Title: Status report on Brick: Controller, Mechanics, Power Consumption
1Status report on Brick Controller, Mechanics,
Power Consumption
- Work done by
- Marco Incagli, Franco Spinella, Marco Piendibene
- Electronics meeting 7/8 feb 2005
2PART 1 the new HV controller board
3New HV controller round 1
- New HV controller received in Pisa Oct, 25 2004
- To test it, an interface board (made by CAEN),
that sends the equivalent of LeCroy commands, is
used - First tests on analog part
- HOT part OK
- COLD part not working
- Controller back at CAEN where the problem on COLD
part was solved - Shorts due to some residual soldering material
4New HV controller round 2
- Back in Pisa on Nov 15
- After few tests the controller stops working
- CAEN engineers come to Pisa and find a chip that
was exploded presumably a wrong alimentation
problem (our fault) - Controller back at CAEN where the chip is
replaced - At the same time, the maximum possible voltage is
moved from 1000V to 900V (900/1024 steps) - Controller in pisa end of November all
regulators work fine
5New HV controller round 3
- Controller at CERN 9-10 December tests with A.L.
V.K. using JINFV2 and tracker backplane - JINFV2 does not correctly talk with HV controller
- Try to reproduce the problem in Pisa and then
study the problem together with CAEN engineers - For this we need the ECAL backplane
- The EBP arrives in Pisa end of december
6New HV controller round 4
Setting voltages with A.L. program
- The system with EPPCANEBPJINF2EHV is mounted
and tested - Software from Lebedev, re-written by M.I.
Keithley readout (20channels)
EPPCAN interface
7New HV controller round 4
JINF
New EHV controller
10 PMTs
Data cable
8New HV controller round 4
- CAEN engineers come to Pisa and identify the
problem in the ACTEL code (their fault) ?
synchronization ? see talk of Spinella - Controller back to CAEN, ACTEL chips (AB)
unsoldered - Only one is mounted back in order to have another
possible test on the same board for an eventual
re-programming
9New HV controller round 5
- Controller with new ACTEL in Pisa Jan, 24
- Communication problem carefully tested
- With correct commands, the Brick always responds
correctly (intensively tested sending million of
commands and checking the answer) - With pathological commands, the controller stops
working, until a software reset (64 NULL commands
in a row) is issued ? possible critical point
10New HV controller current situation
- HV controller is currently winning, but we have a
few more rounds to go - Brick tests scheduled for 9/10 feb at CERN with
A.L.V.K. - If CAEN has the green light, and no reprogramming
(and retesting!) is needed, they can put the
second ACTEL on board in two working days - Once both ACTELs are onboard, we can make other
tests, like swithcing on both A and B sections
and sending commands on both lines, while waiting
for the mechanics
11PART 2 power consumption
12Brick power consumption
- Current drawn with only 1 section operative (A or
B) and all PMTs at 800 V (at t0 normal voltage
is 700V, but it may increase with time) - 3.3V ? 0.09A 5.0V ? 0.09A 28V ? 0.32A
- Ptot 3.30.09 50.09 280.32 9.8 W
- In worst case scenario (no commands arrive at
EHV) both sections are on and elevators set to
maximum voltage (reference voltage and transient
time tbd) - 3.3V ? 0.15A 5.0V ? 0.2A 28V ? 0.45A
- Ptot 3.30.15 50.2 280.45 14.1 W
13Power drop at EHV and at PMT level
- We have measured the current drawn by a PMT set
at 800 V . The total output power (drop at PMT
level) is - Pout 800V 0.160mA 55 7W
- Therefore the power drop at EHV level is
- Pdrop Ptot Pout 9.8W 7W 2.8W in
standard conditions - Pdrop Ptot Pout 14.1W 7W 7.1W in worst
case scenario
14PART 3 mechanics and SQ tests
15Mechanics and SQ tests
- Mechanics is the same for all bricks
(TOFRICHECAL) - IAC institute, in Canarie islands, will build the
mechanics for EHV (thanks to Berdugo who is
following the job) - The first prototype, to be used for EHV QM tests,
will be done by in Pisa CIEMAT, Madrid - SQ tests, vibrationEMI(TVT), can be done in
Terni ? mechanical fixtures must be built.
Necessary before ordering FM, which take 8 months
to build!