Title: Central Fiber Tracker Status


1
Central Fiber Tracker Status
  • 8 layers
  • Outer 6
  • 2.52 m
  • Inner 2
  • 1.66 m
  • r - .2 to .51 m
  • Axial readout to south
  • VLPC Readout
  • Waveguide system
  • 8-11.5 m
  • Pipes light from detector to VLPCs

2
CFT Status - Tracker Mechanical
Complete
Global precision 33 mm (Measured vs Desired)
3
CFT Status - Tracker Mechanical
  • Residual Stereo angle on axial layers was always
    a concern
  • 4 mil end-end offset was spec -Trigger constraint

4
CFT Status - Tracker Mechanical
5
CFT Status - Waveguides
  • Waveguide Production
  • CPS complete (IU)
  • Fiber pulling/sheathing at ND 75 complete for
    CFT
  • Fiber sorted
  • Best (attn.L from Kuraray) - longest runs
    8-11.5m
  • FPS at IU
  • CFT WG Connectorization
  • At ND Fermilab IU
  • Expect to complete production in August

6
CFT Status - Waveguides
7
CFT Status - Waveguide Routing
  • Routing, strain relief, etc for CFT (CPS) design
    complete and most parts fabricated

8
CFT Status - Readout System
  • VLPC Characterization/test/sort now complete
  • Cassette Assignment
  • As shown

9
CFT Status - Readout System II
  • Cassette production
  • Approximately 60-75 of sub-component complete
  • 14 production cassettes complete
  • All components in-house except Flex circuit
  • Flex Circuit
  • Production deliveries going well
  • 850 of 2000 in hand
  • 100/week

10
CFT Status - Readout III
  • Cassette Test - Going Well
  • Noise low
  • Good uniformity

11
CFT Status - Cassette Production
12
CFT Status - Cryo
  • Fabrication delayed by delivery of top plates
  • Now in house
  • To spec
  • Making up some time
  • Welding going well
  • Final Cryo Operational in June

13
CFT Status - Electronics
  • Analog Front-End (AFE) Board
  • SIFT
  • Trigger pickoff
  • SVX
  • Shares much with Silicon
  • Sequencer
  • L3 VRB
  • Etc.
  • Mixing Box
  • Reorders optical signals into trigger towers
  • Digital Front-End (DFE) Board

14
CFT Status - Electronics
  • Analog Front End Board
  • Pre-Production prototype under test
  • First production boards available in mid-August
  • Production 9/00-10/00
  • Mixer Box
  • Test prototype 8/00
  • Production 10/00 - 12/00
  • Digital Front End
  • Mother Board and Daughter board prototype testing
    complete
  • Tracking at 50 MHz
  • Production has started
  • First 10 mother boards here
  • First daughter boards due in two weeks
  • 8/00 - 10/00

15
CFT Status - Commissioning
  • Commissioning has already started
  • Lab 3 Cosmic Ray Test Stand
  • Using both sequencer-L3 and stand-alone-sequencer
  • Not using AFE boards
  • Stereo Boards - SVX readout only, no MCM - no
    SIFT
  • DAB commissioning
  • Waveguide installation starts
  • Plan to use SB
  • IF prototype AFEs available will go with them
  • Should have over 50 cassettes available
  • Full commissioning will be driven by delivery of
    production quantities of AFE Board
  • L1 trigger test to follow

127 cm
16
CFT Status
17
CFT Status - Schedule
  • At lab 3 we currently are
  • Installing silicon support structures
  • CFT alignment fixtures (VSTAR targets for use at
    DAB)
  • Final optical connector inspection
  • Light and gas tighting
  • Should be ready to move to DAB on or about June
    16, 2000
  • Waveguide installation starts mid-August
  • Waveguide fabrication should be essentially
    complete at this time
  • Commissioning starts at this time

18
CFT Status - Conclusions
  • CFT Mechanical construction is complete
  • Mechanical assembly is to specification
  • Move to DAB June 16, 2000
  • VLPC Cryo
  • VLPC characterization/selection complete
  • 1024 channel cassettes working well
  • Cassette production assembly underway
  • Subcomponents 75 complete
  • First 14 production cassettes assembled
  • CFT Waveguide production
  • Fiber pulling/sheathing going well
  • Complete in mid-August
  • Commissioning starts with waveguide installation
  • 7.8M final cost
  • Completed at Lehman 98 Baseline with No
    Contingency