Target Status Report - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Target Status Report

Description:

Lara Howlett University of Sheffield. MICE UK, July 2005. Contents. A look at the specs ... Lara Howlett University of Sheffield. MICE UK, July 2005 ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 20
Provided by: lara168
Category:
Tags: lara | report | status | target

less

Transcript and Presenter's Notes

Title: Target Status Report


1
Target Status Report
  • Lara Howlett
  • University of Sheffield

2
Contents
  • A look at the specs
  • Reminder of Prototype plans
  • Meetings with ISIS engineers
  • Testbeam plans
  • Readout and radiation studies
  • Plans / Timescale

3
Updated Specs
  • Frequency 1-3 Hz. Higher may be possible but we
    may be limited by heating
  • Target will dip into the beam by 5-10mm
  • Only the intersection of the beam in the last 1ms
    is useful
  • We wish to intersect as little beam that is not
    useful as possible

4
Updated Specs
2.05ms
4.4mm
5
Updated Specs
2.75ms
7.4mm
6
Updated specs
3.35ms
9.8mm
7
Overview of Prototype
  • The prototype is currently being built and is
    expected to be ready by the end of the month
  • The design consists of a a magnetic shuttle to
    which the target rod is attached
  • This sits inside a series of coils which are
    driven in 3 phase

8
Prototype
8 cm
9
Target Mechanism
10
Meetings with ISIS
  • Several very useful meetings have taken place
    with engineers from ISIS
  • These have been very useful for beginning to look
    at
  • Safety issues
  • Vacuum issues
  • How the target mechanism will be mounted
  • A first set of engineering drawings have also
    been produced by Stephanie Yang

11
Radiation Studies
  • Simulations of radiation levels have continued
  • These now include the geometry of the target
    mechanism
  • Radiation levels in the magnet are extremely high

12
Radiation studies
Units Grays/year/ Unit Density
13
Status of Readout
  • Problems with the readout board were experienced
    which caused jumps in the counts which were read
    out
  • After long correspondance with the company who
    provided the board, and returning the board for
    tests twice the problem has been resolved
  • The readout system will therefore be ready to be
    used with the new prototype when it arrives
  • Sheffield has a summer student who will be
    working on this in the coming months
  • We are looking into the possibility of replacing
    the inductive measurement system with an optical
    system

14
Test Beam Plans
  • There are plans to have the prototype ready for a
    test operation by December
  • This would involve intersecting a few ISIS beam
    pulses when the machine starts up in January
  • Measurements from the scintillators of the
    Glasgow group will hopefully allow us to gain a
    better understanding of how far into the beam we
    need to go and how the beam profile changes with
    distance

15
Backup plans
  • In parallel with the work described two backup
    plans are being investigated in the background
  • The use of a lever to move the actuator away from
    the target
  • The use of a cam to provide the motion

16
Lever
  • Despite the hope that a lever would provide a
    mechanical advantage discussions with an engineer
    indicate that because of the low mass of the
    shuttle this is not possible
  • However the use of a lever would give the
    advantage of moving the electronics and magnets
    away from the radiation if this is necessary
  • The other advantage of this arrangement is that
    the target mechanism is isolated from the ISIS
    vacuum eliminating any possible problems of
    contamination

17
Cam
  • The idea of a cam has also been investigated in
    the background so that in the instance that the
    em design does not produce the accelerations
    required a backup plan is in place. This would be
    used in conjunction with a lever

18
Plans
  • Upcoming milestones
  • Prototype should be assembled and ready for tests
    to begin mid July
  • Prototype should be sufficiently tested to put in
    the beam by Christmas
  • Data from beam tests should be used as input for
    final design

19
Conclusions
  • Work towards the prototype is progressing and we
    expect to start tests in the coming weeks
  • Several successful meetings with ISIS engineers
    have taken place and these have been extremely
    useful in progressing with the design
  • Exactly how far we need to go into the beam has
    significant implications for the design, so we
    should pin this number down as much as we can
Write a Comment
User Comments (0)
About PowerShow.com