Current Module LT Testing Capability - PowerPoint PPT Presentation

About This Presentation
Title:

Current Module LT Testing Capability

Description:

... immediately and that system scales from 1 to 8 rods with no major problems ... equipment piece (2 types) and software package (4 types) can easily be delayed ... – PowerPoint PPT presentation

Number of Views:10
Avg rating:3.0/5.0
Slides: 10
Provided by: joeinc
Category:

less

Transcript and Presenter's Notes

Title: Current Module LT Testing Capability


1
Current Module LT Testing Capability
  • Only Vienna Boxes Available
  • 10 slots at each site
  • 75 efficiency of running time
  • Will estimate the amount of time run per module
    with
  • 50,100 module tested at each site
  • 1 month, 2 months, 4 months run periods
  • Will assume 1 week at end to pull together
    results and 1 week lost to produce modules,
    procure test module components, etc.

2
Current Time Estimates
Time 1 Month 2 Months 4 Months
50 Modules 2 ½ Days 7 Days 16 Days
100 Modules 1 ¼ Days 3 ¼ Days 8 Days
Modules Per Site
  • To run 100 modules for week each will need
    either
  • Both sites running for 2 months
  • 1 running for 4 months
  • Any production beyond the 100 modules mentioned
    disrupts this test significantly
  • Any new modules would have to be put into Vienna
    box for testing as rods will not be available at
    rates to burn-in on rods
  • Thus, more modules could be run, but for less
    time
  • Even more time lost to loading/etc.
  • How long do we want to run the modules?

3
Way To Increase Modules Run
  • Run modules on rods in rod burn-in box
  • To get statistics needed (100 modules), use 16
    single sided rods
  • Use of DS rods will not increase statistics DAQ
    hardware max-ed out at 8 SS4 rods
  • Two fully equipped/functional rod burn-in boxes
  • Or multiple runs with smaller number of rods
  • Calculate time run assuming
  • 2, 4, or 8 rods per box
  • DAQ components for 2 rod running should be
    available at end of December
  • 4, 5, or 6 month periods from today
  • Assume 3 months to commission system to point
    that it is safe enough to run unattended and
    assemble 16 rods
  • Assume 75 efficiency once stable
  • Very aggressive, assumes that software and
    hardware works almost immediately and that system
    scales from 1 to 8 rods with no major problems
  • 10 more cabled rods available late Jan./early
    Feb.
  • Assume 2 weeks total to pull together results
    after run
  • THIS SCHEDULE IS EXTREMELY AGGRESSIVE AND HAS
    NEVER HISTORICALLY OCCURRED IN SIMILAR SITUATIONS

4
Rod Burn-in Time Estimates
Time 4 Months 5 Months 6 Months
2 Rods 3 Days 8.5 Days 14 Days
4 Rods 6 Days 17 Days 28 Days
8 Rods 12 Days 34 Days 56 Days
Rods Per Cycle
  • To get more significant running time per module
    (2 weeks)
  • Need 6 months with 2 rod per cycle capability
  • Need 5 months with 4 rod per cycle capability
  • Need 4 months with 8 rod per cycle capability
  • If a month per module is preferred, need 4-8 rod
    per cycle capability in order to finish test in
    time period given
  • Would take significant manpower, hardware
    increases, and software and data analysis
    development
  • Takes resources from other commitments TOB/TEC
    hybrid PA wire bonding/testing, starting TEC
    module production, ramp up of TOB module
    production, finalization of module LT setups

5
Difficulties in Rod Burn-in (Hardware)
  • Assumes equipment/hardware we do not have yet
  • 12 assembled rods
  • PS cables
  • 2 rods per cycle still need
  • 2 Delphi LV PS
  • 2 OFED (2 OEC each)
  • 2 oMUX crates with 3 oMUX each
  • 4 rods per cycle still need
  • 6 Delphi LV PS
  • 4 OFED (2 OEC each)
  • 2 oMUX crates with 5 oMUX each
  • 8 rods per cycle still need
  • 14 Delphi LV PS
  • 8 OFED (2 OEC each)
  • 4 oMUX crates with 5 oMUX each
  • Recent/imminent deliveries of
  • All oMUX
  • All OFED
  • Parts and test equipment limit number of rods
    usable
  • Assembled rods
  • 10 more rods late Jan/early Feb
  • Rest in late Feb
  • Delphi LV PS
  • 5 total for tracker in Dec.
  • 5 total for tracker in Jan.
  • 12 total for tracker at end of Feb.
  • Rest in April
  • To do significant number of rods would require
    majority of Delphi LV PS built
  • May have to borrow existing supplies from
    current sites

6
Difficulties in Rod Burn-in (Software)
  • Assumes software we do not have yet
  • LT only shown to work on 1 rod
  • May not be easily expandable to number of modules
    needed (Multiple oMUX crates, memory, etc.)
  • May require significant fraction of Wims and
    Valerys time
  • Single rod commissioning/ validation software not
    developed yet
  • Do not have algorithms to do fault finding
  • Software to monitor/find changes in module
    response during module burn-in does not exist yet
  • Similar rod software would have to follow the
    module software
  • Rod burn-in slow controls/interlocks have not
    been commissioned with rods yet
  • Integration beginning as we speak

7
Difficulties in Rod Burn-in (Manpower)
  • The same personnel at UCSB/FNAL would have to be
    used for
  • Testing/assembly of modules/rods for this study
  • Begin TEC module construction/testing
  • Begin TOB/TEC hybrid testing
  • Construction/commissioning rod burn-in stand
  • Development in stages due to lack of rods and
    power supplies
  • The same personnel needed for software
    development
  • Module LT analysis
  • Rod commissioning
  • Rod burn-in software
  • Rod burn-in analysis

8
Conclusions (1)
  • The rod burn-in stands needed to run large number
    of modules for a significant period of time
  • Such a program would require a commitment of a
    large fraction of the resources needed for
    sub-structure assembly/testing
  • (Almost) all the Delphi LV PS in community
  • Large fraction of testing manpower at UCSB/FNAL
  • Most of the software developers time
  • This commitment will leave few resources for
    other tasks
  • Hybrid/module production and testing
  • TEC module production in US
  • If everything delivered on schedule and works
    perfectly, earliest we could get 100 modules run
    for 1 month each would be April
  • This assumes 8 rod burn-in assemble and
    commissioned at both sites starting late February
  • This assumes 4 complicated software packages will
    developed and commissioned in the same time frame

9
Conclusions (2)
  • From historically similar situations
  • It is not likely that all equipment needed will
    arrive in the time needed
  • It is not likely that all the software needed
    will be developed in time
  • From this experience I would assume that we could
    run 100 modules for an one-month period by
    June/July/Aug
  • I do not have enough information now to make a
    more precise estimate
  • Each equipment piece (2 types) and software
    package (4 types) can easily be delayed by a
    month easily
Write a Comment
User Comments (0)
About PowerShow.com