during
construction, and have a minimal impact on
existing student parking. - Would replace existing soccer field with new
field.
9NO. PROPERTY (Access from Lot 4-A)
10North Property Parking through Lot 4AProject
Cost Estimate 4,990,982 Per Space
Estimated Cost 6,101Does not include land
costs
- Disadvantages with this option include
- The property owner has been reluctant to discuss
the sale of the property with the district. - EIR issues including, protected species, shrubs
and possible vernal pools. Risk of expending
funds to find out discretionary approval for
vernal pools can not be obtained - Time needed to complete an EIR on the site.
- Extended walking distance to the central campus.
- Possible exiting issues and back up with all
parking exiting through parking lot 4A - Advantages with this option include
- Gives the college additional land to expand its
services in the future. - Would minimize disruption of the campus during
construction, and have a minimal impact on
existing student parking. - If land is available it is the least expensive
option, depending on sale price of land which is
not included in cost estimate attached. - Dr. Martinez has been working with the Foundation
to work up a proposal about a possible donation
of the property.
11NO. PROPERTY (Access through Maintenance Yard)
12North Property Parking though Maint.Project Cost
Estimate 8,930,897Per Space Estimated Cost
11,094Does Not Include Land Costs
- Disadvantages with this option include
- The property owner has been reluctant to discuss
the sale of the property with the district. - EIR issues including, protected species, shrubs
and possible vernal pools. Risk of expending
funds to find out discretionary approval for
vernal pools can not be obtained - Time needed to complete an EIR on the site.
- Extended walking distance to the central campus.
- Additional cost and service disruption caused by
relocation of maintenance buildings - Advantages with this option include
- Gives the college additional land to expand its
services in the future. - Would minimize disruption of the campus during
construction, and have a minimal impact on
existing student parking. - Provides better traffic flow than lot 4A option.
- If land is available it is the second least
expensive option, depending on sale price of land
which is not included in cost estimate attached. - Dr. Martinez has been working with the Foundation
to work up a proposal about a possible donation
of the property.
13EAST CANYON
Cal Trans Property
14East Canyon StructureProject Cost Estimate
20,957,443 Per Space Estimated Cost 18,695
- Disadvantages with this option include
- EIR issues including protected species and
plants. - Encroachment on Cal Trans property and possibly
already mitigated land - Some of the parking in lot seven would be lost
and traffic issues may result from this structure
would need to be studied. - Aesthetic Issues of having a parking structure be
located at the front entrance of campus. - Security issues on a multistoried lot with
minimal view corridors. - Advantages with this option include
- Minimal loss of existing student parking during
construction - Over 1,100 new spaces created, more than any
other design. - Cost per space is lowest of all parking
structures. - Ability to possibly add signage or lettering that
could be seen from SR. 125. - Ability to utilize untapped, already owned campus
property.
15FOOTBALL FIELD Upper Level
16FOOTBALL FIELD Ground Level
17Football Field StructureProject Cost Estimate
24,941,512 Per Space Estimated Cost 28,570
- Disadvantages with this option include
- Loss of classes and athletics during construction
time estimated at 12 -18 months. - Traffic flow conflicts with student traffic
having to turn left across the perimeter road to
exit the structure. - The football field is an old canyon fill some
areas are 100 ft. deep. Much of this will need
to be re-compacted if this was the option
selected. - Mitigation required not yet determined
- Would probably require pedestrian bridge to
central campus from location. - Advantages with this option include
- Provide the utilities for future stadium
location. - Close walking distance to central campus
- Replace both the track and football field
surfaces. - Probable requirement to install accessible
pedestrian ramp to field area from the 400
Buildings.
18PARKING STRUCTURE Lot 5
- Net 756 Spaces Gained
- Gross 1400 Overall Spaces Built
19Parking Lot 5 StructureProject Cost Estimate
22,396,310 Per Space Estimated Cost 29,625
- Disadvantages with this option include
- Loss of 1000 student and staff parking spaces
during construction. - High per space and project cost due to having to
build on existing parking, so we do not gain any
additional parking on ground floor, and cost
estimate does not include resurfacing parking lot
5. - Advantages with this option include
- Already have construction plans ready and have
spent 750,000 to date on this project. - No additional EIR work required. Project could
be built quickly upon approval. - Close walking distance to central campus.
- Would rebuild part of the existing parking lot 5
surface parking under the structure footprint so
gross yield is 1,397 - Provides additional accessible route to central
campus.
20Request From Planning Budget Council on 9/29/05
- The Facilities Committee is to provide a
recommended Prop R funding plan for each of the
options listed below , and make a recommendation
on the preferred option. Each of these options
would require cuts to other proposed projects - East Canyon Parking Structure
- North Property Parking Lot, Both Options
- Soccer Field Parking Structure
- Parking Lot 5 parking structure
-
21College Meetings Held to Work On Funding Plan
- 10/4/05 - Facilities Committee meeting to work
on alternate funding plans - 10/13/05 Facilities Committee meeting to work
on alternate funding plans - 10/19/05 - Facilities Committee meeting to work
on alternate funding plans - 10/26/05 Facilities Committee meeting to work
on alternate funding plans - 11/1/05 Facilities Committee meeting to
finalize alternate funding plan
recommendations - 11/3/05 - Planning and Budget meeting to
discuss Facilities Committee recommendation
to move forward with East Canyon North
Property parking options
22Facilities Committee Recommendation Supported by
Planning Budget Council on 11/03/05
- After reviewing all of the impacts and funding
plans of each proposed parking solution the
following recommendation was approved by PBC. - Recommend to proceed with North Property Option,
with time and dollar restrictions. - Recommend East Canyon Structure if North Property
options are not feasible due to cost, time delay,
or environmental constraints
23Re-evaluation of the Lot 5 and East Canyon
Structure Cost Estimates
- Updated cost information was requested for the
following reasons. - Construction escalation had slowed
- East Canyon parking structure cost estimate
appeared low. - The district had current information from
Cuyamaca on retaining wall costs that could be
used for the east Canyon structure. - Needed to include updated construction timelines
in evaluation.
24East Canyon Updated Information
- Design time of 26 months
- Construction time of 20 months
- Parking loss
- New estimated costs of 32 million
25Parking Lot 5 Updated Information
- No design time, design is completed
- Phase 1construction time 3 months
- Phase 2 Construction time 9 months
- Parking loss of 800 spaces for 9 months
- New estimated costs of 21 million
26Cost ComparisonIncluding Soft Costs
27Planning Budget CouncilChange structure
recommendation
- On August 31, 2006, The Planning Budget Council
agrees with the Facilities Committee to remove
East Canyon Structure from consideration. - The North Property and Parking Lot 5 Structure
are forwarded as the college recommended parking
options - It is agreed that if the North Property
negotiations do not progress, the college would
move forward with the Parking Lot 5 Structure.
28Resulting in a move to address our Parking
shortage by constructing a parking structure in
parking lot 5
- Environmental constraints including vernal pools
have eliminated our ability to purchase and
build parking to the north of the district
29PHASE IConstruction Time 10/07 thru
12/07Estimated Parking Loss 400
SpacesEstimated Parking Available 600 Spaces
- PHASE II
- Construction Time 3/08 thru 12/08
- Parking Loss Approx. 812 Spaces
- Parking Available Approx 218 spaces
30Parking Lot 5 Upon Completion
- At Completion, parking lot 5 will contain 1861
total parking spaces - A new Public Safety Building
- Upgraded accessibility to the center of campus
- Completely upgraded surrounding surface parking
- Upgraded landscaping