Title: Current Module LT Testing Capability
1Current Module LT Testing Capability
- Only Vienna Boxes Available
- 10 slots at each site
- 75 efficiency of running time
- Will estimate the amount of time run per module
with - 50,100 module tested at each site
- 1 month, 2 months, 4 months run periods
- Will assume 1 week at end to pull together
results and 1 week lost to produce modules,
procure test module components, etc.
2Current Time Estimates
Time 1 Month 2 Months 4 Months
50 Modules 2 ½ Days 7 Days 16 Days
100 Modules 1 ¼ Days 3 ¼ Days 8 Days
Modules Per Site
- To run 100 modules for week each will need
either - Both sites running for 2 months
- 1 running for 4 months
- Any production beyond the 100 modules mentioned
disrupts this test significantly - Any new modules would have to be put into Vienna
box for testing as rods will not be available at
rates to burn-in on rods - Thus, more modules could be run, but for less
time - Even more time lost to loading/etc.
- How long do we want to run the modules?
3Way To Increase Modules Run
- Run modules on rods in rod burn-in box
- To get statistics needed (100 modules), use 16
single sided rods - Use of DS rods will not increase statistics DAQ
hardware max-ed out at 8 SS4 rods - Two fully equipped/functional rod burn-in boxes
- Or multiple runs with smaller number of rods
- Calculate time run assuming
- 2, 4, or 8 rods per box
- DAQ components for 2 rod running should be
available at end of December - 4, 5, or 6 month periods from today
- Assume 3 months to commission system to point
that it is safe enough to run unattended and
assemble 16 rods - Assume 75 efficiency once stable
- Very aggressive, assumes that software and
hardware works almost immediately and that system
scales from 1 to 8 rods with no major problems - 10 more cabled rods available late Jan./early
Feb. - Assume 2 weeks total to pull together results
after run - THIS SCHEDULE IS EXTREMELY AGGRESSIVE AND HAS
NEVER HISTORICALLY OCCURRED IN SIMILAR SITUATIONS
4Rod Burn-in Time Estimates
Time 4 Months 5 Months 6 Months
2 Rods 3 Days 8.5 Days 14 Days
4 Rods 6 Days 17 Days 28 Days
8 Rods 12 Days 34 Days 56 Days
Rods Per Cycle
- To get more significant running time per module
(2 weeks) - Need 6 months with 2 rod per cycle capability
- Need 5 months with 4 rod per cycle capability
- Need 4 months with 8 rod per cycle capability
- If a month per module is preferred, need 4-8 rod
per cycle capability in order to finish test in
time period given - Would take significant manpower, hardware
increases, and software and data analysis
development - Takes resources from other commitments TOB/TEC
hybrid PA wire bonding/testing, starting TEC
module production, ramp up of TOB module
production, finalization of module LT setups
5Difficulties in Rod Burn-in (Hardware)
- Assumes equipment/hardware we do not have yet
- 12 assembled rods
- PS cables
- 2 rods per cycle still need
- 2 Delphi LV PS
- 2 OFED (2 OEC each)
- 2 oMUX crates with 3 oMUX each
- 4 rods per cycle still need
- 6 Delphi LV PS
- 4 OFED (2 OEC each)
- 2 oMUX crates with 5 oMUX each
- 8 rods per cycle still need
- 14 Delphi LV PS
- 8 OFED (2 OEC each)
- 4 oMUX crates with 5 oMUX each
- Recent/imminent deliveries of
- All oMUX
- All OFED
- Parts and test equipment limit number of rods
usable - Assembled rods
- 10 more rods late Jan/early Feb
- Rest in late Feb
- Delphi LV PS
- 5 total for tracker in Dec.
- 5 total for tracker in Jan.
- 12 total for tracker at end of Feb.
- Rest in April
- To do significant number of rods would require
majority of Delphi LV PS built - May have to borrow existing supplies from
current sites
6Difficulties in Rod Burn-in (Software)
- Assumes software we do not have yet
- LT only shown to work on 1 rod
- May not be easily expandable to number of modules
needed (Multiple oMUX crates, memory, etc.) - May require significant fraction of Wims and
Valerys time - Single rod commissioning/ validation software not
developed yet - Do not have algorithms to do fault finding
- Software to monitor/find changes in module
response during module burn-in does not exist yet - Similar rod software would have to follow the
module software - Rod burn-in slow controls/interlocks have not
been commissioned with rods yet - Integration beginning as we speak
7Difficulties in Rod Burn-in (Manpower)
- The same personnel at UCSB/FNAL would have to be
used for - Testing/assembly of modules/rods for this study
- Begin TEC module construction/testing
- Begin TOB/TEC hybrid testing
- Construction/commissioning rod burn-in stand
- Development in stages due to lack of rods and
power supplies - The same personnel needed for software
development - Module LT analysis
- Rod commissioning
- Rod burn-in software
- Rod burn-in analysis
8Conclusions (1)
- The rod burn-in stands needed to run large number
of modules for a significant period of time - Such a program would require a commitment of a
large fraction of the resources needed for
sub-structure assembly/testing - (Almost) all the Delphi LV PS in community
- Large fraction of testing manpower at UCSB/FNAL
- Most of the software developers time
- This commitment will leave few resources for
other tasks - Hybrid/module production and testing
- TEC module production in US
- If everything delivered on schedule and works
perfectly, earliest we could get 100 modules run
for 1 month each would be April - This assumes 8 rod burn-in assemble and
commissioned at both sites starting late February - This assumes 4 complicated software packages will
developed and commissioned in the same time frame
9Conclusions (2)
- From historically similar situations
- It is not likely that all equipment needed will
arrive in the time needed - It is not likely that all the software needed
will be developed in time - From this experience I would assume that we could
run 100 modules for an one-month period by
June/July/Aug - I do not have enough information now to make a
more precise estimate - Each equipment piece (2 types) and software
package (4 types) can easily be delayed by a
month easily