Title: Timedependent Stability Implications for Two Seam Mining OCI
1Old Mines - New Regulations The Re-opening of the
Gordonsville, Elmwood, and Cumberland Mines Under
New DPM Regulations
12th U.S./North American Mine Ventilation
Symposium June 9-11, 2008 Reno, Nevada
USA Presented by Albert Adu-Acheampong Susan
Patton
AGAPITO ASSOCIATES, INC.
Mining Civil Engineers Geologists
2Presentation Outline
- Site Overview and Background
- Previous Work by Agapito Associates, Inc. (AAI)
- Future Mining Plans
- Basis for the Analysis
- Ventilation System Design
- Recommendations
- Startup Issues
3Site Overview
72 km (45 miles) East of Nashville
4Site Overview and Background
- The Gordonsville, Elmwood (GV/E) and Cumberland
Mines were formerly owned by Pasminco - The mines were last operated in 2003 and were
decommissioned - Currently owned by Strategic Resource Acquisition
(SRA) and operated by Dynatec. - The mines utilize a random room-and-pillar mining
method to extract zinc underground
5Previous Work by AAI
- Pressure/quantity survey in 1996 for Savage Zinc,
Inc. - Developed and validated a computer network model
for the mine
6Layout of the GV/E and Cumberland Complex
7Future MinePlans
8Basis for the Analysis
- 1996 pressure/quantity survey data
- Site Visit
- Information Received from Client
- Equipment selection table with utilization
- Production sequence with mine map
- Power cost
- Ventilation System Constraints
- Fans limited to less than 300 BHP
- Decline on intake air
- Plans to bore two new 3.7m (12 ft) diameter vent
raises
9Ventilation System Design Quantity Estimation
- DPM
- New DPM exposure limit of 160TC µg/m3
- Equipment approved by MSHA has a nameplate with
two pieces of information - (a) Particulate Index (PI)Dilution air required
to reduce the exhaust total DPM concentration to
1000 µg/m3 (total carbon content 80) - (b) gaseous ventilation rate
10Ventilation System Design Quantity Estimation
- DPM
- Sum of PI for the equipment specified for
GV/E115.89 m3/s (245,550 cfm) - Sum of PI for the equipment specified for the
Cumberland Mine11.7 m3/s (23,650 cfm) - By ratio (800?PI/Exposure Limit) equates to
total volume of air required of 613.53 m3/s (1.3
million cfm) and 58.5 m3/s (118,250 cfm)
11Ventilation System Design Analysis and Results
- Based on the quantity required
- Eight scenarios were analyzed for the GV/E Mine
Complex - The GV/E Mine Complex required 5 intakes and 7
exhausts
12Ventilation System Design Analysis and Results
- Based on the quantity required
- Three scenarios were analyzed for the Cumberland
Mine - The Cumberland Mine required 2 intakes and 2
exhausts
13Ventilation System Design Recommendations
- Startup settings
- Continued monitoring
- Practice contaminant monitoring
- Ventilation surveys recommended to correlate
models
14Mine Ventilation Startup Issues
- Auxiliary system capacity
- Existing raises
- Managing equipment locations to limit exposures
- Rehabilitating shafts and raises
- Dewatering
15Acknowledgements
- The authors would like to thank SRA
- and Dynatec for initiating this project
16Questions ???
Albert Adu-Acheampong 715 Horizon Dr. Ste
340 Grand Junction, CO 81504 Tel 970
254-9392 Email aaadu_at_agapito.com